FDOT contract T7566 bid tabulation
SR 595 (ALT US 19 / BAYSHORE DR) FROM WILSON ST TO CURLEW ST. Let by Florida DOT on September 24, 2025, Pinellas, District 7. 6 bids received; low bid $1,275,290 by Burgess Civil, LLC.
- Owner
- Florida DOT
- Letting
- 24 SEP 2025
- Pay items
- 74
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Burgess Civil, LLC | $1,275,290 | Low |
| 2 | Kamminga & Roodvoets, Inc. | $1,349,347 | +6.0% |
| 3 | Blacktip Services Incorporated | $1,399,047 | +10% |
| 4 | Preferred Materials Inc. | $1,418,057 | +11% |
| 5 | American Design Engineering Construction Inc. | $1,445,604 | +13% |
| 6 | Ajax Paving Industries of Florida LLC | $1,903,560 | +49% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Burgess Civil, LLC | 2. Kamminga & Roodvoets, Inc. | 3. Blacktip Services Incorporated | 4. Preferred Materials Inc. | 5. American Design Engineering Construction Inc. | 6. Ajax Paving Industries of Florida LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $120,000 | $242,000 | $134,000 | $204,000 | $165,000 | $230,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $80,000 | $73,000 | $25,000 | $139,900 | $65,000 | $392,000 |
| 0015 | Pedestrian escort/flagger (0102-5) | HR | 240 | $31.60 | $27.00 | $100.00 | $16.18 | $30.00 | $1.09 |
| 0020 | Traffic control officer (0102-14) | HR | 196 | $65.00 | $69.00 | $85.00 | $92.36 | $95.00 | $120.37 |
| 0025 | Work zone sign (0102-60) | ED | 2,616 | $0.21 | $0.21 | $0.30 | $0.24 | $3.00 | $0.23 |
| 0030 | Business sign (0102-61) | EACH | 1 | $45.00 | $45.00 | $55.00 | $51.95 | $2,500.00 | $49.24 |
| 0035 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 27,230 | $0.08 | $0.08 | $0.15 | $0.09 | $3.00 | $0.09 |
| 0040 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 3,000 | $0.08 | $0.08 | $0.15 | $0.09 | $3.00 | $0.09 |
| 0045 | Arrow board / advance warning arrow panel (0102-76) | ED | 84 | $5.00 | $5.00 | $7.00 | $5.77 | $35.00 | $5.47 |
| 0050 | Portable changeable message sign, temporary (0102-99) | ED | 314 | $9.00 | $9.00 | $12.00 | $10.39 | $35.00 | $9.85 |
| 0055 | Temporary signalization and maintenance, intersection (0102-104) | ED | 160 | $22.71 | $75.00 | $35.00 | $86.59 | $150.00 | $18.60 |
| 0060 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 160 | $22.71 | $55.00 | $35.00 | $63.50 | $150.00 | $40.49 |
| 0065 | Existing ITS maintenance (0102-112) | DA | 160 | $26.65 | $95.00 | $73.00 | $109.68 | $150.00 | $361.10 |
| 0070 | Sediment barrier (0104-10-3) | LF | 3,722 | $0.91 | $6.00 | $6.00 | $2.89 | $4.00 | $8.00 |
| 0075 | Soil tracking prevention device (0104-15) | EACH | 3 | $2,159.69 | $1,200.00 | $750.00 | $6,460.48 | $4,500.00 | $7,445.84 |
| 0080 | Inlet protection system (0104-18) | EACH | 16 | $171.18 | $250.00 | $50.00 | $207.15 | $156.00 | $242.49 |
| 0085 | Litter removal (0107-1) | ACRE | 1.89 | $451.49 | $200.00 | $100.00 | $1,154.48 | $100.00 | $824.23 |
| 0090 | Mowing (0107-2) | ACRE | 0.15 | $456.27 | $300.00 | $100.00 | $7,504.13 | $100.00 | $10,385 |
| 0095 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $160,000 | $145,500 | $108,000 | $101,562 | $8,500.00 | $59,558 |
| 0100 | Selective clearing and areas with trees to remain (0110-2-2) | ACRE | 0.31 | $88,350 | $75,000 | $28,000 | $7,561.16 | $8,500.00 | $64,851 |
| 0105 | Removal of existing concrete (0110-4-10) | SY | 308 | $22.60 | $28.00 | $75.00 | $53.03 | $15.00 | $107.54 |
| 0110 | Tree removal (0110-23) | EACH | 1 | $500.00 | $800.00 | $2,500.00 | $740.92 | $750.00 | $2,438.55 |
| 0115 | Embankment (0120-6) | CY | 14.30 | $46.47 | $86.00 | $70.00 | $90.79 | $35.00 | $491.83 |
| 0120 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 8,802 | $3.32 | $3.50 | $9.00 | $4.88 | $8.00 | $7.90 |
| 0125 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 726.20 | $210.70 | $200.00 | $256.00 | $227.67 | $285.00 | $288.00 |
| 0130 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 3 | $8,311.95 | $6,000.00 | $13,000 | $10,424 | $18,000 | $10,228 |
| 0135 | Manhole, adjust, utilities (0425-5-1) | EACH | 3 | $487.02 | $1,200.00 | $1,000.00 | $2,166.79 | $2,200.00 | $50.00 |
| 0140 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 223 | $154.67 | $150.00 | $280.00 | $227.33 | $120.00 | $339.78 |
| 0145 | Concrete curb & gutter, type E (0520-1-7) | LF | 617 | $46.62 | $63.00 | $60.00 | $53.61 | $35.00 | $65.09 |
| 0150 | Concrete curb & gutter, type F (0520-1-10) | LF | 223 | $45.62 | $61.00 | $60.00 | $52.24 | $35.00 | $92.22 |
| 0155 | Concrete curb, type B (0520-2-2) | LF | 147 | $54.62 | $65.00 | $60.00 | $51.43 | $35.00 | $40.15 |
| 0160 | Concrete curb, type D (0520-2-4) | LF | 12 | $49.62 | $78.00 | $60.00 | $96.28 | $35.00 | $108.06 |
| 0165 | Traffic separator concrete- type I, 4' wide (0520-5-11) | LF | 422 | $110.00 | $96.00 | $80.00 | $66.22 | $120.00 | $73.05 |
| 0170 | Concrete traffic separator, special- variable width (0520-70) | SY | 120 | $120.00 | $196.00 | $120.00 | $145.51 | $125.00 | $173.50 |
| 0175 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 291 | $61.69 | $118.00 | $90.00 | $107.44 | $55.00 | $115.57 |
| 0180 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 218 | $81.69 | $136.00 | $100.00 | $160.35 | $65.00 | $166.88 |
| 0185 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 5 | $118.49 | $200.00 | $120.00 | $141.86 | $65.00 | $258.02 |
| 0190 | Pavers, architectural, remove existing and reinstall (0526-1101) | SY | 1 | $75.00 | $300.00 | $500.00 | $368.66 | $500.00 | $732.55 |
| 0195 | Detectable warnings (0527-2) | SF | 199 | $25.00 | $65.00 | $30.00 | $31.39 | $30.00 | $24.07 |
| 0200 | Performance turf, sod (0570-1-2) | SY | 1,533 | $8.05 | $16.00 | $8.00 | $9.48 | $8.00 | $11.63 |
| 0205 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 492 | $4.00 | $1.75 | $5.00 | $3.35 | $1.00 | $3.74 |
| 0210 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0215 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 28 | $600.00 | $450.00 | $690.00 | $634.96 | $400.00 | $601.84 |
| 0220 | Single column ground sign assembly, relocate (0700-1500) | EACH | 3 | $200.00 | $300.00 | $230.00 | $288.62 | $200.00 | $273.56 |
| 0225 | Single column ground sign assembly, remove (0700-1600) | EACH | 2 | $50.00 | $200.00 | $60.00 | $115.45 | $350.00 | $109.43 |
| 0230 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 1 | $400.00 | $450.00 | $460.00 | $288.62 | $650.00 | $273.56 |
| 0235 | Tubular marker, 36" yellow (0704-1-4) | EACH | 18 | $250.00 | $95.00 | $288.00 | $173.17 | $350.00 | $164.14 |
| 0240 | Raised pavement marker, type B (0706-1-3) | EACH | 407 | $5.00 | $10.00 | $6.00 | $4.62 | $4.00 | $5.17 |
| 0245 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 93 | $5.00 | $3.75 | $6.00 | $11.54 | $2.00 | $12.91 |
| 0250 | Painted pavement markings, surface (0710-90) | LS | 1 | $5,000.00 | $750.00 | $5,750.00 | $15,401 | $15,000 | $17,226 |
| 0255 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 964 | $6.00 | $4.00 | $7.00 | $3.59 | $10.00 | $4.02 |
| 0260 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 232 | $10.00 | $8.00 | $12.00 | $7.18 | $12.00 | $8.03 |
| 0265 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.11 | $4,716.98 | $5,800.00 | $5,750.00 | $2,404.81 | $3,500.00 | $2,851.22 |
| 0270 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 20 | $175.00 | $88.00 | $201.00 | $87.74 | $150.00 | $98.14 |
| 0275 | Thermoplastic, standard, arrow (0711-11170) | EACH | 18 | $75.00 | $58.00 | $86.00 | $61.19 | $150.00 | $68.44 |
| 0280 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 230 | $7.00 | $6.00 | $8.00 | $4.91 | $10.00 | $5.49 |
| 0285 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.07 | $4,929.58 | $5,810.00 | $5,750.00 | $2,513.24 | $3,500.00 | $2,851.22 |
| 0290 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 904 | $17.00 | $9.00 | $20.00 | $18.01 | $22.00 | $20.14 |
| 0295 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.87 | $6,943.48 | $5,810.00 | $8,050.00 | $6,709.46 | $6,500.00 | $7,565.80 |
| 0300 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.83 | $6,949.15 | $5,810.00 | $8,050.00 | $6,171.69 | $6,500.00 | $6,953.71 |
| 0305 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.03 | $1,571.43 | $5,810.00 | $2,530.00 | $1,110.71 | $3,500.00 | $1,739.40 |
| 0310 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 140 | $10.00 | $2.50 | $12.00 | $5.77 | $20.00 | $6.46 |
| 0315 | Conduit, furnish & install, open trench (0630-2-11) | LF | 38 | $29.64 | $11.00 | $12.00 | $12.70 | $25.00 | $24.07 |
| 0320 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 82 | $65.04 | $62.00 | $29.00 | $71.58 | $100.00 | $42.68 |
| 0325 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $9,988.95 | $3,750.00 | $6,860.00 | $4,329.28 | $15,500 | $1,750.80 |
| 0330 | Fiber optic cable locator (0633-6) | DA | 160 | $318.67 | $286.00 | $601.00 | $330.18 | $275.00 | $339.22 |
| 0335 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 4 | $1,215.32 | $975.00 | $784.00 | $1,125.62 | $2,650.00 | $1,510.07 |
| 0340 | Aluminum signals pole, (0646-1-11) | EACH | 2 | $2,660.92 | $1,796.00 | $3,044.00 | $2,073.44 | $1,850.00 | $3,282.76 |
| 0345 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 2 | $810.17 | $735.00 | $932.00 | $848.54 | $1,850.00 | $902.76 |
| 0350 | Midblock crosswalk: rec rapid flashing beacon, solar, sign assembly- single dir accessible detector (0654-2-27) | AS | 12 | $12,463 | $7,715.00 | $11,730 | $8,906.78 | $12,000 | $11,161 |
| 0355 | Midblock crosswalk: rec rapid flashing beacon, solar, sign assembly- back-back accessible detector (0654-2-28) | AS | 4 | $13,681 | $8,895.00 | $11,730 | $10,269 | $14,000 | $13,131 |
| 0360 | Loop assembly- F&I, type A (0660-2101) | AS | 2 | $2,378.92 | $1,175.00 | $2,750.00 | $1,356.51 | $2,500.00 | $2,079.08 |
| 0365 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 2 | $442.03 | $375.00 | $535.00 | $432.93 | $450.00 | $470.53 |
| 0370 | Traffic controller, modify (0671-2-40) | EACH | 1 | $7,870.49 | $4,750.00 | $3,327.00 | $5,483.76 | $6,000.00 | $612.78 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of September 24, 2025. Compiled by Mirage Metrics.