ODOT contract 250012 bid tabulation
GAL-SR 7-19.94 (SLIDE REPAIR). Let by Ohio DOT on January 16, 2025, GAL. 4 bids received; low bid $2,473,505 by Alan Stone Co Inc, +11% against the engineer's estimate of $2,221,000.
- Owner
- Ohio DOT
- Letting
- 16 JAN 2025
- Pay items
- 68
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Alan Stone Co Inc | $2,473,505 | Low | +11% |
| 2 | Shelly & Sands Inc | $2,490,466 | +1.0% | +12% |
| 3 | Kokosing Construction Company Inc | $2,648,707 | +7.0% | +19% |
| 4 | Allard Excavation LLC | $3,217,815 | +30% | +45% |
Engineer's estimate: $2,221,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alan Stone Co Inc | 2. Shelly & Sands Inc | 3. Kokosing Construction Company Inc | 4. Allard Excavation LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $12,000 | $1,500.00 | $10,000 | $3,931.00 |
| 2 | Pavement removed, as per plan (202E23001) | SY | 138 | $25.00 | $30.00 | $35.00 | $7.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 5 | $140.00 | $22.00 | $75.00 | $10.00 |
| 4 | Guardrail removed (202E38000) | FT | 214 | $6.50 | $3.00 | $3.00 | $3.00 |
| 5 | Anchor assembly removed (202E42206) | EACH | 2 | $450.00 | $175.00 | $200.00 | $50.00 |
| 6 | Catch basin removed (202E58100) | EACH | 1 | $450.00 | $500.00 | $350.00 | $393.00 |
| 7 | Special - fill and plug existing conduit (202E70000) | FT | 93 | $45.00 | $50.00 | $40.00 | $46.00 |
| 8 | Removal misc.:concrete outlet apron (202E98100) | EACH | 1 | $350.00 | $250.00 | $1,500.00 | $281.00 |
| 9 | Removal misc.:stand pipe (202E98100) | EACH | 1 | $900.00 | $250.00 | $350.00 | $459.00 |
| 10 | Excavation (203E10000) | CY | 156 | $30.00 | $40.00 | $95.00 | $32.00 |
| 11 | Embankment (203E20000) | CY | 236 | $15.00 | $25.00 | $45.00 | $24.00 |
| 12 | Subgrade compaction (204E10000) | SY | 349 | $7.00 | $10.00 | $7.00 | $3.00 |
| 13 | Pavement planing, asphalt concrete, as per planvar (254E01001) | SY | 254 | $40.00 | $32.00 | $32.00 | $37.00 |
| 14 | Guardrail, type MGS (606E15050) | FT | 200 | $25.00 | $22.50 | $19.98 | $23.00 |
| 15 | Guardrail, type MGS with long posts (606E15100) | FT | 337.50 | $25.00 | $24.00 | $21.46 | $25.00 |
| 16 | Rounded end section (606E20050) | EACH | 2 | $75.00 | $70.00 | $55.00 | $63.00 |
| 17 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,400.00 | $1,250.00 | $1,000.00 | $1,143.00 |
| 18 | Rock channel protection, type B with filter (601E32100) | CY | 3 | $480.00 | $190.00 | $750.00 | $76.00 |
| 19 | Seeding and mulching (659E10000) | SY | 1,544 | $2.00 | $2.45 | $2.45 | $2.45 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.21 | $620.00 | $1,435.02 | $1,507.18 | $571.00 |
| 21 | Lime (659E31000) | ACRE | 0.32 | $890.00 | $200.00 | $200.00 | $571.00 |
| 22 | Water (659E35000) | MGAL | 4.17 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Class QC MS concrete (511E52110) | CY | 56 | $290.00 | $255.00 | $340.00 | $408.00 |
| 25 | Concrete masonry (602E20000) | CY | 1.20 | $2,200.00 | $2,550.00 | $3,500.00 | $4,725.00 |
| 26 | 4" base pipe underdrains (605E06000) | FT | 443 | $15.00 | $19.00 | $25.00 | $27.00 |
| 27 | 30" conduit, type A (611E13200) | FT | 75 | $270.00 | $300.00 | $375.00 | $292.00 |
| 28 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $420.00 | $350.00 | $400.00 | $336.00 |
| 29 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 72 | $280.00 | $425.00 | $425.00 | $486.00 |
| 30 | Aggregate base (304E20000) | CY | 93 | $85.00 | $120.00 | $132.00 | $77.00 |
| 31 | Non-tracking tack coat (407E20000) | GAL | 211 | $5.00 | $4.00 | $3.90 | $4.00 |
| 32 | Prime coat (408E10000) | GAL | 138 | $15.00 | $10.00 | $5.00 | $6.00 |
| 33 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 106 | $290.00 | $275.00 | $275.00 | $318.00 |
| 34 | Asphalt concrete intermediate course, type 1, (448) (441E50200) | CY | 12 | $660.00 | $395.00 | $395.00 | $451.00 |
| 35 | Asphalt concrete intermediate course, type 1, (449) (441E70200) | CY | 68 | $320.00 | $320.00 | $320.00 | $366.00 |
| 36 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 7 | $870.00 | $275.00 | $275.00 | $314.00 |
| 37 | Compacted aggregate (617E10100) | CY | 29 | $150.00 | $145.00 | $140.00 | $78.00 |
| 38 | RPM (621E00100) | EACH | 20 | $190.00 | $175.00 | $175.00 | $200.00 |
| 39 | Raised pavement marker removed (621E54000) | EACH | 20 | $20.00 | $12.00 | $25.00 | $8.00 |
| 40 | Barrier reflector, type 2(bidirectional) (626E00110) | EACH | 12 | $15.00 | $12.00 | $10.00 | $11.00 |
| 41 | Edge line, 6", type 1 (642E00104) | MI | 0.30 | $3,100.00 | $2,800.00 | $2,800.00 | $3,200.00 |
| 42 | Center line, type 1 (642E00300) | MI | 0.15 | $5,700.00 | $5,200.00 | $5,200.00 | $5,942.00 |
| 43 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 4 | $2,700.00 | $2,400.00 | $3,500.00 | $1,800.00 |
| 44 | Work zone lighting system (614E12740) | EACH | 1 | $1,100.00 | $41,000 | $30,000 | $6,073.00 |
| 45 | Barrier reflector, type 1(bidirectional) (614E13310) | EACH | 17 | $50.00 | $8.00 | $45.00 | $11.00 |
| 46 | Object marker, two way (614E13360) | EACH | 17 | $55.00 | $12.00 | $48.00 | $11.00 |
| 47 | Work zone edge line, class I, 6" (614E22010) | MI | 0.31 | $5,600.00 | $5,075.00 | $10,450 | $5,799.00 |
| 48 | Work zone stop line, class I (614E26000) | FT | 24 | $15.00 | $14.00 | $14.00 | $16.00 |
| 49 | Roads for maintaining traffic (615E10000) | LS | 1 | $10,500 | $12,000 | $4,500.00 | $5,074.00 |
| 50 | Pavement for maintaining traffic, class B (615E25000) | SY | 85 | $70.00 | $165.00 | $160.00 | $119.00 |
| 51 | Portable barrier, unanchored (622E41100) | FT | 850 | $20.00 | $35.00 | $25.00 | $27.00 |
| 52 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $25.00 | $22,100 | $23,000 | $10,037 |
| 53 | Steel piles, misc.:soldier piles, W27X146 (507E00400) | FT | 3,706 | $131.00 | $125.00 | $148.00 | $139.00 |
| 54 | Class QC1 concrete, footing, as per plan (511E46511) | CY | 20 | $500.00 | $450.00 | $610.00 | $429.00 |
| 55 | Porous backfill with geotextile fabric (518E21200) | CY | 137 | $85.00 | $115.00 | $80.00 | $112.00 |
| 56 | 6" perforated corrugated plastic pipe (518E40000) | FT | 233 | $9.00 | $4.00 | $12.00 | $6.00 |
| 57 | 6" non-perforated corrugated plastic pipe (518E40012) | FT | 38 | $6.00 | $25.00 | $35.00 | $6.00 |
| 58 | Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703) | FT | 950 | $160.00 | $140.00 | $110.00 | $90.00 |
| 59 | Drilled shafts, 42" diameter, above bedrock, as per plan (524E94803) | FT | 2,664 | $190.00 | $200.00 | $140.00 | $125.00 |
| 60 | Drilled shafts, 42" diameter, into bedrock, as per plan (524E94805) | FT | 780 | $410.00 | $240.00 | $200.00 | $129.00 |
| 61 | Drilled shafts, misc.:36" permanent casing (524E95000) | FT | 950 | $130.00 | $160.00 | $195.00 | $427.00 |
| 62 | Drilled shafts, misc.:42" permanent casing (524E95000) | FT | 2,664 | $160.00 | $170.00 | $230.00 | $361.00 |
| 63 | Drilled shafts, misc.:extension (524E95000) | FT | 3 | $260.00 | $180.00 | $150.00 | $1,908.00 |
| 64 | Special - retaining wall, precast concrete lagging (530E51010) | SF | 1,320 | $25.00 | $30.00 | $30.00 | $164.00 |
| 65 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $17,000 | $14,499 | $10,000 | $21,472 |
| 66 | Maintaining traffic (614E11000) | LS | 1 | $65,000 | $16,000 | $80,000 | $43,948 |
| 67 | Construction layout stakes and surveying (623E10000) | LS | 1 | $13,000 | $15,000 | $12,000 | $23,517 |
| 68 | Mobilization (624E10000) | LS | 1 | $32,000 | $105,000 | $130,000 | $177,056 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.