NJDOT contract 25122 bid tabulation

Route 295 Noise Barrier. Let by New Jersey DOT on August 26, 2025, Mercer, C1. 10 bids received; low bid $11,528,000 by PKF-Mark III, Inc..

Owner
New Jersey DOT
Letting
26 AUG 2025
Pay items
134
Data through
16 APR 2026

Bidders

RankBidderTotal bidAgainst the low bid
1PKF-Mark III, Inc.$11,528,000Low
2South State, Inc.$13,558,884+18%
3Iew Construction Group, Inc.$13,851,455+20%
4Ritacco Construction, Inc.$14,110,000+22%
5Joseph M. Sanzari, Inc.$14,201,909+23%
6Earle Asphalt Company$15,165,713+32%
7Anselmi & Decicco, Inc.$15,531,775+35%
8Black Rock Enterprises, LLC$15,964,488+38%
9Railroad Construction Company, Inc.$16,324,587+42%
10JPC Group, Inc.$17,111,247+48%
NJDOT contract 25122: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. PKF-Mark III, Inc.2. South State, Inc.3. Iew Construction Group, Inc.4. Ritacco Construction, Inc.5. Joseph M. Sanzari, Inc.6. Earle Asphalt Company
0001Performance bond and payment bond (151006M)DOL1$69,521$60,000$61,639$70,000$112,000$35,000
0002Pollution liability insurance (152015P)DOL1$10,000$1.00$0.01$20,000$13,000$0.01
0003Progress schedule (153003P)LS1$15,000$100.00$5,000.00$10,500$10,000$7,500.00
0004Progress schedule update (153005M)U3$1,000.00$500.00$500.00$2,000.00$500.00$1,000.00
0005Mobilization (154003P)LS1$778,991$1,350,000$865,000$2,116,000$1,050,560$2,201,431
0006Field office type F set UP (155018M)U1$28,393$40,000$38,411$20,000$45,000$40,000
0007Field office type F maintenance (155036M)MO15$3,923.00$5,000.00$4,986.03$2,500.00$3,500.00$4,750.00
0008Monument (157006M)U7$2,054.35$700.00$597.64$750.00$1,330.00$1,150.00
0009Heavy duty silt fence, orange (158009M)LF5,475$12.83$7.00$8.12$8.00$9.00$6.00
0010Heavy duty silt fence, black (158012M)LF9,389$12.83$7.00$8.08$9.00$7.00$6.00
0011Haybale (158015M)U100$149.17$30.00$35.11$20.00$34.00$1.00
0012Inlet filter type 2, 2' X 4' (158030M)U17$351.00$100.00$173.85$100.00$200.00$75.00
0013Inlet filter type 2, 4' X 4' (158033M)U40$342.97$150.00$182.97$150.00$292.00$125.00
0014Sediment control bag (158054M)SF100$74.07$30.00$62.52$15.00$16.00$0.01
0015Construction driveway (158060M)T38$427.94$150.00$80.79$90.00$250.00$205.00
0016Concrete washout system (158063P)LS1$32,750$10,000$25,538$10,500$8,160.00$2,500.00
0017Bioretention system (158068P)SY5,166$151.95$125.00$159.68$125.00$180.00$120.00
0018Oil only emergency spill kit, type 1 (158072M)U2$2,200.00$2,000.00$3,310.48$500.00$1,330.00$1,200.00
0019Erosion control sediment removal (158084M)CY2,000$1.00$0.01$5.00$1.00$121.00$0.01
0020Tree protection (158090P)LF2,970$6.25$20.00$6.77$4.00$12.00$0.01
0021Wood mats (158105M)SY300$100.00$10.00$139.51$100.00$273.00$80.00
0022Breakaway barricade (159003M)U15$167.93$1.00$0.01$20.00$180.00$0.01
0023Drum (159006M)U140$67.17$1.00$0.01$10.00$75.00$0.01
0024Traffic cone (159009M)U140$22.89$1.00$0.01$1.00$25.00$0.01
0025Construction signs (159012M)SF919$18.90$17.00$19.32$17.00$20.00$0.01
0026Construction barrier curb (159021P)LF7,700$39.92$100.00$72.08$50.00$90.00$45.00
0027Arrow board, 4' X 8' (159027M)U2$7,272.66$1,500.00$608.06$500.00$3,500.00$5,000.00
0028Portable variable message sign (159030M)U3$25,000$6,500.00$3,040.26$1,000.00$10,000$19,000
0029Temporary crash cushion, inertial barrier system, 16 modules (159060M)U5$2,975.00$5,000.00$11,052$3,000.00$15,000$8,500.00
0030Traffic control truck with mounted crash cushion (159108M)U5$35,406$100.00$608.05$2,000.00$20,000$25,000
0031Fuel price adjustment (160004M)DOL1$33,200$33,200$33,200$33,200$33,200$33,200
0032Asphalt price adjustment (160007M)DOL1$12,500$12,500$12,500$12,500$12,500$12,500
0033Steel price adjustment (160009M)DOL1$100.00$100.00$100.00$100.00$100.00$100.00
0034Final cleanup (161003P)LS1$9,581.91$100.00$25,000$10,500$25,000$20,000
0035Clearing site (201003P)LS1$145,000$150,000$134,374$150,000$150,000$150,000
0036Stripping (202003P)ACRE3$9,158.13$500.00$16,397$7,500.00$75,000$15,500
0037Excavation, test pit (202006M)CY50$195.97$300.00$938.13$100.00$750.00$250.00
0038Excavation, unclassified (202009P)CY27,061$50.00$50.00$98.18$45.00$50.00$50.00
0039Removal of pavement (202021P)SY1,478$29.21$10.00$45.10$75.00$40.00$15.00
0040Geogrid reinforcement (203043P)SY108$128.35$8.00$38.33$55.00$53.00$75.00
0041Subbase (301006P)CY454$59.75$75.00$129.67$150.00$100.00$125.00
0042Dense-graded aggregate base course, 6" thick (302036P)SY436$36.56$30.00$23.99$44.00$24.00$16.50
0043Dense-graded aggregate base course, 10" thick (302045P)SY1,042$60.68$40.00$39.92$46.00$25.00$19.00
0044Polymerized joint adhesive (401027M)LF4,168$1.00$1.00$1.14$2.00$1.00$0.01
0045Tack coat (401030M)GAL175$10.00$1.00$11.37$10.00$10.00$4.00
0046Prime coat (401036M)GAL560$10.00$1.00$1.14$0.10$14.00$0.01
0047Hot mix asphalt 12.5 M E surface course (401061M)T196$265.00$300.00$301.18$290.00$230.00$135.00
0048Hot mix asphalt 19 M E intermediate course (401091M)T350$225.00$260.00$255.72$270.00$190.00$140.00
0049Temporary sheeting (501003P)SF1,010$46.56$1.00$0.01$1.00$50.00$0.01
005015" reinforced concrete pipe (601122P)LF2,040$120.98$175.00$119.19$110.00$150.00$100.00
005118" reinforced concrete pipe (601124P)LF488$121.89$190.00$142.94$135.00$190.00$102.00
005224" reinforced concrete pipe (601128P)LF29$134.38$260.00$331.79$180.00$562.00$204.00
005315" reinforced concrete pipe, class V (601194P)LF400$127.47$200.00$127.55$230.00$158.00$105.00
005418" reinforced concrete pipe, class V (601196P)LF76$130.51$250.00$154.31$310.00$286.00$105.00
005515" reinforced concrete end section (601370M)U3$5,881.83$2,400.00$2,595.71$2,000.00$4,750.00$2,500.00
005624" reinforced concrete end section (601376M)U1$5,979.48$2,800.00$3,683.01$3,000.00$6,780.00$2,915.00
0057Subbase outlet drain (601404P)LF76$66.71$35.00$141.21$70.00$165.00$80.00
0058Underdrain, type F (601416P)LF1,735$73.62$60.00$62.27$60.00$5.00$55.50
0059Cleaning existing pipe, 12" to 24" diameter (601670M)LF1,012$12.00$8.00$13.88$10.00$18.00$14.50
0060Cleaning existing pipe, over 48" to 72" diameter (601674M)LF307$20.00$20.00$45.76$60.00$45.00$85.00
006116" ductile iron pipe (601680M)LF178$212.74$290.00$197.61$280.00$415.00$225.00
006224" ductile iron pipe (601682M)LF36$336.64$425.00$438.43$380.00$728.00$475.00
0063Concrete headwall (602006P)CY16$3,837.19$2,100.00$1,982.71$2,500.00$3,250.00$1,500.00
0064Inlet, type B (602012M)U7$8,598.67$6,800.00$7,261.68$8,000.00$6,790.00$4,820.00
0065Inlet, type E (602018M)U22$9,132.94$7,200.00$9,309.30$6,500.00$8,500.00$5,990.00
0066Inlet, type B-2 (602027M)U3$7,538.44$8,900.00$8,042.23$6,500.00$8,220.00$7,860.00
0067Manhole, 4' diameter (602054M)U8$8,300.31$8,700.00$10,055$5,000.00$7,620.00$6,200.00
0068Manhole, 5' diameter (602057M)U1$10,095$18,000$13,487$6,500.00$10,800$12,225
0069Inlet converted to manhole (602096M)U2$6,691.80$2,500.00$5,146.70$3,000.00$4,520.00$2,450.00
0070Reconstructed inlet, type B, using new casting (602153M)U2$7,505.58$2,800.00$5,000.77$3,000.00$4,000.00$2,450.00
0071Reconstructed inlet, type E, using new casting (602159M)U1$7,663.07$2,900.00$5,151.37$3,000.00$4,910.00$2,625.00
0072Reconstructed manhole, using new casting (602183M)U1$6,980.58$3,300.00$6,306.49$3,000.00$4,730.00$900.00
0073Cleaning drainage structure (602216M)U5$500.00$800.00$936.51$1,000.00$2,100.00$1,350.00
0074Outlet control structure (602223M)U4$11,745$10,000$11,405$12,500$13,170$13,000
0075Junction chamber (602226M)U4$11,745$16,000$14,456$11,500$11,540$15,000
0076Manufactured treatment device (602229M)U2$54,995$160,000$59,237$70,000$100,000$102,000
0077Riprap stone slope protection, 18" thick (D50=9") (603021P)SY111$180.06$100.00$321.64$100.00$176.00$185.00
0078Riprap stone channel protection, 12" thick (D50=6") (603036P)SY169$114.03$80.00$299.90$60.00$140.00$250.00
0079Chain-link fence, PVC-coated steel, 6' high (605027P)LF664$59.00$100.00$65.35$55.00$58.00$90.00
0080Chain-link fence, 5' high (605042P)LF171$69.00$135.00$72.17$55.00$64.00$85.00
0081Gate, chain-link fence, PVC- coated steel, 14' wide (605114M)U1$4,000.00$9,000.00$3,017.53$2,500.00$2,655.00$5,300.00
0082Concrete driveway, 6" thick (606051P)SY44$447.17$225.00$218.22$140.00$273.00$180.00
00839" X 16" concrete vertical curb (607018P)LF1,259$55.00$40.00$60.81$35.00$57.00$52.00
00849" X 14" concrete vertical curb (607034P)LF334$55.00$45.00$64.21$40.00$59.00$40.00
0085Nonvegetative surface, hot mix asphalt (608003P)SY3,341$50.00$50.00$61.37$55.00$54.00$63.75
0086Beam guide rail (609003M)LF2,870$34.00$35.00$33.53$30.00$30.00$42.50
0087Modified thrie beam guide rail (609009M)LF4,841$62.00$60.00$65.07$55.00$57.00$77.50
0088Modified thrie beam guide rail, dual faced (609012M)LF299$93.00$95.00$108.54$90.00$95.00$116.25
0089Tangent guide rail terminal (609027M)U2$3,450.00$3,500.00$4,375.71$3,500.00$3,850.00$4,312.50
0090Telescoping guide rail end terminal (609030M)U1$6,800.00$6,800.00$7,387.56$6,500.00$6,500.00$8,500.00
0091Beam guide rail anchorage (609039M)U3$1,450.00$1,500.00$1,420.68$1,250.00$1,250.00$1,812.50
0092Removal of beam guide rail (609075M)LF3,884$1.00$1.00$1.14$1.00$1.00$1.00
0093Traffic stripes, 6" (610006M)LF1,200$2.00$2.00$2.27$2.00$2.00$2.50
0094Relocate sign (612021M)U1$2,424.35$350.00$1,136.55$750.00$1,000.00$625.00
0095Custom sign (612032P)SF3$494.32$45.00$1,136.55$250.00$1,500.00$62.50
0096Modify existing load center (701375P)LS1$948.94$4,800.00$4,842.83$12,500$4,261.00$6,337.50
0097Lighting standard aluminum (703003M)U1$5,762.43$4,100.00$5,420.38$4,500.00$4,769.00$5,450.00
0098Lighting mast arm aluminum (703012M)U2$4,223.47$1,800.00$2,514.68$2,000.00$2,212.00$2,325.00
0099Luminaire (703018M)U7$3,545.50$2,100.00$1,169.14$1,500.00$1,028.00$2,862.50
0100Temporary highway lighting system (703033P)LS1$50,000$100.00$21,662$50,000$19,000$52,100
0101Selective thinning (801003M)ACRE2$23,500$10,000$38,188$35,000$33,600$21,175
0102Tree removal, over 18" to 24" diameter (802027M)U5$1,000.00$2,000.00$1,591.17$1,400.00$1,400.00$1,000.00
0103Tree removal, over 24" to 30" diameter (802030M)U3$1,000.00$2,500.00$2,216.27$1,900.00$1,950.00$1,375.00
0104Topsoil spreading __" thick 4" thick (804000P)SY18,310$8.15$7.00$4.55$4.00$7.00$9.00
0105Plant pit soil (804014P)CY20$195.00$70.00$73.88$65.00$65.00$156.25
0106Fertilizing and seeding, type A-3 (806006P)SY12,102$1.95$1.50$1.88$1.50$2.00$3.75
0107Fertilizing and seeding, basin bottom (806029P)SY8,533$1.95$1.50$4.32$3.50$4.00$5.00
0108Wildflower seeding (806030P)SY369$5.69$8.00$5.68$5.00$5.00$15.00
0109Fertilizing and seeding, low maintenance (806033P)SY3,311$1.95$1.50$1.93$1.50$2.00$5.00
0110Topsoil stabilization, type 2 mat (807006M)SY7,866$2.70$5.00$5.11$4.50$5.00$4.50
0111Straw mulching (809003M)SY8,902$0.54$1.00$1.14$1.00$1.00$1.25
0112Fiber mulching (809006M)SY12,102$0.54$1.50$1.76$1.50$2.00$1.25
0113Wood mulching (809018M)SY77$27.27$7.00$5.68$5.00$5.00$12.50
0114Large deciduous tree, 2-2 1/2" caliper, B&B (811006M)U12$895.00$600.00$710.34$600.00$625.00$750.00
0115Small deciduous tree, 2-2 1/2" caliper, B&B (811024M)U4$995.00$600.00$710.34$600.00$625.00$750.00
0116Small deciduous tree, 7-8' high, B&B (811031M)U8$895.00$600.00$670.56$550.00$590.00$650.00
0117Evergreen tree, 7-8' high B&B (811037M)U10$895.00$875.00$909.24$800.00$800.00$875.00
0118Deciduous shrub, 18-24" high, #3 container (811063M)U48$85.00$65.00$68.19$60.00$60.00$206.00
0119Evergreen shrub, 18-24" high, #3 container (811078M)U15$160.00$65.00$68.19$60.00$60.00$245.00
0120Plant establishment and maintenance period (811138M)LS1$8,500.00$75,000$6,677.21$6,000.00$5,875.00$18,750
0121Watering (811165M)MG7$1,250.00$400.00$397.79$350.00$350.00$625.00
0122Temporary sheeting (501003P)SF790$1.00$1.00$0.01$1.00$40.00$75.00
0123Furnishing drilled shaft equipment (503003P)LS1$500,000$255,000$15,912$169,522$50,700$505,000
0124Demonstration drilled shaft (503006M)LF20$2,400.00$850.00$1,449.01$550.00$1,100.00$1,562.50
0125Crosshole sonic logging (503012M)U5$1,200.00$3,300.00$3,409.64$4,000.00$3,418.00$3,125.00
0126Shaft coring (503015M)LF100$50.50$450.00$113.65$200.00$480.00$125.00
0127Drilled shaft in soil 36" diameter (503018M)LF3,261$191.29$675.00$593.85$350.00$732.00$1,000.00
0128Drilled shaft in soil, 42" diameter (503019M)LF84$338.30$825.00$533.59$450.00$927.00$1,170.00
0129Obstruction removal (503048M)LF20$2,900.00$100.00$909.24$1,500.00$2,990.00$1,250.00
0130Drilled shaft in rock, 30" diameter (503049M)LF295$1,072.89$790.00$1,329.58$950.00$834.00$1,188.00
0131Tomography (503051M)U5$1,200.00$2,100.00$1,136.55$2,000.00$2,200.00$3,125.00
0132Noise barrier, foundation (613002P)U2$28,570$33,000$59,767$55,000$28,390$22,580
0133Noise barrier, roadway (613004P)SY5,050$530.00$560.00$514.27$900.00$540.00$500.00
0134Noise barrier test posts and panels (613015P)LS1$12,033$10,000$11,365$10,000$13,000$25,000
NJDOT contract 25122: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

Every contract let that day: NJDOT letting of August 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy