Jet Excavating Company: ODOT bid record
Jet Excavating Company submitted 16 bids on Ohio DOT contracts in the data, from 23 JAN 2020 to 15 SEP 2022, and was the low bidder on 4 of them (25%). When it was not low, its total sat a median +27% above the low bid.
- Owner
- Ohio DOT
- Low bid volume
- $5,555,822
- Latest bid
- 15 SEP 2022
- Data through
- 12 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 6 | 2 | 33% |
| 2021 | 6 | 0 | 0% |
| 2022 | 4 | 2 | 50% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| GEA | 7 | 2 | 29% |
| TRU | 4 | 0 | 0% |
| JEF | 1 | 1 | 100% |
| District 4 | 1 | 0 | 0% |
| ATB | 1 | 0 | 0% |
| STA | 1 | 0 | 0% |
| TUS | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion control | 832E30000 | EACH | 15 | 15 (100%) | $1.00 | $1.00 |
| Water | 659E35000 | MGAL | 14 | 13 (93%) | $1.00 | $1.00 |
| Subgrade compaction | 204E10000 | SY | 14 | 7 (50%) | $2.00 | $3.00 |
| Repair seeding and mulching | 659E14000 | SY | 13 | 6 (46%) | $1.00 | $1.25 |
| Tack coat | 407E10000 | GAL | 10 | 6 (60%) | $3.25 | $3.25 |
| Seeding and mulching | 659E10000 | SY | 9 | 6 (67%) | $1.50 | $2.60 |
| Class QC1 concrete, footing | 511E46510 | CY | 9 | 5 (56%) | $875.00 | $690.00 |
| Proof rolling | 204E45000 | HR | 6 | 5 (83%) | $50.00 | $219.05 |
| Object marker, two way | 614E13360 | EACH | 6 | 5 (83%) | $15.00 | $21.00 |
| Traffic compacted surface, type A or B | 410E12000 | CY | 6 | 5 (83%) | $45.00 | $79.08 |
| Epoxy coated steel reinforcement | 509E10000 | LB | 5 | 5 (100%) | $2.00 | $2.00 |
| Class QC1 concrete, retaining/wingwall not including footing, as per plan | 511E46011 | CY | 5 | 5 (100%) | $2,500.00 | $1,900.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Eclipse Co LLC | 12 | 6 of 12 |
| Bog Construction Inc | 7 | 5 of 7 |
| Lockhart Concrete Co | 4 | 1 of 4 |
| Catts Construction Inc | 3 | 3 of 3 |
| Shelly & Sands Inc | 3 | 2 of 3 |
| Marucci & Gaffney Excavating Co | 3 | 1 of 3 |
| Shook Company LLC | 3 | 2 of 3 |
| Americon Industrial Services LLC | 2 | 2 of 2 |
| Nerone & Sons Inc | 2 | 0 of 2 |
| Rudzik Excavating Inc | 2 | 1 of 2 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 15 SEP 2022 | 224024 | GEA | GEA-US 322-01.64/VAR (CULVERT REPLACEMENT) | 1 of 2 | $3,817,560 | Low, 19% under the second |
| 17 FEB 2022 | 224010 | TUS | TUS-SR 212-10.80 (CULVERT REPLACEMENT) | 1 of 5 | $607,952 | Low, 1.0% under the second |
| 27 JAN 2022 | 224005 | GEA | GEA-SR 528-15.26 Replace (CULVERT REPLACEMENT) | 2 of 3 | $592,637 | +9.0% |
| 13 JAN 2022 | 223001 | TRU | TRU-SR 46-25.07 (BRIDGE REPAIR) | 3 of 5 | $925,890 | +8.0% |
| 16 DEC 2021 | 214023 | TRU | TRU-SR 5-06.41/06.63 (SLIDE REPAIR) | 3 of 3 | $647,732 | +11% |
| 18 NOV 2021 | 214018 | GEA | GEA-US 322-04.36 Culvert (CULVERT REPLACEMENT) | 2 of 4 | $413,964 | +13% |
| 29 APR 2021 | 214012 | STA | STA-/POR Culverts FY2021 (CULVERT REPLACEMENT) | 4 of 4 | $806,952 | +27% |
| 15 APR 2021 | 214009 | GEA | GEA-US 422-14.90 Culvert (CULVERT REPLACEMENT) | 3 of 3 | $554,908 | +31% |
| 11 FEB 2021 | 210100 | TRU | TRU-Warner Rd Bridge (BRIDGE REPLACEMENT (1 BRIDGE)) | 6 of 7 | $1,584,731 | +35% |
| 14 JAN 2021 | 210018 | GEA | GEA-SR 166-01.08 (CULVERT REPLACEMENT) | 7 of 11 | $239,571 | +27% |
| 30 JUL 2020 | 204013 | GEA | GEA-SR 608-07.10 (BRIDGE REPAIR) | 1 of 2 | $675,853 | Low, 18% under the second |
| 23 APR 2020 | 200244 | TRU | TRU-Myron St Bridge (BRIDGE REPAIR) | 2 of 4 | $498,894 | +7.0% |
| 26 MAR 2020 | 200184 | ATB | ATB-Culverts FY2020 (CULVERT REPLACEMENT) | 7 of 8 | $472,767 | +55% |
| 27 FEB 2020 | 204006 | District 4 | D04-BH FY2020 (East) (BRIDGE REPAIR) | 4 of 4 | $1,291,869 | +71% |
| 23 JAN 2020 | 200040 | GEA | GEA-SR 168-04.10 Culvert (CULVERT REPLACEMENT) | 8 of 12 | $272,747 | +29% |
| 23 JAN 2020 | 204001 | JEF | JEF-SR 151-15.24 (CULVERT REPLACEMENT) | 1 of 6 | $454,457 | Low, -19% under the second |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.