ODOT contract 250033 bid tabulation
D09-Guardrail Project FY2025 (GUARDRAIL REBUILDING). Let by Ohio DOT on January 16, 2025, District 9. 4 bids received; low bid $608,511 by PDK Construction Inc, -18% against the engineer's estimate of $738,000.
- Owner
- Ohio DOT
- Letting
- 16 JAN 2025
- Pay items
- 34
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | PDK Construction Inc | $608,511 | Low | -18% |
| 2 | M P Dory Co | $698,943 | +15% | -5.0% |
| 3 | Lake Erie Construction Company | $719,275 | +18% | -3.0% |
| 4 | Cuyahoga Fence LLC | $796,860 | +31% | +8.0% |
Engineer's estimate: $738,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. PDK Construction Inc | 2. M P Dory Co | 3. Lake Erie Construction Company | 4. Cuyahoga Fence LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $500.00 | $2,500.00 | $1,150.00 | $2,500.00 |
| 2 | Guardrail removed (202E38000) | FT | 1,275 | $1.80 | $2.50 | $2.40 | $3.00 |
| 3 | Guardrail removed, as per plan (202E38001) | FT | 100 | $1.60 | $3.00 | $3.00 | $2.00 |
| 4 | Guardrail removed for storage, as per plan (202E38101) | FT | 12,812.50 | $2.00 | $3.50 | $2.80 | $3.50 |
| 5 | Anchor assembly removed, type A (202E42000) | EACH | 50 | $230.00 | $350.00 | $365.00 | $350.00 |
| 6 | Anchor assembly removed, type T (202E42040) | EACH | 12 | $160.00 | $120.00 | $120.00 | $125.00 |
| 7 | Bridge terminal assembly removed (202E47000) | EACH | 4 | $150.00 | $120.00 | $150.00 | $150.00 |
| 8 | Borrow (203E40000) | CY | 1,732 | $50.00 | $50.00 | $60.00 | $68.00 |
| 9 | Linear grading, as per plan (209E60201) | STA | 173 | $12.00 | $150.00 | $35.00 | $150.00 |
| 10 | Deep beam bridge retrofit railing (517E75600) | FT | 100 | $107.54 | $112.00 | $128.00 | $125.00 |
| 11 | Guardrail, type 5 (606E13000) | FT | 100 | $16.80 | $22.00 | $19.40 | $21.00 |
| 12 | Guardrail, type MGS (606E15050) | FT | 12,887.50 | $16.86 | $19.00 | $19.60 | $21.50 |
| 13 | Guardrail, type MGS with long posts (606E15100) | FT | 1,725 | $18.26 | $20.50 | $22.40 | $24.50 |
| 14 | Guardrail, type MGS, 25' long-span (606E17350) | FT | 100 | $22.38 | $28.00 | $22.00 | $25.00 |
| 15 | Anchor assembly, MGS type B (606E26050) | EACH | 2 | $2,320.00 | $2,400.00 | $2,795.00 | $1,950.00 |
| 16 | Anchor assembly, type E (606E26100) | EACH | 4 | $2,180.00 | $2,450.00 | $2,725.00 | $2,550.00 |
| 17 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 37 | $2,180.00 | $2,500.00 | $2,750.00 | $2,650.00 |
| 18 | Anchor assembly, type T (606E26500) | EACH | 25 | $1,000.00 | $900.00 | $825.00 | $1,300.00 |
| 19 | Bridge terminal assembly, type 4 (606E35140) | EACH | 4 | $590.00 | $950.00 | $1,080.00 | $1,100.00 |
| 20 | Special - mailbox support system, single (690E50100) | EACH | 15 | $100.00 | $100.00 | $150.00 | $150.00 |
| 21 | Special - mailbox support system, double (690E50200) | EACH | 5 | $200.00 | $200.00 | $260.00 | $175.00 |
| 22 | Special - mailbox removed and reset (690E50350) | EACH | 25 | $50.00 | $50.00 | $120.00 | $75.00 |
| 23 | Seeding and mulching (659E10000) | SY | 14,417 | $1.07 | $2.50 | $1.00 | $1.75 |
| 24 | Repair seeding and mulching (659E14000) | SY | 721 | $1.07 | $1.00 | $0.50 | $0.50 |
| 25 | Commercial fertilizer (659E20000) | TON | 1.95 | $1,605.00 | $685.00 | $370.00 | $500.00 |
| 26 | Lime (659E31000) | ACRE | 3 | $214.00 | $155.00 | $50.00 | $75.00 |
| 27 | Water (659E35000) | MGAL | 78 | $1.00 | $10.00 | $1.00 | $1.00 |
| 28 | Barrier reflector, type 3 BI-directional (626E00112) | EACH | 206 | $9.00 | $12.00 | $13.00 | $13.00 |
| 29 | Ground mounted support, no. 3 post (630E03100) | FT | 100 | $13.00 | $15.00 | $12.00 | $15.00 |
| 30 | Removal of ground mounted sign and reerection (630E85100) | EACH | 25 | $50.00 | $50.00 | $55.00 | $75.00 |
| 31 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,300.00 | $7,000.00 | $3,735.00 | $7,750.00 |
| 32 | Maintaining traffic (614E11000) | LS | 1 | $53,300 | $5,000.00 | $18,500 | $25,000 |
| 33 | Mobilization (624E10000) | LS | 1 | $6,600.00 | $25,000 | $46,500 | $25,000 |
| 100 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.