FDOT letting results, March 29, 2023
15 contracts let by Florida DOT on March 29, 2023, $246,737,655 in low bids, a median of 3 bidders per contract.
- Owner
- Florida DOT
- Contracts
- 15
- Low bids, total
- $246,737,655
- Data through
- 28 OCT 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| T4639 | CR 606 (OSLO RD) | District 4 | 7 | Halley Engineering Contractors, Inc. | $95,783,212 | $108,769,932 | +14% | FDOT |
| T1859 | SR 70 | District 1 | 3 | Watson Civil Construction, Inc. | $42,956,506 | $48,823,117 | +14% | FDOT |
| T4551 | LOXAHATCHEE RD | District 4 | 6 | Horizon Contractors, Inc. | $33,480,585 | $34,719,343 | +4.0% | FDOT |
| T2915 | SR 15 | District 2 | 3 | Duval Asphalt Products, Inc. | $11,703,806 | $12,790,467 | +9.0% | FDOT |
| T1855 | SR 70 | District 1 | 3 | Superior Asphalt, Inc. | $11,238,774 | $11,993,561 | +7.0% | FDOT |
| T3835 | SR 10 (US 90) | District 3 | 2 | Anderson Columbia Co., Inc. | $10,919,335 | $12,173,430 | +11% | FDOT |
| T6562 | SR 9 (SR 817) (NW 27 AVE) | District 6 | 3 | General Asphalt Company, LLC | $9,816,354 | $10,440,183 | +6.0% | FDOT |
| T3863 | SR 95 (US 29) (N PALAFOX ST) | District 3 | 3 | Roads, Inc. of NWF | $7,039,667 | $7,197,126 | +2.0% | FDOT |
| T3856 | SR 85 | District 3 | 2 | Anderson Columbia Co., Inc. | $6,737,296 | $7,864,610 | +17% | FDOT |
| T2912 | SR 20 (US 27) | District 2 | 1 | Anderson Columbia Co., Inc. | $5,713,250 | FDOT | ||
| T7506 | SR 93 (I-275) | District 7 | 4 | Hubbard Construction Company | $4,477,908 | $4,653,564 | +4.0% | FDOT |
| T4642 | SR 809 (MILITARY TRAIL) | District 4 | 1 | J.W. Cheatham, LLC | $2,584,711 | FDOT | ||
| T6572 | SR 852 (CO LINE RD) | District 6 | 7 | Ohla USA Inc | $2,360,100 | $2,597,873 | +10% | FDOT |
| T3825 | SR 8 (I-10) | District 3 | 2 | Collins Land Services, Inc | $1,398,733 | $1,411,837 | +1.0% | FDOT |
| T5785 | I-95 | District 5 | 4 | Chinchor Electric Inc. | $527,418 | $594,000 | +13% | FDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than FDOT received, the others did not match their published totals and are left out.