ODOT contract 250037 bid tabulation
HOL-SR 515-00.15 (CULVERT REPLACEMENT). Let by Ohio DOT on January 16, 2025, HOL. 5 bids received; low bid $594,539 by Shelly & Sands Inc, -6.5% against the engineer's estimate of $636,000.
- Owner
- Ohio DOT
- Letting
- 16 JAN 2025
- Pay items
- 78
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $594,539 | Low | -7.0% |
| 2 | Ohio-West Virginia Excavating Co | $685,120 | +15% | +8.0% |
| 3 | Adena Corporation | $810,492 | +36% | +27% |
| 4 | Dennison Bridge Inc | $874,809 | +47% | +38% |
| 5 | Stanley Miller Construction Company | $894,330 | +50% | +41% |
Engineer's estimate: $636,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Ohio-West Virginia Excavating Co | 3. Adena Corporation | 4. Dennison Bridge Inc | 5. Stanley Miller Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $750.00 | $3,500.00 | $2,927.53 | $1,000.00 | $1,352.00 |
| 2 | Pavement removed (202E23000) | SY | 595 | $15.00 | $21.00 | $23.55 | $35.00 | $34.00 |
| 3 | Walk removed (202E30000) | SF | 71 | $4.00 | $25.00 | $15.07 | $30.00 | $38.00 |
| 4 | Curb removed (202E32000) | FT | 278 | $2.00 | $15.00 | $10.53 | $10.00 | $14.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 100 | $11.00 | $45.00 | $23.60 | $35.00 | $27.00 |
| 6 | Pipe removed, over 24" diameter (202E35200) | FT | 30 | $55.00 | $150.00 | $88.12 | $50.00 | $100.00 |
| 7 | Guardrail removed (202E38000) | FT | 252 | $3.00 | $12.00 | $9.36 | $3.00 | $8.50 |
| 8 | Catch basin removed (202E58100) | EACH | 6 | $250.00 | $1,400.00 | $487.92 | $1,000.00 | $800.00 |
| 9 | Special - fill and plug existing conduit (202E70000) | FT | 93 | $37.00 | $60.00 | $34.19 | $50.00 | $82.00 |
| 10 | Removal misc.: landscaping removed (202E98000) | LS | 1 | $950.00 | $2,000.00 | $786.72 | $5,000.00 | $3,529.00 |
| 11 | Removal misc.: piling removed (202E98000) | LS | 1 | $13,500 | $10,000 | $9,440.73 | $20,000 | $14,705 |
| 12 | Removal misc.: commercial sign removed (202E98100) | EACH | 1 | $400.00 | $2,000.00 | $786.72 | $2,500.00 | $1,352.00 |
| 13 | Removal misc.: landscape lighting removed (202E98100) | EACH | 3 | $400.00 | $450.00 | $65.56 | $2,000.00 | $450.00 |
| 14 | Removal misc.: conduit (202E98200) | FT | 50 | $15.00 | $35.00 | $94.40 | $35.00 | $56.00 |
| 15 | Excavation (203E10000) | CY | 13 | $140.00 | $125.00 | $400.66 | $50.00 | $88.00 |
| 16 | Embankment (203E20000) | CY | 140 | $22.00 | $75.00 | $91.26 | $75.00 | $108.00 |
| 17 | Subgrade compaction (204E10000) | SY | 669 | $7.00 | $5.00 | $3.52 | $5.00 | $2.00 |
| 18 | Guardrail, type MGS half post spacing, as per plan (606E15151) | FT | 212.50 | $35.50 | $54.46 | $40.34 | $36.00 | $37.00 |
| 19 | Anchor assembly, MGS type A (606E25550) | EACH | 1 | $2,000.00 | $3,403.50 | $3,151.95 | $2,600.00 | $2,941.00 |
| 20 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,700.00 | $3,403.50 | $2,395.48 | $2,000.00 | $2,235.00 |
| 21 | Fence, misc.: temporary orange plastic constructio (607E98000) | FT | 550 | $5.00 | $5.00 | $1.64 | $15.00 | $7.00 |
| 22 | 4" concrete walk (608E10000) | SF | 71 | $25.00 | $40.00 | $84.24 | $40.00 | $45.00 |
| 23 | Walkway, misc.:existing brick walk removed and rep (608E98000) | SF | 625 | $33.00 | $28.00 | $24.17 | $75.00 | $20.00 |
| 24 | Soil analysis test (659E00100) | EACH | 2 | $125.00 | $150.00 | $100.00 | $100.00 | $150.00 |
| 25 | Topsoil (659E00300) | CY | 35 | $95.00 | $85.00 | $76.51 | $85.00 | $55.00 |
| 26 | Seeding and mulching (659E10000) | SY | 313 | $13.75 | $15.00 | $5.33 | $13.00 | $5.00 |
| 27 | Repair seeding and mulching (659E14000) | SY | 16 | $12.00 | $10.00 | $1.00 | $20.00 | $2.00 |
| 28 | Commercial fertilizer (659E20000) | TON | 0.04 | $950.00 | $1,200.00 | $1,576.00 | $2,000.00 | $800.00 |
| 29 | Lime (659E31000) | ACRE | 0.06 | $167.00 | $300.00 | $1,050.67 | $500.00 | $150.00 |
| 30 | Water (659E35000) | MGAL | 2 | $1.00 | $2.00 | $1.00 | $1.00 | $1.00 |
| 31 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 32 | 6" conduit, type B (611E00900) | FT | 10 | $80.00 | $55.00 | $91.20 | $125.00 | $50.00 |
| 33 | 8" conduit, type B (611E01800) | FT | 26 | $100.00 | $165.00 | $40.18 | $150.00 | $50.00 |
| 34 | 12" conduit, type B (611E04400) | FT | 133 | $141.00 | $150.00 | $108.10 | $275.00 | $35.00 |
| 35 | 12" conduit, type C (611E04600) | FT | 11 | $250.00 | $275.00 | $96.27 | $275.00 | $100.00 |
| 36 | 15" conduit, type B (611E05900) | FT | 6 | $330.00 | $300.00 | $201.01 | $325.00 | $250.00 |
| 37 | 18" conduit, type B (611E07400) | FT | 8 | $240.00 | $300.00 | $251.62 | $500.00 | $300.00 |
| 38 | 18" conduit, type B, as per plan (611E07401) | FT | 30 | $250.00 | $525.00 | $140.06 | $500.00 | $100.00 |
| 39 | Conduit, misc.: type E for drainage discharge cont (611E97400) | FT | 50 | $65.00 | $20.00 | $4.00 | $125.00 | $50.00 |
| 40 | Catch basin, no. 3 (611E98150) | EACH | 1 | $4,700.00 | $5,000.00 | $4,040.80 | $8,000.00 | $4,500.00 |
| 41 | Catch basin, no. 3A (611E98180) | EACH | 1 | $5,700.00 | $5,500.00 | $4,187.05 | $24,000 | $4,500.00 |
| 42 | Catch basin, no. 6 (611E98370) | EACH | 1 | $3,600.00 | $4,500.00 | $2,749.76 | $4,000.00 | $4,500.00 |
| 43 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $3,200.00 | $3,500.00 | $2,181.15 | $4,000.00 | $4,500.00 |
| 44 | Catch basin, no. 2-2C (611E98504) | EACH | 1 | $3,500.00 | $4,500.00 | $2,733.37 | $4,000.00 | $4,500.00 |
| 45 | Pavement planing, asphalt concrete (1 1/4") (254E01000) | SY | 761 | $10.00 | $11.00 | $18.91 | $20.00 | $14.00 |
| 46 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 123 | $280.00 | $290.00 | $322.44 | $400.00 | $353.00 |
| 47 | Aggregate base (304E20000) | CY | 101 | $130.00 | $125.00 | $111.62 | $140.00 | $180.00 |
| 48 | Non-tracking tack coat (407E20000) | GAL | 156 | $4.00 | $10.00 | $7.56 | $10.00 | $17.00 |
| 49 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 46 | $370.00 | $450.00 | $806.29 | $360.00 | $482.00 |
| 50 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 27 | $345.00 | $500.00 | $868.67 | $400.00 | $411.00 |
| 51 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 65 | $170.00 | $200.00 | $134.69 | $250.00 | $539.00 |
| 52 | Curb, type 6 (609E26000) | FT | 270 | $40.00 | $70.00 | $56.66 | $80.00 | $60.00 |
| 53 | RPM (621E00100) | EACH | 11 | $325.00 | $400.00 | $81.95 | $350.00 | $76.00 |
| 54 | Raised pavement marker removed (621E54000) | EACH | 11 | $20.00 | $35.00 | $50.00 | $50.00 | $150.00 |
| 55 | Barrier reflector, type 2, (bidirectional) (626E00110) | EACH | 6 | $12.00 | $50.00 | $16.39 | $15.00 | $15.00 |
| 56 | Edge line, 6" (646E10010) | MI | 0.16 | $20,615 | $15,000 | $43,320 | $30,000 | $14,352 |
| 57 | Center line (646E10200) | MI | 0.08 | $35,317 | $25,000 | $57,763 | $55,000 | $24,590 |
| 58 | Detour signing (614E12420) | LS | 1 | $4,800.00 | $5,500.00 | $5,288.97 | $10,000 | $6,000.00 |
| 59 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $290.00 | $300.00 | $400.00 | $250.00 | $700.00 |
| 60 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,000.00 | $2,000.00 | $1,197.74 | $1,500.00 | $2,000.00 |
| 61 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.16 | $7,805.00 | $5,000.00 | $9,840.38 | $15,000 | $5,360.00 |
| 62 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.32 | $5,855.00 | $2,500.00 | $7,381.88 | $10,000 | $2,900.00 |
| 63 | Water (616E10000) | MGAL | 15 | $50.00 | $8.00 | $1.00 | $1.00 | $2.00 |
| 64 | Unclassified excavation, as per plan (503E21101) | CY | 474 | $40.00 | $35.00 | $221.49 | $105.00 | $80.00 |
| 65 | Steel piles HP12X53, furnished (507E00200) | FT | 1,080 | $40.00 | $45.00 | $41.97 | $50.00 | $40.00 |
| 66 | Class QC1 concrete, footing, as per plan (511E46511) | CY | 30 | $475.00 | $550.00 | $451.52 | $600.00 | $682.00 |
| 67 | Porous backfill with geotextile fabric (518E21200) | CY | 134 | $135.00 | $135.00 | $272.91 | $200.00 | $156.00 |
| 68 | 6" perforated corrugated plastic pipe (518E40000) | FT | 210 | $5.00 | $10.00 | $36.71 | $10.00 | $20.00 |
| 69 | 6" non-perforated corrugated plastic pipe (518E40012) | FT | 3 | $35.00 | $10.00 | $430.17 | $30.00 | $1,200.00 |
| 70 | Drilled shafts, 24" diameter, above bedrock, as per plan (524E94503) | FT | 637 | $75.00 | $70.00 | $145.99 | $95.00 | $130.00 |
| 71 | Drilled shafts, 24" diameter, into bedrock, as per plan (524E94505) | FT | 72 | $125.00 | $165.00 | $200.04 | $125.00 | $85.00 |
| 72 | Special - retaining wall, precast concrete lagging (530E51010) | SF | 2,016 | $28.00 | $35.00 | $29.30 | $42.00 | $50.00 |
| 73 | Special - drilling through obstructions (690E98600) | HR | 10 | $725.00 | $500.00 | $1,863.43 | $400.00 | $1,857.00 |
| 74 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,846.00 | $9,000.00 | $10,212 | $15,000 | $15,000 |
| 75 | Maintaining traffic (614E11000) | LS | 1 | $4,000.00 | $17,000 | $16,785 | $15,000 | $49,000 |
| 76 | Field office, type B (619E16010) | MNTH | 6 | $3,800.00 | $2,000.00 | $240.00 | $1,500.00 | $1,500.00 |
| 77 | Construction layout stakes and surveying (623E10000) | LS | 1 | $13,500 | $6,200.00 | $8,938.94 | $5,000.00 | $30,000 |
| 78 | Mobilization (624E10000) | LS | 1 | $30,000 | $20,000 | $13,387 | $25,000 | $49,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.