Adams Construction Company: NCDOT bid record

Adams Construction Company submitted 23 bids on North Carolina DOT contracts in the data, from 18 JUN 2013 to 20 MAY 2025, and was the low bidder on 3 of them (13%). When it was not low, its total sat a median +20% above the low bid.

Owner
North Carolina DOT
Low bid volume
$11,656,294
Latest bid
20 MAY 2025
Data through
20 OCT 2026
23Bids
3Low bids
13Win rate, percent
+20%Median gap to the low bid when not low, 20 bids

By year

YearBidsLow bidsWin rate
2013500%
20144125%
2015200%
2016100%
2017100%
2018100%
20215120%
20222150%
2023100%
2025100%
Adams Construction Company, NCDOT: bids and low bids by year of letting

By county

CountyBidsLow bidsWin rate
Person8225%
Rockingham500%
Stokes200%
Warren200%
Caswell2150%
Person, Caswell100%
Halifax100%
Surry, Yadkin100%
Surry100%
Adams Construction Company, NCDOT: bids and low bids by county

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Thermoplastic pavement marking lines (4", 90 mils)4685000000-ELF1810 (56%)$0.46$0.75
Thermoplastic pavement marking symbol (90 mils)4725000000-EEACH1510 (67%)$150.00$135.00
Work zone advance/general warning signing4413000000-ESF169 (56%)$6.14$6.33
Paint pavement marking lines (4")4810000000-ELF129 (75%)$0.10$0.27
Incidental stone base1220000000-ETON228 (36%)$47.68$40.00
Incidental milling1330000000-ESY208 (40%)$7.00$12.00
Thermoplastic pavement marking lines (4", 120 mils)4686000000-ELF117 (64%)$0.59$0.74
Paint pavement marking symbol4845000000-NEACH97 (78%)$40.00$50.00
Snowplowable pavement markers4905000000-NEACH146 (43%)$26.77$29.50
Seeding and mulching6084000000-EACRE126 (50%)$2,087.50$2,365.00
Inductive loop sawcut7444000000-ELF106 (60%)$6.12$7.25
Paint pavement marking lines (24")4835000000-ELF96 (67%)$3.00$3.50
Adams Construction Company, NCDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Carolina Sunrock LLC129 of 12
Apac - Atlantic, Inc. Thompson Arthur Division119 of 11
FSC II LLC DBA Fred Smith Company73 of 7
Sharpe Brothers A Div of Vecellio & Grogan, Inc.65 of 6
Larco Construction A Division of Branscome Inc43 of 4
S T Wooten Corporation43 of 4
Blythe Construction Inc33 of 3
Barnhill Contracting Company22 of 2
Carl Rose & Sons, Inc.22 of 2
Sunrock Industries LLC DBA Carolina Sunrock LLC11 of 1
Adams Construction Company, NCDOT: the firms on the same contracts most often

Latest bids

LetContractCountyProjectRankIts bidAgainst the low bid
20 MAY 2025C205103Person, CaswellMILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 10 SECTIONS OF SECONDARY ROADS2 of 3$1,584,100+8.0%
17 OCT 2023C204899PersonMilling, resufacing and shoulder reconstruction. 5 SECTIONS OF SECONDARY ROADS.3 of 3$3,147,280+150%
20 DEC 2022C204807WarrenMilling, and resurfacing. 1 SECTION OF NC-903 AND 10 SECTIONS OF PRIMARY ROADS.2 of 3$4,489,000+8.0%
18 OCT 2022C204780PersonResurfacing and shoulder grading. 2 SECTIONS OF SECONDARY ROADS.1 of 2$2,559,314Low, 2.0% under the second
16 NOV 2021C204671WarrenMilling, resurfacing, and shoulder grading. 4 SECTIONS OF SECONDARY ROADS.3 of 3$2,180,135+4.0%
21 SEP 2021C204366HalifaxPavement rehabilitation and drainage. I-95 FROM MILE MARKER 153.20 (NC-148) TO MILE MARKER 167.00.3 of 3$15,464,638+23%
21 SEP 2021C204664PersonMilling, resurfacing and shoulder grading. 1 SECTION OF NC-158, 1 SECTION OF NC-49 AND 8 SECTIONS OF SECONDARY ROADS.2 of 2$4,695,491+20%
18 MAY 2021C204635CaswellMilling and resurfacing. 1 SECTION OF NC-119 AND 18 SECTIONS OF SECONDARY ROADS.1 of 4$3,855,647Low, 0.0% under the second
16 MAR 2021C204610PersonMilling, resurfacing, and shoulder grading. 11 SECTIONS OF SECONDARY ROADS.3 of 3$3,840,420+29%
20 NOV 2018C204267PersonMilling, resurfacing, and shoulder grading. 15 SECTIONS OF SECONDARY ROADS.2 of 2$4,986,765+21%
21 NOV 2017C204092RockinghamMilling & resurfacing. US-29 FROM US-158 TO CASWELL COUNTY LINE.3 of 3$5,508,845+11%
19 APR 2016C203852PersonMilling, resurfacing & shoulder reconstruction. 1 SECTION OF NC-49, 1 SECTION OF NC-157,1 SECTION OF US-501, AND 25 SECTIONS OF SECONDARY RO2 of 2$11,605,832+46%
16 JUN 2015C203708RockinghamMilling & resurfacing. NC-87 FROM US-29 BUS TO SR-2594 AND 22 SECTIONS OF SECONDARY ROADS.4 of 4$4,433,983+30%
16 JUN 2015C203700StokesMilling, resurfacing & shoulder reconstruction. NC-8 FROM NC-89 TO VIRGINIA STATE LINE & 2 SECTIONS OF SECONDARY ROADS.4 of 4$2,285,000+43%
21 OCT 2014C203610RockinghamMilling & resurfacing. NC-704 FROM BRG #48 TO US-220 BUS, NC-770 FROM SR-1533 TO LEMONS ST AND 7 SECTIONS OF SECONDARY ROADS.3 of 5$3,073,149+8.0%
26 AUG 2014C203603PersonMilling, resurfacing & shoulder reconstruction. 1 SECTION EACH OF NC-57, US-501 & US-158, 2 SECTIONS OF NC-49 AND 6 SECTIONS OF SECONDARY RO1 of 5$5,241,333Low, 1.0% under the second
15 JUL 2014C203576StokesMilling, resurfacing & shoulder reconstruction. NC-89 FROM NC-66 TO SURRY CO LINE, NC-704 FROM NC-8 TO SR-1434 AND 8 SECTIONS OF SECONDARY R3 of 3$2,502,627+11%
21 JAN 2014C203475RockinghamMilling & resurfacing. US-311 FROM EAST OF SUMMIT ST TO BRIDGE #30 AND 12 SECTIONS OF SECONDARY ROADS.5 of 5$2,509,627+31%
15 OCT 2013C203444CaswellResurfacing and shoulder reconstruction. NC-62 FROM THE ALAMANCE COUNTY LINE TO SR-1751 & SR-1156, AND 1 SECTION OF SECONDARY ROAD.5 of 5$2,305,248+20%
15 OCT 2013C203442SurryMilling and resurfacing. I-77 FROM MM-95 TO MM-99.2 of 2$2,739,928+2.0%
17 SEP 2013C203428PersonMilling, resurfacing, and shoulder reconstruction. NC-57 FROM SR-1340 TO CASWELL COUNTY LINE AND 4 SECTIONS OF SECONDARY ROADS.6 of 6$3,060,559+19%
20 AUG 2013C203417Surry, YadkinMilling, milled rumble strips, resurfacing, & shldr reconst. US-52 FROM SR-1856 TO SR-1822, US-421 SBL FROM WILKES CO TO WEST OF SR-1103, AN2 of 2$3,785,496+5.0%
18 JUN 2013C203371RockinghamWidening, resurfacing & shoulder reconstruction. US-158 FROM EAST OF SR-2351 TO WEST OF SR-2426.4 of 4$2,060,938+47%
Adams Construction Company: latest NCDOT bids in the data

How this record was read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Every bid counted here matched its published total to within one dollar; NCDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy