9.5 F2 Top Course Asphalt, 80 Series Compaction, NYSDOT 404.098201
Low bidders on NYSDOT contracts carried a median of $193.00 per TON for this item, from 06 JAN 2022 to 11 APR 2024, across 79 low bids. Half of all 336 bids fell between $150.00 and $240.00.
- Owner
- New York State DOT
- Item
- 404.098201
- Unit
- TON
- Data through
- 15 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 33 | 33 | $193.00 | 144 | $180.00 |
| 2023 | 31 | 31 | $164.45 | 138 | $175.50 |
| 2024 | 15 | 15 | $200.00 | 54 | $210.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Region 05 | 26 | $196.50 | 110 | $180.00 |
| Region 09 | 14 | $160.57 | 71 | $180.00 |
| Region 02 | 13 | $227.00 | 59 | $193.50 |
| Region 03 | 7 | $180.00 | 38 | $180.00 |
| Region 04 | 9 | $155.00 | 30 | $187.50 |
| Region 01 | 8 | $255.00 | 22 | $250.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 3 to 113 | 19 | $265.00 |
| 119 to 259 | 20 | $199.00 |
| 265 to 549 | 20 | $175.00 |
| 549 to 13,886 | 20 | $141.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Cold Spring Construction Company | 22 | 7 (32%) |
| Bothar Construction LLC | 16 | 7 (44%) |
| Union Concrete & Construction Corp | 10 | 7 (70%) |
| Vector Construction Corp | 23 | 6 (26%) |
| Concrete Applied Technologies Corp/DBA:Catco | 20 | 6 (30%) |
| Oakgrove Construction Inc | 16 | 5 (31%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 11 APR 2024 | D265216 | Region 01 | 63 | $300.00 | $300.00 | 3 | Callanan Industries Inc | NYSDOT |
| 28 MAR 2024 | D265086 | Region 09 | 99 | $165.00 | $165.00 | 3 | Tioga Construction Company Inc | NYSDOT |
| 28 MAR 2024 | D265181 | Region 02 | 151 | $240.00 | $250.00 | 4 | Tioga Construction Company Inc | NYSDOT |
| 28 MAR 2024 | D265194 | Region 05 | 119 | $198.00 | $185.00 | 4 | The L C Whitford Co Inc | NYSDOT |
| 28 MAR 2024 | D265221 | Region 05 | 318 | $250.00 | $270.00 | 4 | Oakgrove Construction Inc | NYSDOT |
| 28 MAR 2024 | D265236 | Region 05 | 250 | $195.00 | $230.00 | 3 | Union Concrete & Construction Corp | NYSDOT |
| 28 MAR 2024 | D265242 | Region 05 | 690 | $203.00 | $203.00 | 3 | McLaughlin Construction Corp/DBA Edbauer Construction | NYSDOT |
| 14 MAR 2024 | D265190 | Region 03 | 219 | $180.00 | $174.00 | 4 | Economy Paving Co Inc | NYSDOT |
| 14 MAR 2024 | D265202 | Region 05 | 3,531 | $78.00 | $127.50 | 2 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 14 MAR 2024 | D265213 | Region 04 | 325 | $150.00 | $155.00 | 3 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 14 MAR 2024 | D265223 | Region 05 | 464 | $300.00 | $300.00 | 5 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 14 MAR 2024 | D265224 | Region 05 | 210 | $200.00 | $200.00 | 7 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 08 FEB 2024 | D265185 | Region 05 | 184 | $200.00 | $225.00 | 2 | Oakgrove Construction Inc | NYSDOT |
| 25 JAN 2024 | D265161 | Region 01 | 265 | $230.00 | $230.00 | 4 | Bette & Cring LLC | NYSDOT |
| 11 JAN 2024 | D265182 | Region 06 | 49 | $350.00 | $212.00 | 3 | Vacri Construction Corp | NYSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the NYSDOT explorer.
How these prices were read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NYSDOT's own: this item is compared with NYSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NYSDOT letting of 15 OCT 2026 and was rebuilt on 26 NOV 2026.