ODOT contract 250037 bid tabulation

HOL-SR 515-00.15 (CULVERT REPLACEMENT). Let by Ohio DOT on January 16, 2025, HOL. 5 bids received; low bid $594,539 by Shelly & Sands Inc, -6.5% against the engineer's estimate of $636,000.

Owner
Ohio DOT
Letting
16 JAN 2025
Pay items
78
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly & Sands Inc$594,539Low-7.0%
2Ohio-West Virginia Excavating Co$685,120+15%+8.0%
3Adena Corporation$810,492+36%+27%
4Dennison Bridge Inc$874,809+47%+38%
5Stanley Miller Construction Company$894,330+50%+41%
ODOT contract 250037: bids by rank

Engineer's estimate: $636,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly & Sands Inc2. Ohio-West Virginia Excavating Co3. Adena Corporation4. Dennison Bridge Inc5. Stanley Miller Construction Company
1Clearing and grubbing (201E11000)LS1$750.00$3,500.00$2,927.53$1,000.00$1,352.00
2Pavement removed (202E23000)SY595$15.00$21.00$23.55$35.00$34.00
3Walk removed (202E30000)SF71$4.00$25.00$15.07$30.00$38.00
4Curb removed (202E32000)FT278$2.00$15.00$10.53$10.00$14.00
5Pipe removed, 24" and under (202E35100)FT100$11.00$45.00$23.60$35.00$27.00
6Pipe removed, over 24" diameter (202E35200)FT30$55.00$150.00$88.12$50.00$100.00
7Guardrail removed (202E38000)FT252$3.00$12.00$9.36$3.00$8.50
8Catch basin removed (202E58100)EACH6$250.00$1,400.00$487.92$1,000.00$800.00
9Special - fill and plug existing conduit (202E70000)FT93$37.00$60.00$34.19$50.00$82.00
10Removal misc.: landscaping removed (202E98000)LS1$950.00$2,000.00$786.72$5,000.00$3,529.00
11Removal misc.: piling removed (202E98000)LS1$13,500$10,000$9,440.73$20,000$14,705
12Removal misc.: commercial sign removed (202E98100)EACH1$400.00$2,000.00$786.72$2,500.00$1,352.00
13Removal misc.: landscape lighting removed (202E98100)EACH3$400.00$450.00$65.56$2,000.00$450.00
14Removal misc.: conduit (202E98200)FT50$15.00$35.00$94.40$35.00$56.00
15Excavation (203E10000)CY13$140.00$125.00$400.66$50.00$88.00
16Embankment (203E20000)CY140$22.00$75.00$91.26$75.00$108.00
17Subgrade compaction (204E10000)SY669$7.00$5.00$3.52$5.00$2.00
18Guardrail, type MGS half post spacing, as per plan (606E15151)FT212.50$35.50$54.46$40.34$36.00$37.00
19Anchor assembly, MGS type A (606E25550)EACH1$2,000.00$3,403.50$3,151.95$2,600.00$2,941.00
20Anchor assembly, MGS type T (606E26550)EACH1$1,700.00$3,403.50$2,395.48$2,000.00$2,235.00
21Fence, misc.: temporary orange plastic constructio (607E98000)FT550$5.00$5.00$1.64$15.00$7.00
224" concrete walk (608E10000)SF71$25.00$40.00$84.24$40.00$45.00
23Walkway, misc.:existing brick walk removed and rep (608E98000)SF625$33.00$28.00$24.17$75.00$20.00
24Soil analysis test (659E00100)EACH2$125.00$150.00$100.00$100.00$150.00
25Topsoil (659E00300)CY35$95.00$85.00$76.51$85.00$55.00
26Seeding and mulching (659E10000)SY313$13.75$15.00$5.33$13.00$5.00
27Repair seeding and mulching (659E14000)SY16$12.00$10.00$1.00$20.00$2.00
28Commercial fertilizer (659E20000)TON0.04$950.00$1,200.00$1,576.00$2,000.00$800.00
29Lime (659E31000)ACRE0.06$167.00$300.00$1,050.67$500.00$150.00
30Water (659E35000)MGAL2$1.00$2.00$1.00$1.00$1.00
31Erosion control (832E30000)EACH5,000$1.00$1.00$1.00$1.00$1.00
326" conduit, type B (611E00900)FT10$80.00$55.00$91.20$125.00$50.00
338" conduit, type B (611E01800)FT26$100.00$165.00$40.18$150.00$50.00
3412" conduit, type B (611E04400)FT133$141.00$150.00$108.10$275.00$35.00
3512" conduit, type C (611E04600)FT11$250.00$275.00$96.27$275.00$100.00
3615" conduit, type B (611E05900)FT6$330.00$300.00$201.01$325.00$250.00
3718" conduit, type B (611E07400)FT8$240.00$300.00$251.62$500.00$300.00
3818" conduit, type B, as per plan (611E07401)FT30$250.00$525.00$140.06$500.00$100.00
39Conduit, misc.: type E for drainage discharge cont (611E97400)FT50$65.00$20.00$4.00$125.00$50.00
40Catch basin, no. 3 (611E98150)EACH1$4,700.00$5,000.00$4,040.80$8,000.00$4,500.00
41Catch basin, no. 3A (611E98180)EACH1$5,700.00$5,500.00$4,187.05$24,000$4,500.00
42Catch basin, no. 6 (611E98370)EACH1$3,600.00$4,500.00$2,749.76$4,000.00$4,500.00
43Catch basin, no. 2-2B (611E98470)EACH1$3,200.00$3,500.00$2,181.15$4,000.00$4,500.00
44Catch basin, no. 2-2C (611E98504)EACH1$3,500.00$4,500.00$2,733.37$4,000.00$4,500.00
45Pavement planing, asphalt concrete (1 1/4") (254E01000)SY761$10.00$11.00$18.91$20.00$14.00
46Asphalt concrete base, PG64-22, (449) (301E56000)CY123$280.00$290.00$322.44$400.00$353.00
47Aggregate base (304E20000)CY101$130.00$125.00$111.62$140.00$180.00
48Non-tracking tack coat (407E20000)GAL156$4.00$10.00$7.56$10.00$17.00
49Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100)CY46$370.00$450.00$806.29$360.00$482.00
50Asphalt concrete intermediate course, type 2, (449) (441E70300)CY27$345.00$500.00$868.67$400.00$411.00
518" non-reinforced concrete pavement, class QC 1P (452E12010)SY65$170.00$200.00$134.69$250.00$539.00
52Curb, type 6 (609E26000)FT270$40.00$70.00$56.66$80.00$60.00
53RPM (621E00100)EACH11$325.00$400.00$81.95$350.00$76.00
54Raised pavement marker removed (621E54000)EACH11$20.00$35.00$50.00$50.00$150.00
55Barrier reflector, type 2, (bidirectional) (626E00110)EACH6$12.00$50.00$16.39$15.00$15.00
56Edge line, 6" (646E10010)MI0.16$20,615$15,000$43,320$30,000$14,352
57Center line (646E10200)MI0.08$35,317$25,000$57,763$55,000$24,590
58Detour signing (614E12420)LS1$4,800.00$5,500.00$5,288.97$10,000$6,000.00
59Asphalt concrete for maintaining traffic (614E13000)CY50$290.00$300.00$400.00$250.00$700.00
60Portable changeable message sign, as per plan (614E18601)SNMT12$1,000.00$2,000.00$1,197.74$1,500.00$2,000.00
61Work zone center line, class III, 642 paint (614E21550)MI0.16$7,805.00$5,000.00$9,840.38$15,000$5,360.00
62Work zone edge line, class III, 6", 642 paint (614E22360)MI0.32$5,855.00$2,500.00$7,381.88$10,000$2,900.00
63Water (616E10000)MGAL15$50.00$8.00$1.00$1.00$2.00
64Unclassified excavation, as per plan (503E21101)CY474$40.00$35.00$221.49$105.00$80.00
65Steel piles HP12X53, furnished (507E00200)FT1,080$40.00$45.00$41.97$50.00$40.00
66Class QC1 concrete, footing, as per plan (511E46511)CY30$475.00$550.00$451.52$600.00$682.00
67Porous backfill with geotextile fabric (518E21200)CY134$135.00$135.00$272.91$200.00$156.00
686" perforated corrugated plastic pipe (518E40000)FT210$5.00$10.00$36.71$10.00$20.00
696" non-perforated corrugated plastic pipe (518E40012)FT3$35.00$10.00$430.17$30.00$1,200.00
70Drilled shafts, 24" diameter, above bedrock, as per plan (524E94503)FT637$75.00$70.00$145.99$95.00$130.00
71Drilled shafts, 24" diameter, into bedrock, as per plan (524E94505)FT72$125.00$165.00$200.04$125.00$85.00
72Special - retaining wall, precast concrete lagging (530E51010)SF2,016$28.00$35.00$29.30$42.00$50.00
73Special - drilling through obstructions (690E98600)HR10$725.00$500.00$1,863.43$400.00$1,857.00
74Premium for contract performance bond and for payment bond (103E05000)LS1$3,846.00$9,000.00$10,212$15,000$15,000
75Maintaining traffic (614E11000)LS1$4,000.00$17,000$16,785$15,000$49,000
76Field office, type B (619E16010)MNTH6$3,800.00$2,000.00$240.00$1,500.00$1,500.00
77Construction layout stakes and surveying (623E10000)LS1$13,500$6,200.00$8,938.94$5,000.00$30,000
78Mobilization (624E10000)LS1$30,000$20,000$13,387$25,000$49,000
ODOT contract 250037: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy