ODOT contract 250016 bid tabulation

HUR-SR 18-17.10 (INTERSECTION). Let by Ohio DOT on January 16, 2025, HUR. 7 bids received; low bid $1,519,776 by D L Smith Concrete LLC, -15% against the engineer's estimate of $1,790,000.

Owner
Ohio DOT
Letting
16 JAN 2025
Pay items
139
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1D L Smith Concrete LLC$1,519,776Low-15%
2Smith Paving & Excavating Inc$1,562,056+3.0%-13%
3Fechko Excavating LLC$1,689,764+11%-6.0%
4Shelly & Sands Inc$1,768,185+16%-1.0%
5Eclipse Co LLC$1,851,134+22%+3.0%
6Kokosing Construction Company Inc$2,020,276+33%+13%
7Great Lakes Demolition Company$2,112,824+39%+18%
ODOT contract 250016: bids by rank

Engineer's estimate: $1,790,000.

Bid tabulation

LinePay itemUnitQuantity1. D L Smith Concrete LLC2. Smith Paving & Excavating Inc3. Fechko Excavating LLC4. Shelly & Sands Inc5. Eclipse Co LLC6. Kokosing Construction Company Inc
1Clearing and grubbing (201E11000)LS1$3,500.00$21,000$11,000$40,000$10,000$15,000
2Pavement removed (202E23000)SY5,114$6.35$8.75$8.25$12.00$9.00$11.00
3Pipe removed, 24" and under (202E35100)FT163$22.00$14.00$35.00$21.50$27.00$35.00
4Guardrail removed (202E38000)FT78$2.50$2.50$3.50$3.00$3.00$10.00
5Guard post removed (202E38800)EACH12$25.00$25.00$150.00$46.00$26.00$75.00
6Mailbox removed (202E53100)EACH1$30.00$50.00$150.00$279.00$183.00$200.00
7Fence removed (202E75000)FT584$3.50$3.50$4.00$4.00$4.00$10.00
8Removal misc.: decorative well & functioning spigo (202E98100)EACH1$4,500.00$3,300.00$900.00$588.00$183.00$1,000.00
9Excavation (203E10000)CY2,574$20.00$23.00$27.50$20.00$41.00$33.50
10Embankment (203E20000)CY1,324$27.00$19.50$12.25$22.00$22.00$10.00
11Subgrade compaction (204E10000)SY667$2.00$2.00$5.00$2.00$1.00$6.50
12Proof rolling (204E45000)HR4$150.00$100.00$300.00$378.00$332.00$240.00
13Cement (206E10500)TON192$190.00$203.00$190.00$214.00$235.00$203.00
14Curing coat (206E11000)SY7,415$1.20$1.20$1.20$1.00$1.50$1.20
15Cement stabilized subgrade, 12 inches deep (206E15010)SY7,415$4.10$4.60$4.70$5.00$5.00$5.00
16Pavement planing, asphalt concrete, (1.50") (254E01000)SY1,649$7.00$6.50$7.50$4.00$3.50$5.00
17Guardrail, type 5 (606E13000)FT75$24.00$24.00$24.00$26.00$24.00$21.00
18Guardrail, type MGS (606E15050)FT262.50$24.80$24.80$25.00$27.00$25.00$21.00
19Rounded end section (606E20050)EACH1$65.00$65.00$65.00$70.00$68.00$50.00
20Anchor assembly, MGS type E [MASH 2016] (606E26150)EACH1$2,580.00$2,580.00$2,580.00$2,761.00$2,580.00$2,450.00
21Anchor assembly, type T (606E26500)EACH1$985.00$985.00$985.00$1,054.00$985.00$1,375.00
22Bridge terminal assembly, type 4 (606E35140)EACH2$960.00$960.00$960.00$1,028.00$960.00$1,100.00
23Fence, type CLT, as per plan (607E23001)FT488$30.50$30.50$30.50$33.00$31.00$48.00
24Gate, type CLT, as per plan (607E61201)EACH1$12,850$12,850$12,850$13,753$12,850$21,500
25Fenceline seeding and mulching (607E70000)FT488$1.50$2.00$5.00$2.00$2.00$1.45
26Monument assembly, type C (623E38500)EACH5$1,000.00$1,200.00$2,400.00$3,000.00$2,272.00$1,000.00
27Right-of-way monument, type B (623E40520)EACH9$155.00$650.00$150.00$600.00$807.00$250.00
28Preconstruction survey monument verification and report (623E50000)LS1$2,200.00$1,250.00$5,300.00$3,200.00$4,298.00$2,100.00
29Post construction survey monument verification and report (623E51000)LS1$2,200.00$1,250.00$2,700.00$3,000.00$4,298.00$2,100.00
30Special - mailbox support system, single (690E50100)EACH1$215.00$250.00$165.00$343.00$179.00$200.00
31Tied concrete block mat with type 1 underlayment (601E21050)SY8$195.00$175.00$98.00$200.00$197.00$150.00
32Tied concrete block mat with type 2 underlayment (601E21060)SY48$135.00$120.00$100.00$120.00$166.00$100.00
33Rock channel protection, type C with filter (601E32200)CY3$245.00$100.00$200.00$254.00$239.00$200.00
34Concrete masonry (602E20000)CY1$1,750.00$2,000.00$3,650.00$842.00$730.00$1,200.00
35Soil analysis test (659E00100)EACH2$90.00$200.00$150.00$160.00$105.00$50.00
36Topsoil (659E00300)CY427$40.00$36.00$26.00$22.00$73.00$12.00
37Seeding and mulching (659E10000)SY3,847$2.00$2.00$3.00$2.00$2.00$1.20
38Repair seeding and mulching (659E14000)SY192$0.75$4.00$2.50$0.80$1.00$1.00
39Inter-seeding (659E15000)SY192$0.10$4.00$2.30$0.10$0.11$0.20
40Commercial fertilizer (659E20000)TON0.54$645.00$1,500.00$3,000.00$690.00$678.00$800.00
41Lime (659E31000)ACRE0.79$45.00$1,500.00$500.00$48.00$47.00$5.00
42Water (659E35000)MGAL21$1.00$20.00$80.00$1.00$1.00$10.00
43Slope erosion protection (670E00500)SY1,215$2.30$2.25$5.25$2.50$2.50$2.50
44Ditch erosion protection (670E00700)SY542$2.40$2.50$5.25$2.50$2.50$2.50
45Storm water pollution prevention plan (832E15000)LS1$1,150.00$1,600.00$2,185.00$1,100.00$7,500.00$1,025.00
46Storm water pollution prevention inspections (832E15002)LS1$3,225.00$1,850.00$8,160.00$9,900.00$18,396$4,625.25
47Storm water pollution prevention inspection software (832E15010)LS1$8,600.00$9,925.00$8,600.00$11,150$10,953$14,500
48Erosion control (832E30000)EACH56,681$1.00$1.00$1.00$1.00$1.00$1.00
494" unclassified pipe underdrains (605E05200)FT25$45.00$12.00$13.00$31.00$37.00$35.00
504" base pipe underdrains (605E06000)FT3,002$13.32$10.00$14.00$16.00$26.00$13.00
51Aggregate drains (605E31100)FT25$35.00$11.00$32.00$14.00$21.00$18.00
524" conduit, type F (611E00406)FT25$45.00$14.00$25.00$13.00$29.00$35.00
534" conduit, type F for underdrain outlet (611E00410)FT123$15.00$14.00$25.00$40.00$37.00$40.00
548" conduit, type C (611E02000)FT5$100.00$32.00$86.00$194.00$72.00$250.00
5512" conduit, type D (611E04900)FT140$80.00$34.00$45.00$56.00$90.00$90.00
5615" conduit, type B (611E05900)FT204$125.00$85.00$91.00$160.00$127.00$200.00
5715" conduit, type C (611E06100)FT26$100.00$60.00$76.00$124.00$129.00$160.00
5815" conduit, type D (611E06400)FT43$100.00$60.00$42.00$79.00$100.00$120.00
5924" conduit, type D (611E10900)FT286$145.00$95.00$80.00$73.00$105.00$300.00
60Catch basin, no. 3 (611E98150)EACH3$7,800.00$5,600.00$4,000.00$5,000.00$5,832.00$6,500.00
61Catch basin, no. 2-2B (611E98470)EACH3$5,800.00$3,200.00$2,800.00$2,822.00$4,614.00$4,200.00
62Catch basin reconstructed to grade, as per plan (611E98635)EACH1$2,850.00$1,350.00$1,200.00$985.00$1,658.00$3,200.00
63Manhole, no. 3 (611E99574)EACH2$8,900.00$6,450.00$3,800.00$4,730.00$7,042.00$6,600.00
64Precast reinforced concrete outlet (611E99710)EACH4$850.00$400.00$650.00$292.00$567.00$550.00
65Asphalt concrete base, PG64-22, (449) (301E56000)CY796$200.00$166.00$199.00$178.00$166.00$215.00
66Aggregate base (304E20000)CY1,380$70.00$70.00$63.00$77.00$72.00$80.00
67Tack coat (407E10000)GAL831$2.50$2.55$3.50$3.00$3.00$2.50
68Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY11$500.00$555.00$333.00$594.00$555.00$860.00
69Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700)CY7$500.00$400.00$256.00$428.00$400.00$860.00
70Asphalt concrete surface course, 12.5 MM, type A (446), as per plan (442E10001)CY310$315.00$364.00$330.00$390.00$364.00$449.00
71Asphalt concrete intermediate course, 12.5 MM, type A (446) (442E10080)CY315$245.00$250.00$226.00$267.00$250.00$290.00
728" reinforced concrete pavement, class QC 1P, as per plan (451E13011)SY148$95.00$108.00$140.00$156.00$200.00$150.00
736" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011)SY485$84.00$77.00$145.00$105.00$105.00$79.00
748" non-reinforced concrete pavement, class QC 1P (452E12010)SY362$70.00$67.00$90.00$100.00$110.00$88.00
75Curb, type 2-A (609E14000)FT236$10.00$13.75$6.00$21.00$12.00$5.00
76Combination curb and gutter, type 3 (609E18000)FT1,235$15.00$23.00$30.00$40.00$32.00$22.00
77Curb, type 3-B, as per plan (609E22001)FT327$15.00$15.50$27.00$28.00$32.00$20.50
78Curb, type 4-C (609E24510)FT701$12.00$16.00$33.00$37.00$42.00$20.00
79Curb, type 6 (609E26000)FT695$12.00$16.00$33.00$38.00$61.00$20.00
804" conduit, type E (611E00400)FT100$2.00$16.00$10.00$5.00$2.00$40.00
81Precast reinforced concrete outlet (611E99710)EACH5$800.00$400.00$650.00$375.00$800.00$425.00
82Connection, fused pull apart (625E00450)EACH72$130.00$110.00$145.00$120.00$130.00$175.00
83Light pole, conventional, 30' pole, 10' bracket AR (625E10490)EACH8$3,100.00$3,100.00$3,200.00$3,420.00$3,100.00$6,000.00
84Light pole, conventional, 30' pole, 15' bracket AR (625E10490)EACH1$3,200.00$3,300.00$3,400.00$3,650.00$3,200.00$6,700.00
85Light pole, conventional, 30' pole, 20' bracket AR (625E10490)EACH1$3,400.00$3,300.00$3,900.00$3,200.00$3,400.00$7,100.00
86Light pole foundation, 24" X 6' deep (625E14000)EACH10$1,200.00$1,565.00$1,900.00$1,600.00$1,200.00$2,800.00
87No. 4 AWG 2400 volt distribution cable (625E23200)FT351$4.00$3.70$4.50$4.00$4.00$13.00
88No. 12 AWG pole and bracket cable (625E23410)FT1,395$1.00$1.94$1.90$1.00$1.00$2.00
891-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320)FT1,098$18.50$12.00$15.00$12.00$18.50$25.00
90Conduit, 3", 725.04 (625E25500)FT113$25.00$31.00$30.00$32.00$25.00$68.00
91Conduit, jacked or drilled, 725.04, 3" (625E25902)FT172$45.00$50.00$125.00$50.00$45.00$85.00
92Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH10$410.00$440.00$725.00$450.00$410.00$1,100.00
93Trench, 24" deep (625E29002)FT950$10.00$11.00$12.00$12.00$11.00$15.00
94Pull box, 725.08, 18" (625E30700)EACH7$1,000.00$1,100.00$950.00$1,200.00$1,051.00$1,800.00
95Ground rod (625E32000)EACH10$300.00$265.00$350.00$270.00$315.00$350.00
96Power service, as per plan (625E34001)EACH1$2,500.00$2,396.00$6,800.00$2,600.00$2,628.00$10,000
97Control center cabinet, complete (625E34450)EACH1$4,400.00$8,700.00$5,500.00$9,000.00$4,625.00$6,400.00
98Underground warning marking tape (625E36010)FT950$2.00$3.00$3.50$3.00$2.00$4.50
99Controller work pad, as per plan (633E67201)EACH1$1,000.00$300.00$900.00$320.00$1,051.00$5,100.00
100Delineator, post surface mounted (620E60000)EACH8$165.00$165.00$125.00$128.00$200.00$95.00
101RPM (621E00100)EACH108$61.25$61.25$61.25$69.00$68.00$67.38
102Raised pavement marker removed (621E54000)EACH48$10.00$20.00$35.00$12.00$11.00$42.00
103Barrier reflector, type 2 (BI-directional) (626E00110)EACH6$15.00$15.00$10.00$16.00$16.00$13.00
104Ground mounted support, no. 3 post (630E03100)FT329.40$17.00$17.00$12.00$18.00$18.00$17.00
105Ground mounted support, no. 4 post (630E04100)FT164.50$18.00$18.00$14.00$19.00$19.00$18.00
106Street name sign support, no. 3 post (630E08520)FT11$16.90$16.90$13.00$18.00$18.00$16.90
107Sign post reflector (630E08600)EACH28$45.00$45.00$65.00$48.00$47.00$45.00
108Sign support assembly, pole mounted (630E79500)EACH4$225.00$225.00$95.00$241.00$237.00$225.00
109Sign, flat sheet (630E80100)SF338.22$15.00$15.00$14.00$16.00$16.00$15.00
110Sign, double faced, street name (630E80500)EACH1$195.00$195.00$145.00$209.00$205.00$195.00
111Removal of ground mounted sign and disposal (630E84900)EACH40$10.00$10.00$45.00$11.00$11.00$10.00
112Removal of ground mounted sign and reerection (630E85100)EACH3$65.00$65.00$125.00$70.00$68.00$65.00
113Removal of ground mounted sign and delivery (630E85200)EACH1$50.00$50.00$55.00$54.00$53.00$50.00
114Removal of ground mounted post support and disposal (630E86002)EACH34$15.00$15.00$60.00$16.00$21.00$15.00
115Signing, misc.: 6" PVC pipe (630E97700)EACH9$45.00$45.00$725.00$48.00$53.00$90.00
116Edge line, 6" (644E00104)MI1.18$6,000.00$6,000.00$2,800.00$6,420.00$7,359.00$7,955.00
117Center line (644E00300)MI0.47$10,000$10,000$7,500.00$10,700$8,410.00$10,320
118Transverse/diagonal line (644E00700)FT166$7.00$7.00$9.00$7.00$11.00$5.50
119Lane arrow (644E01300)EACH4$100.00$100.00$145.00$107.00$131.00$200.00
120Dotted line, 6" (644E01510)FT174$3.00$3.00$5.00$3.00$2.00$1.50
121Yield line (644E20800)FT63$10.00$10.00$15.00$11.00$21.00$8.50
122Special - stone mulch (690E98300)SY453$48.00$60.00$60.00$53.00$105.00$40.00
123Law enforcement officer with patrol car for assistance (614E11110)HR120$50.00$90.00$50.00$75.00$68.00$105.00
124Detour signing (614E12420)LS1$10,000$10,000$22,850$12,000$15,000$15,000
125Portable changeable message sign, as per plan (614E18601)SNMT12$1,150.00$1,000.00$900.00$1,050.00$762.00$700.00
126Work zone center line, class I, 642 paint (614E21100)MI0.47$2,500.00$2,500.00$2,500.00$2,600.00$3,926.00$3,005.00
127Work zone edge line, class I, 6", 642 paint (614E22110)MI1.18$1,500.00$1,500.00$1,100.00$1,600.00$2,355.00$2,415.00
128Work zone dotted line, class I, 6", 642 paint (614E24202)FT174$1.00$1.00$3.00$1.00$3.00$1.00
129Work zone transverse/diagonal line, class I, 642 paint (614E25200)FT166$3.00$3.00$3.00$3.00$5.00$3.50
130Work zone arrow, class I, 642 paint (614E30200)EACH4$40.00$40.00$85.00$43.00$102.00$100.00
131Roads for maintaining traffic (615E10000)LS1$11,330$32,000$25,000$16,000$25,848$7,500.00
132Water (616E10000)MGAL35$25.00$15.00$80.00$65.00$43.00$150.00
133Temporary lighting (625E39000)LS1$20,000$15,000$30,000$9,000.00$21,024$26,250
134Yield line, type 1 (642E20802)FT64$5.00$5.00$5.00$5.00$11.00$8.50
135Premium for contract performance bond and for payment bond (103E05000)LS1$23,500$16,000$15,000$13,000$28,000$9,000.00
136Maintaining traffic (614E11000)LS1$6,000.00$15,000$12,000$24,000$21,961$67,000
137Field office, type B (619E16010)MNTH10$600.00$1,200.00$2,000.00$4,250.00$683.00$4,800.00
138Construction layout stakes and surveying (623E10000)LS1$18,000$20,900$28,000$20,000$30,000$32,000
139Mobilization (624E10000)LS1$67,650$100,000$73,000$88,000$49,390$102,000
ODOT contract 250016: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy