Thalle Construction Co., Inc.: NCDOT bid record

Thalle Construction Co., Inc. submitted 29 bids on North Carolina DOT contracts in the data, from 21 JAN 2014 to 15 JUL 2025, and was the low bidder on 4 of them (14%). When it was not low, its total sat a median +18% above the low bid.

Owner
North Carolina DOT
Low bid volume
$146,922,403
Latest bid
15 JUL 2025
Data through
20 OCT 2026
29Bids
4Low bids
14Win rate, percent
+18%Median gap to the low bid when not low, 25 bids

By year

YearBidsLow bidsWin rate
2014300%
20154125%
2016300%
20172150%
20185120%
20195120%
2022200%
2023400%
2025100%
Thalle Construction Co., Inc., NCDOT: bids and low bids by year of letting

By county

CountyBidsLow bidsWin rate
Guilford400%
Wake300%
Johnston200%
Alamance22100%
Halifax200%
New Hanover, Pender100%
Beaufort, Martin100%
Brunswick100%
Lenoir11100%
Carteret100%
Dare100%
Forsyth100%
Thalle Construction Co., Inc., NCDOT: bids and low bids by county

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Temporary raised pavement markers4650000000-NEACH2516 (64%)$7.00$9.00
Thermoplastic pavement marking symbol (90 mils)4725000000-EEACH2515 (60%)$135.00$135.00
Paint pavement marking symbol4845000000-NEACH2215 (68%)$52.50$50.00
Barricades (type III)4445000000-ELF2914 (48%)$25.00$24.30
Paint pavement marking lines (4")4810000000-ELF2614 (54%)$0.25$0.27
Additional guardrail posts3150000000-NEACH2614 (54%)$25.00$13.00
Disposal of sign system, U-channel4155000000-NEACH2414 (58%)$2.00$5.00
Work zone signs (barricade mounted)4410000000-ESF2913 (45%)$7.00$7.50
Sign erection, type D4096000000-NEACH2413 (54%)$125.00$125.00
Asphalt conc surface course, type S9.5C1523000000-ETON2113 (62%)$55.00$64.72
Thermoplastic pavement marking lines (8", 90 mils)4695000000-ELF1913 (68%)$2.00$2.25
Specialized hand mowing6114500000-NMHR2912 (41%)$60.00$64.75
Thalle Construction Co., Inc., NCDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Thalle Construction Co., Inc., NCDOT: the firms on the same contracts most often

Latest bids

LetContractCountyProjectRankIts bidAgainst the low bid
15 JUL 2025C205072New Hanover, PenderGRADING, DRAINAGE, PAVING, AND STRUCTURES. US-17 (HAMPSTEAD BYPASS) FROM US-17 BYPASS SOUTH OF HAMPSTEAD TO NC-2106 of 7$217,410,825+19%
19 SEP 2023C204785HarnettGrading, drainage, paving, signals, and culverts. NC-55 FROM SOUTH OF SR-1532 (OAK GROVE CHURCH RD) TO NC-210.5 of 5$60,703,368+25%
15 AUG 2023C204872ChathamGrading, drainage, and paving. CHATHAM PARKWAY FROM NORTH OF US-64 TO NORTH OF PROPOSED GRANT DRIVE.7 of 8$17,995,320+32%
18 JUL 2023C204786WakeGrading, drainage, paving, signals, and structures. US-401 AT SR-2044 (LIGON MILL RD)/SR-2224 (MITCHELL MILL RD) AND SR-2006 (PERRY CREEK RD2 of 4$51,571,558+14%
16 MAY 2023C204570ColumbusGrading, drainage, paving, and structures. NC-87 AT NC-11 CONSTRUCT INTERCHANGE.6 of 6$51,865,465+44%
21 JUN 2022C204110CumberlandGrading, drainage, paving, signing, signals, and structures. FAYETTEVILLE OUTER LOOP FROM SOUTH OF SR-1003 (CAMDEN ROAD) TO SOUTH OF US-401.4 of 6$163,150,000+7.0%
19 APR 2022C204498Beaufort, MartinGrading, drainage, paving, and structure. US-17 FROM WASHINGTON BYPASS NORTH OF NC-171 TO MULTI-LANES SOUTH OF WILLIAMSTON.4 of 4$106,880,613+24%
17 DEC 2019C204378SampsonGrading, drainage, paving, signals, and structures. NC-24 FROM US-421/701 AND SR-1296 (SUNSET AVE) TO EAST OF SR-1935 (CECIL ODIE RD).4 of 8$29,297,192+19%
19 NOV 2019C204351WakeGrading, drainage, paving, its, and structures. I-40 AND SR-3015 (AIRPORT BLVD) INTERCHANGE AND I-40 WESTBOUND FROM SR-3015 (AIRPORT BLVD) T3 of 6$38,481,583+10%
15 OCT 2019C204368RichmondGrading, drainage, paving, and structures. I-73/74 FROM US-74 BYPASS WEST OF ROCKINGHAM AT SR-1109 (ZION CHURCH RD) TO NORTH OF SR-1304 (HAR5 of 5$172,132,633+18%
16 JUL 2019C204210NorthamptonGrading, drainage, paving, and structures. US-158/NC-46 FROM I-95/NC-46 IN ROANOKE RAPIDS TO SR-1312 (ST JOHN CHURCH ST).1 of 4$81,907,374Low, 8.0% under the second
16 APR 2019C204078OrangeGrading, drainage, paving, and structure. BRIDGE #46 OVER ENO RIVER ON US-70 BYPASS.6 of 7$6,587,508+35%
02 OCT 2018C204149HalifaxGrading, drainage, paving, signals, and structures. NC-125 FROM I-95 TO OLD FARM RD SOUTH; SR-1627 (THREE BRIDGE RD) FROM NC-125 TO PREMIER 3 of 5$25,261,130+3.0%
17 JUL 2018C204106AlamanceGrading, drainage, paving, and structure. NC-119 RELOCATION NORTH OF SR-1921 (MEBANE ROGERS RD) TO SOUTH OF SR-1918 (MRS WHITE RD).1 of 8$8,151,661Low, 9.0% under the second
19 JUN 2018C204103GuilfordGrading, drainage, paving, signals, and structures. SR-1486/SR-4121 (GREENSBORO/HIGH POINT RD) FROM PROPOSED US-311 BYPASS TO WEST OF SR-1485 of 7$62,128,773+11%
20 MAR 2018C204096GuilfordGrading, drainage, paving, signals, its, and structures. GREENSBORO EASTERN LOOP FROM US-29 NORTH OF GREENSBORO TO SR-2303 (LAWNDALE DR).4 of 8$147,761,650+9.0%
20 FEB 2018C204069WakeGrading, drainage, paving, its, and structures. I-40 AND SR-1002 (AVIATION PARKWAY) INTERCHANGE.3 of 7$22,572,471+5.0%
21 NOV 2017C203979ForsythWiden, grading, paving, drainage, signing, signals & strs. WINSTON-SALEM NORTHERN BELTWAY (EASTERN SECTION) FROM US-311 TO US-158 (FUTURE I-7 of 10$39,192,897+18%
16 MAY 2017C203844AlamanceGrading, drainage, paving, signals & structures. NC-119 RELOCATION FROM I-40/85 TO SR-1921 (MEBANE ROGERS RD/ STAGE COACH RD).1 of 10$45,389,069Low, 3.0% under the second
18 OCT 2016C203921JohnstonGrading, drainage, paving, and structure. NOVO NORDISK ACCESS ROAD FROM SR-1913 (GORDON ROAD) TO PROPOSED NOVO NORDISK SITE.5 of 9$6,734,252+10%
20 SEP 2016C203792GuilfordGrading, drainage, paving, its, signals & structures. GREENSBORO WESTERN LOOP - FROM US-220 (BATTLEGROUND AVENUE) TO SR-2303 (LAWNDALE DRIVE5 of 8$67,449,297+16%
19 JUL 2016C203749HalifaxGrading, drainage, paving, & structure. BRIDGE #29 OVER LITTLE FISHING CREEK ON NC-561.6 of 6$2,989,146+17%
17 NOV 2015C203658JohnstonGrading, drainage, paving, structure, & signals. BRIDGES #114 AND 116 OVER LITTLE RIVER ON I-95.5 of 8$14,632,914+19%
20 OCT 2015C203756DareGrading, drainage, paving & structure. NC-12 - SHORT-TERM IMPROVEMENTS AT PEA ISLAND (PHASE II).7 of 8$26,498,111+58%
21 APR 2015C203563CarteretGrading, drainage, paving, and structures. BRIDGE #33 OVER NORTH RIVER ON US-70.2 of 6$17,910,125+26%
Thalle Construction Co., Inc.: latest NCDOT bids in the data

How this record was read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Every bid counted here matched its published total to within one dollar; NCDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy