ODOT contract 250117 bid tabulation
DEF-US 24-11.35(Independence Rd) (INTERCHANGE). Let by Ohio DOT on February 27, 2025, DEF. 3 bids received; low bid $5,336,584 by E S Wagner Company, -32% against the engineer's estimate of $7,850,000.
- Owner
- Ohio DOT
- Letting
- 27 FEB 2025
- Pay items
- 154
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | E S Wagner Company | $5,336,584 | Low | -32% |
| 2 | Miller Bros Const Inc | $5,486,087 | +3.0% | -30% |
| 3 | Vernon Nagel Inc | $5,732,337 | +7.0% | -27% |
Engineer's estimate: $7,850,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E S Wagner Company | 2. Miller Bros Const Inc | 3. Vernon Nagel Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $34,708 | $25,000 | $15,000 |
| 2 | Pavement removed (202E23000) | SY | 5,201 | $8.50 | $4.40 | $5.00 |
| 3 | Pavement removed, as per plan (202E23001) | SY | 4,252 | $5.00 | $9.00 | $10.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 975 | $20.00 | $10.00 | $8.00 |
| 5 | Pipe removed, over 24" diameter (202E35200) | FT | 320 | $28.50 | $50.00 | $10.00 |
| 6 | Catch basin removed (202E58100) | EACH | 1 | $305.00 | $400.00 | $225.00 |
| 7 | Fence removed (202E75000) | FT | 2,313 | $2.00 | $2.00 | $4.00 |
| 8 | Excavation (203E10000) | CY | 2,762 | $8.54 | $8.00 | $13.50 |
| 9 | Embankment (203E20000) | CY | 82,304 | $9.68 | $11.60 | $13.50 |
| 10 | Subgrade compaction (204E10000) | SY | 7,993 | $1.77 | $1.40 | $1.00 |
| 11 | Excavation of subgrade (204E13000) | CY | 209 | $8.54 | $17.50 | $18.00 |
| 12 | Embankment (204E20000) | CY | 209 | $9.68 | $21.00 | $13.00 |
| 13 | Geotextile fabric (204E50000) | SY | 627 | $1.57 | $1.50 | $1.30 |
| 14 | Special - geocell, SUBGRADE6?, geoweb (204E60000) | SY | 324 | $47.00 | $55.00 | $28.00 |
| 15 | Guardrail, type MGS, as per plan (606E15051) | FT | 988 | $20.40 | $20.40 | $20.40 |
| 16 | Guardrail, barrier design, type MGS, as per plan (606E15551) | FT | 151 | $34.00 | $34.00 | $34.00 |
| 17 | Anchor assembly, MGS type emash 2016 (606E26150) | EACH | 4 | $2,580.00 | $2,580.00 | $2,580.00 |
| 18 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,320.00 | $1,320.00 | $1,320.00 |
| 19 | MGS bridge terminal assembly, type 1, as per plan (606E35003) | EACH | 4 | $2,550.00 | $2,550.00 | $2,550.00 |
| 20 | Impact attenuator, type 1 (bidirectional) (606E60012) | EACH | 2 | $8,120.00 | $8,120.00 | $8,120.00 |
| 21 | Fence, type 47, as per plan (607E15001) | FT | 1,820 | $13.60 | $13.60 | $13.60 |
| 22 | Concrete barrier, single slope, type D (622E10160) | FT | 308 | $113.00 | $113.00 | $113.00 |
| 23 | Monument assembly, type C (623E38500) | EACH | 1 | $2,000.00 | $1,250.00 | $800.00 |
| 24 | Monument assembly removed and reset (623E40000) | EACH | 1 | $2,000.00 | $1,200.00 | $800.00 |
| 25 | Right-of-way monument, type B (623E40520) | EACH | 1 | $1,000.00 | $100.00 | $350.00 |
| 26 | Monument, misc.: mag spike to BE set during constr (623E40900) | EACH | 12 | $200.00 | $50.00 | $500.00 |
| 27 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $5,000.00 | $2,000.00 | $3,000.00 |
| 28 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,000.00 | $2,000.00 | $1,000.00 |
| 29 | Ground rod (625E32000) | EACH | 4 | $320.00 | $320.00 | $265.00 |
| 30 | Special - mailbox support system, single (690E50100) | EACH | 2 | $630.00 | $180.00 | $180.00 |
| 31 | Special - mailbox removed and reset (690E50350) | EACH | 2 | $395.00 | $700.00 | $195.00 |
| 32 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 13 | $193.00 | $185.00 | $125.00 |
| 33 | Rock channel protection, type C with aggregate filter (601E32210) | CY | 19 | $249.50 | $122.00 | $125.00 |
| 34 | Soil analysis test (659E00100) | EACH | 2 | $40.00 | $40.00 | $40.00 |
| 35 | Topsoil (659E00300) | CY | 4,030 | $7.50 | $8.50 | $5.00 |
| 36 | Seeding and mulching (659E10000) | SY | 33,928 | $0.74 | $0.74 | $1.00 |
| 37 | Seeding and mulching, as per plan (659E10001) | SY | 2,559 | $0.74 | $0.74 | $0.74 |
| 38 | Repair seeding and mulching (659E14000) | SY | 1,815 | $3.10 | $0.74 | $0.74 |
| 39 | Inter-seeding (659E15000) | SY | 1,815 | $0.50 | $0.50 | $0.50 |
| 40 | Commercial fertilizer (659E20000) | TON | 4.90 | $850.00 | $850.00 | $850.00 |
| 41 | Lime (659E31000) | ACRE | 7.50 | $35.00 | $35.00 | $35.00 |
| 42 | Water (659E35000) | MGAL | 196 | $1.00 | $1.00 | $1.00 |
| 43 | Slope erosion protection (670E00500) | SY | 11,728 | $1.80 | $1.80 | $1.80 |
| 44 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $1,025.00 | $2,000.00 |
| 45 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $8,825.00 | $6,650.00 | $9,500.00 |
| 46 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $11,020 | $10,200 | $12,000 |
| 47 | Erosion control (832E30000) | EACH | 40,000 | $1.00 | $1.00 | $1.00 |
| 48 | Concrete masonry (602E20000) | CY | 20.30 | $671.95 | $1,200.00 | $1,200.00 |
| 49 | 4" base pipe underdrains (605E06000) | FT | 3,230 | $8.00 | $9.40 | $12.00 |
| 50 | 6" shallow pipe underdrains with geotextile fabric (605E11110) | FT | 1,835 | $21.00 | $18.70 | $15.00 |
| 51 | 6" unclassified pipe underdrains (605E13300) | FT | 50 | $22.00 | $19.00 | $20.00 |
| 52 | 4" conduit, type C (611E00200) | FT | 22 | $36.00 | $62.50 | $25.00 |
| 53 | 4" conduit, type E (611E00400) | FT | 50 | $25.00 | $22.50 | $15.00 |
| 54 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 137 | $36.00 | $37.00 | $20.00 |
| 55 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 123 | $45.00 | $45.00 | $22.00 |
| 56 | 6" conduit, type C (611E01100) | FT | 527 | $33.00 | $40.00 | $32.00 |
| 57 | 8" conduit, type C (611E02000) | FT | 87 | $127.00 | $52.00 | $30.00 |
| 58 | 10" conduit, type E (611E03600) | FT | 10 | $91.00 | $32.00 | $25.00 |
| 59 | 12" conduit, type B (611E04400) | FT | 124 | $87.00 | $75.00 | $50.00 |
| 60 | 12" conduit, type C (611E04600) | FT | 338 | $47.00 | $68.00 | $45.00 |
| 61 | 12" conduit, type D (611E04900) | FT | 250 | $73.00 | $65.00 | $48.00 |
| 62 | 12" conduit, type F (611E05200) | FT | 168 | $95.00 | $66.00 | $88.00 |
| 63 | 15" conduit, type C (611E06100) | FT | 382 | $53.00 | $83.00 | $56.00 |
| 64 | 27" conduit, type B (611E11900) | FT | 226 | $140.00 | $151.00 | $90.00 |
| 65 | 30" conduit, type A, 706.02 or 707.33; or 36? type (611E13200) | FT | 158 | $145.00 | $159.00 | $95.00 |
| 66 | 36" conduit, type A (611E16200) | FT | 440 | $155.00 | $170.00 | $100.00 |
| 67 | Catch basin, no. 2-2A, as per plan (611E98451) | EACH | 3 | $3,100.00 | $2,100.00 | $1,500.00 |
| 68 | Inlet, no. 3 for single slope barrier, type D (611E99114) | EACH | 4 | $11,000 | $10,000 | $10,500 |
| 69 | Manhole, no. 3 (611E99574) | EACH | 1 | $5,700.00 | $4,500.00 | $6,500.00 |
| 70 | Precast reinforced concrete outlet (611E99710) | EACH | 13 | $600.00 | $330.00 | $400.00 |
| 71 | Pavement planing, asphalt concrete, 3" (254E01000) | SY | 118 | $10.00 | $10.00 | $10.00 |
| 72 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 769 | $210.00 | $210.00 | $210.00 |
| 73 | Aggregate base (304E20000) | CY | 1,785 | $68.00 | $65.00 | $60.00 |
| 74 | Non-tracking tack coat (407E20000) | GAL | 802 | $2.00 | $2.00 | $2.75 |
| 75 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 237 | $275.00 | $275.00 | $250.00 |
| 76 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 331 | $240.00 | $240.00 | $225.00 |
| 77 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 3 | $500.00 | $500.00 | $250.00 |
| 78 | Curb, type 4-C (609E24510) | FT | 74 | $61.10 | $54.60 | $65.00 |
| 79 | Rumble strips, shoulder (asphalt concrete) (618E40100) | FT | 1,865 | $3.63 | $3.25 | $3.75 |
| 80 | Structure grounding system, as per plan (625E33001) | EACH | 1 | $7,829.00 | $14,500 | $14,500 |
| 81 | Barrier reflector, type 1 (bidirectional) (626E00102) | EACH | 10 | $11.60 | $11.60 | $11.60 |
| 82 | Barrier reflector, type 2 (1 way) (626E00110) | EACH | 8 | $13.00 | $13.00 | $13.00 |
| 83 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 12 | $13.40 | $13.40 | $13.40 |
| 84 | Sign, temporary overlay (630E80300) | SF | 18 | $35.00 | $35.00 | $35.00 |
| 85 | Removal of ground mounted sign and disposal (630E84900) | EACH | 34 | $30.00 | $30.00 | $30.00 |
| 86 | Removal of ground mounted post support and disposal (630E86002) | EACH | 51 | $30.00 | $30.00 | $30.00 |
| 87 | Removal of pavement marking (642E30000) | FT | 100 | $46.90 | $46.90 | $1.00 |
| 88 | Edge line, 4" (643E00100) | MI | 0.88 | $4,510.00 | $4,510.00 | $4,510.00 |
| 89 | Edge line, 6" (643E00104) | MI | 1.09 | $4,510.00 | $4,510.00 | $4,510.00 |
| 90 | Lane line, 6" (643E00204) | MI | 0.54 | $1,910.00 | $1,910.00 | $1,910.00 |
| 91 | Center line (643E00300) | MI | 0.44 | $6,940.00 | $6,940.00 | $6,940.00 |
| 92 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 64 | $103.33 | $85.00 | $80.00 |
| 93 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 6 | $2,380.00 | $2,380.00 | $2,380.00 |
| 94 | Detour signing (614E12420) | LS | 1 | $7,000.00 | $7,000.00 | $7,000.00 |
| 95 | Replacement sign (614E12500) | EACH | 10 | $356.00 | $192.00 | $192.00 |
| 96 | Replacement drum (614E12600) | EACH | 50 | $64.00 | $56.00 | $56.00 |
| 97 | Barrier reflector, type 1 (1 way) (614E13310) | EACH | 140 | $10.26 | $8.00 | $8.00 |
| 98 | Object marker, one way (614E13350) | EACH | 140 | $27.22 | $16.00 | $16.00 |
| 99 | Portable changeable message sign, as per plan (614E18601) | SNMT | 20 | $800.00 | $850.00 | $850.00 |
| 100 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 1 | $10,000 | $10,000 | $10,000 |
| 101 | Water (616E10000) | MGAL | 240 | $50.00 | $15.00 | $2.00 |
| 102 | Portable barrier, unanchored (622E41100) | FT | 6,954 | $11.50 | $10.00 | $22.00 |
| 103 | Embankment (203E20000) | CY | 924 | $10.00 | $18.00 | $18.00 |
| 104 | Granular material, type B (203E35110) | CY | 390 | $80.00 | $60.00 | $55.00 |
| 105 | Special - settlement platform (203E65000) | EACH | 4 | $2,300.00 | $750.00 | $600.00 |
| 106 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 448 | $23.25 | $25.00 | $42.00 |
| 107 | 6" non-perforated corrugated plastic pipe, including specials, as per plan (518E40011) | FT | 189 | $14.43 | $16.50 | $10.00 |
| 108 | Crushed aggregate slope protection, as per plan (601E20001) | SY | 30 | $59.65 | $95.00 | $26.00 |
| 109 | Paved gutter, misc.: concrete gutter adjacent to C (601E40000) | FT | 344 | $37.04 | $50.00 | $35.00 |
| 110 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $565.61 | $330.00 | $450.00 |
| 111 | Mechanically stabilized earth wall (840E20000) | SF | 4,758 | $65.00 | $65.00 | $65.00 |
| 112 | Wall excavation (840E21000) | CY | 1,593 | $15.00 | $5.00 | $7.00 |
| 113 | Foundation preparation, as per plan (840E22001) | SY | 764 | $65.62 | $70.00 | $58.00 |
| 114 | Select granular backfill (840E23000) | CY | 3,751 | $62.00 | $60.00 | $62.00 |
| 115 | Natural soil (840E23050) | CY | 309 | $20.39 | $13.00 | $12.00 |
| 116 | 6" drainage pipe, perforated (840E25010) | FT | 721 | $8.96 | $3.70 | $8.00 |
| 117 | Concrete coping (840E26000) | FT | 344 | $185.68 | $124.00 | $140.00 |
| 118 | On-site assistance (840E27000) | DAY | 5 | $100.00 | $600.00 | $100.00 |
| 119 | SGB inspection and compaction testing (840E28000) | LS | 1 | $17,948 | $9,160.00 | $15,000 |
| 120 | Unclassified excavation (503E21300) | LS | 1 | $10,445 | $10,000 | $2,500.00 |
| 121 | Pile driving equipment mobilization (505E11100) | LS | 1 | $14,044 | $79,000 | $25,000 |
| 122 | Steel piles HP10X42, furnished (507E00100) | FT | 6,140 | $38.50 | $25.00 | $45.00 |
| 123 | Steel piles HP10X42, driven (507E00150) | FT | 5,805 | $11.00 | $19.00 | $10.00 |
| 124 | Epoxy coated steel reinforcement (509E10000) | LB | 116,400 | $1.36 | $1.40 | $1.45 |
| 125 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 8,365 | $1.63 | $1.80 | $2.00 |
| 126 | Class QC2 concrete with QC/QA, superstructure (511E33418) | CY | 67 | $962.34 | $810.00 | $800.00 |
| 127 | Semi-integral diaphragm guide, as per plan (511E33501) | EACH | 2 | $4,204.53 | $3,350.00 | $3,600.00 |
| 128 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 262 | $942.63 | $750.00 | $950.00 |
| 129 | Class QC2 concrete with QC/QA, bridge deck (parapet), as per plan (511E34451) | CY | 74 | $665.00 | $705.00 | $700.00 |
| 130 | Class QC1 concrete with QC/QA, pier above footings (511E41512) | CY | 17 | $866.49 | $870.00 | $1,000.00 |
| 131 | Class QC1 concrete with QC/QA, pier cap (511E42512) | CY | 29 | $1,060.79 | $1,000.00 | $975.00 |
| 132 | Class QC1 concrete with QC/QA, abutment including footing (511E43512) | CY | 217 | $572.27 | $540.00 | $700.00 |
| 133 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 41 | $473.19 | $530.00 | $500.00 |
| 134 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,261 | $17.86 | $22.00 | $42.00 |
| 135 | Type E waterproofing (512E44450) | SY | 8 | $19.21 | $49.00 | $30.00 |
| 136 | Draped strand prestressed concrete bridge I-beam members, level 3, type WF48-49 (515E15090) | EACH | 10 | $60,000 | $61,000 | $67,000 |
| 137 | Intermediate diaphragms (515E20000) | EACH | 24 | $2,600.00 | $1,150.00 | $1,800.00 |
| 138 | Armorless preformed joint seal (516E10010) | FT | 76 | $70.42 | $40.00 | $44.00 |
| 139 | 1" preformed expansion joint filler (516E13600) | SF | 21 | $10.01 | $7.00 | $10.00 |
| 140 | 2" preformed expansion joint filler (516E13900) | SF | 89 | $8.42 | $7.50 | $8.00 |
| 141 | Semi-integral abutment expansion joint seal (516E14020) | FT | 103 | $34.34 | $25.00 | $38.00 |
| 142 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 10 | $3,742.56 | $1,650.00 | $3,700.00 |
| 143 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 10 | $2,180.21 | $3,100.00 | $1,900.00 |
| 144 | Porous backfill with geotextile fabric (518E21200) | CY | 50 | $88.84 | $135.00 | $80.00 |
| 145 | 6" perforated corrugated plastic pipe (518E40000) | FT | 198 | $17.26 | $9.50 | $10.00 |
| 146 | Reinforced concrete approach slabs with QC/QA (T=1 (526E30010) | SY | 236 | $300.00 | $360.00 | $350.00 |
| 147 | Type C installation (526E90030) | FT | 80 | $163.65 | $170.00 | $200.00 |
| 148 | Vandal protection fence, 6' straight, coated fabric (607E39900) | FT | 390 | $90.80 | $90.80 | $90.80 |
| 149 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $25,000 | $38,000 | $40,000 |
| 150 | Maintaining traffic (614E11000) | LS | 1 | $45,000 | $75,500 | $50,000 |
| 151 | Field office, type B (619E16010) | MNTH | 8 | $2,100.00 | $2,200.00 | $2,300.00 |
| 152 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,000 | $22,970 | $25,000 |
| 153 | Mobilization (624E10000) | LS | 1 | $200,000 | $274,304 | $200,000 |
| 200 | Removal misc.:, billboard to BE removed (202E98100) | EACH | 1 | $2,300.00 | $2,200.00 | $611.69 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.