ODOT contract 250185 bid tabulation
ATH-US 50-33.58 (INTERSECTION). Let by Ohio DOT on April 10, 2025, ATH. 3 bids received; low bid $3,195,538 by Axis Civil Construction LLC, -1.7% against the engineer's estimate of $3,252,000.
- Owner
- Ohio DOT
- Letting
- 10 APR 2025
- Pay items
- 141
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Axis Civil Construction LLC | $3,195,538 | Low | -2.0% |
| 2 | Shelly & Sands Inc | $3,469,964 | +9.0% | +7.0% |
| 3 | Alan Stone Co Inc | $3,551,085 | +11% | +9.0% |
Engineer's estimate: $3,252,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Axis Civil Construction LLC | 2. Shelly & Sands Inc | 3. Alan Stone Co Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $57,000 | $6,500.00 |
| 2 | Pavement removed (202E23000) | SY | 5,330 | $13.50 | $17.00 | $12.00 |
| 3 | Curb removed (202E32000) | FT | 63 | $12.00 | $3.50 | $15.00 |
| 4 | Gutter removed (202E32700) | SY | 4 | $80.00 | $55.00 | $260.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 295 | $25.00 | $35.00 | $45.00 |
| 6 | Pipe removed, over 24" diameter (202E35200) | FT | 12 | $50.00 | $25.00 | $20.00 |
| 7 | Guardrail removed (202E38000) | FT | 46 | $8.00 | $5.00 | $7.00 |
| 8 | Anchor assembly removed, type E (202E42010) | EACH | 1 | $700.00 | $250.00 | $340.00 |
| 9 | Anchor assembly removed, type T (202E42040) | EACH | 1 | $700.00 | $150.00 | $200.00 |
| 10 | Catch basin removed (202E58100) | EACH | 2 | $1,300.00 | $225.00 | $290.00 |
| 11 | Excavation (203E10000) | CY | 20,617 | $22.35 | $29.00 | $20.00 |
| 12 | Embankment (203E20000) | CY | 1,612 | $23.00 | $27.00 | $15.00 |
| 13 | Subgrade compaction (204E10000) | SY | 11,191 | $2.50 | $4.50 | $3.50 |
| 14 | Guardrail, type MGS (606E15050) | FT | 75 | $48.00 | $48.00 | $65.00 |
| 15 | Anchor assembly, MGS type B (606E26050) | EACH | 1 | $2,600.00 | $2,600.00 | $3,500.00 |
| 16 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,250.00 | $1,250.00 | $1,700.00 |
| 17 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $125.00 | $170.00 |
| 18 | Topsoil (659E00300) | CY | 2,404 | $40.00 | $22.00 | $10.00 |
| 19 | Seeding and mulching (659E10000) | SY | 18,942 | $0.80 | $0.81 | $1.00 |
| 20 | Repair seeding and mulching (659E14000) | SY | 948 | $0.80 | $0.80 | $1.00 |
| 21 | Inter-seeding (659E15000) | SY | 948 | $0.80 | $0.80 | $1.00 |
| 22 | Commercial fertilizer (659E20000) | TON | 2.71 | $1,250.00 | $850.00 | $900.00 |
| 23 | Lime (659E31000) | ACRE | 3.92 | $150.00 | $155.00 | $180.00 |
| 24 | Water (659E35000) | MGAL | 105 | $1.00 | $1.00 | $1.00 |
| 25 | Slope erosion protection (670E00500) | SY | 2,430 | $2.50 | $1.35 | $1.50 |
| 26 | Ditch erosion protection (670E00700) | SY | 279 | $2.50 | $1.40 | $1.50 |
| 27 | Ditch erosion protection mat, type E (670E00750) | SY | 687 | $3.00 | $2.20 | $2.50 |
| 28 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $3,000.00 | $3,000.00 |
| 29 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $10,800 | $8,500.00 | $9,000.00 |
| 30 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $11,095 | $9,200.00 | $12,000 |
| 31 | Erosion control (832E30000) | EACH | 75,000 | $1.00 | $1.00 | $1.00 |
| 32 | Seeding and erosion control with turf reinforcing mat, type 2 (836E10020) | SY | 45 | $6.00 | $5.50 | $7.00 |
| 33 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 10 | $165.00 | $200.00 | $460.00 |
| 34 | Concrete masonry (602E20000) | CY | 0.50 | $3,200.00 | $3,700.00 | $2,600.00 |
| 35 | 4" shallow pipe underdrains (605E05100) | FT | 2,400 | $18.00 | $17.00 | $18.00 |
| 36 | 6" shallow pipe underdrains (605E11100) | FT | 1,251 | $18.00 | $22.00 | $18.00 |
| 37 | 6" unclassified pipe underdrains (605E13300) | FT | 100 | $20.00 | $22.00 | $20.00 |
| 38 | Aggregate drains (605E31100) | FT | 50 | $20.00 | $17.00 | $30.00 |
| 39 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 106 | $25.00 | $25.00 | $18.00 |
| 40 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 8 | $30.00 | $34.00 | $25.00 |
| 41 | 6" conduit, type F (611E01500) | FT | 50 | $13.00 | $20.00 | $30.00 |
| 42 | 15" conduit, type B (611E05900) | FT | 504 | $80.00 | $105.00 | $170.00 |
| 43 | 15" conduit, type C (611E06100) | FT | 336 | $95.00 | $95.00 | $210.00 |
| 44 | 24" conduit, type C (611E10600) | FT | 6 | $250.00 | $255.00 | $430.00 |
| 45 | 27" conduit, type C (611E12100) | FT | 12 | $450.00 | $255.00 | $820.00 |
| 46 | Slotted drain, type 1, 15" (611E97000) | FT | 475 | $170.00 | $160.00 | $240.00 |
| 47 | Catch basin, no. 3A (611E98180) | EACH | 1 | $3,900.00 | $4,500.00 | $6,400.00 |
| 48 | Catch basin, no. 6 (611E98370) | EACH | 1 | $3,500.00 | $4,100.00 | $5,800.00 |
| 49 | Catch basin, no. 8 (611E98410) | EACH | 3 | $4,600.00 | $6,300.00 | $7,000.00 |
| 50 | Manhole, no. 3 (611E99574) | EACH | 2 | $4,600.00 | $4,500.00 | $5,500.00 |
| 51 | Manhole adjusted to grade (611E99654) | EACH | 2 | $1,200.00 | $1,000.00 | $780.00 |
| 52 | Precast reinforced concrete outlet (611E99710) | EACH | 7 | $400.00 | $450.00 | $590.00 |
| 53 | Pavement planing, asphalt concrete (depth = 1.5") (254E01000) | SY | 614 | $14.00 | $14.00 | $20.00 |
| 54 | Asphalt concrete base, PG64-22, (449) (302E56000) | CY | 2,633 | $230.00 | $230.00 | $240.00 |
| 55 | Aggregate base (304E20000) | CY | 1,921 | $95.50 | $90.00 | $110.00 |
| 56 | Non-tracking tack coat (407E20000) | GAL | 1,804 | $3.50 | $3.50 | $4.00 |
| 57 | Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100) | CY | 453 | $305.00 | $305.00 | $295.00 |
| 58 | Asphalt concrete intermediate course, 12.5 MM, type A (449) (442E22300) | CY | 499 | $295.00 | $295.00 | $340.00 |
| 59 | Curb, type 4-C (609E24510) | FT | 1,075 | $28.00 | $43.00 | $25.00 |
| 60 | 6" concrete traffic island (609E54000) | SY | 334 | $125.00 | $100.00 | $90.00 |
| 61 | Connection, fused pull apart (625E00450) | EACH | 26 | $110.00 | $110.00 | $150.00 |
| 62 | Connection, unfused pull apart (625E00460) | EACH | 6 | $110.00 | $110.00 | $150.00 |
| 63 | Connection, unfused permanent (625E00480) | EACH | 28 | $110.00 | $110.00 | $150.00 |
| 64 | Light pole, conventional, design AT12B40 (625E10490) | EACH | 4 | $3,600.00 | $3,600.00 | $4,900.00 |
| 65 | Light pole, conventional, design AT15B40 (625E10490) | EACH | 2 | $3,750.00 | $3,750.00 | $5,100.00 |
| 66 | Light pole, conventional, design AT18B40 (625E10490) | EACH | 5 | $4,100.00 | $4,100.00 | $5,600.00 |
| 67 | Light pole, conventional, design AT20B40 (625E10490) | EACH | 3 | $4,200.00 | $4,200.00 | $5,700.00 |
| 68 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 14 | $2,350.00 | $2,350.00 | $3,200.00 |
| 69 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 1,206 | $2.75 | $2.75 | $3.50 |
| 70 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,576 | $1.75 | $1.75 | $2.50 |
| 71 | 1-1/2" duct cable with two no. 4 AWG 2400 volt cables (625E24100) | FT | 984 | $9.00 | $9.00 | $10.00 |
| 72 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 2,087 | $11.40 | $11.40 | $15.00 |
| 73 | Conduit, 3", 725.04 (625E25500) | FT | 121 | $29.00 | $29.00 | $40.00 |
| 74 | Conduit, jacked or drilled, 725.04, 3" (625E25902) | FT | 241 | $49.00 | $49.00 | $65.00 |
| 75 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 10 | $375.00 | $375.00 | $510.00 |
| 76 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 4 | $375.00 | $375.00 | $510.00 |
| 77 | Trench (625E29000) | FT | 2,871 | $12.00 | $12.00 | $15.00 |
| 78 | Trench in paved area (625E29400) | FT | 121 | $38.00 | $38.00 | $50.00 |
| 79 | Pull box, 725.08, 18" (625E30700) | EACH | 10 | $1,050.00 | $1,050.00 | $1,400.00 |
| 80 | Ground rod (625E32000) | EACH | 14 | $265.00 | $265.00 | $360.00 |
| 81 | Power service, as per plan (625E34001) | EACH | 1 | $9,200.00 | $9,200.00 | $12,000 |
| 82 | Underground warning marking tape (625E36010) | FT | 2,992 | $3.00 | $3.00 | $4.00 |
| 83 | Special - maintain existing lighting (625E40000) | LS | 1 | $12,250 | $12,500 | $17,000 |
| 84 | Special - replacement of existing lighting unit (625E40010) | EACH | 2 | $850.00 | $850.00 | $1,200.00 |
| 85 | Light pole removed (625E75400) | EACH | 1 | $350.00 | $350.00 | $470.00 |
| 86 | Light pole foundation removed (625E75500) | EACH | 1 | $350.00 | $350.00 | $470.00 |
| 87 | Luminaire removed (625E75506) | EACH | 1 | $75.00 | $75.00 | $100.00 |
| 88 | Arc flash calculations and label, (PS-'1') (625E76000) | EACH | 1 | $4,048.70 | $4,050.00 | $5,500.00 |
| 89 | Delineator, post surface mounted (620E60000) | EACH | 16 | $155.00 | $155.00 | $210.00 |
| 90 | RPM (621E00100) | EACH | 266 | $35.00 | $35.00 | $45.00 |
| 91 | Barrier reflector, type 2, one way (626E00110) | EACH | 5 | $12.00 | $12.00 | $15.00 |
| 92 | Ground mounted support, no. 2 post (630E02100) | FT | 165.50 | $12.00 | $12.00 | $15.00 |
| 93 | Ground mounted support, no. 3 post (630E03100) | FT | 746.50 | $12.50 | $12.50 | $15.00 |
| 94 | Ground mounted structural beam support, S4X7.7 (630E06400) | FT | 59.30 | $22.00 | $22.00 | $30.00 |
| 95 | Ground mounted structural beam support, W6X9 (630E06500) | FT | 63.40 | $23.00 | $23.00 | $30.00 |
| 96 | Ground mounted structural beam support, W10X12 (630E07600) | FT | 44.40 | $28.00 | $28.00 | $40.00 |
| 97 | Street name sign support, no. 3 post (630E08520) | FT | 12.50 | $20.00 | $20.00 | $25.00 |
| 98 | Sign post reflector (630E08600) | EACH | 24 | $45.00 | $45.00 | $60.00 |
| 99 | Breakaway structural beam connection (630E09000) | EACH | 6 | $450.00 | $450.00 | $610.00 |
| 100 | Breakaway structural beam connection, as per plan (630E09001) | EACH | 4 | $1,250.00 | $1,250.00 | $1,700.00 |
| 101 | Sign attachment assembly (630E75000) | EACH | 3 | $950.00 | $950.00 | $1,300.00 |
| 102 | Sign, flat sheet (630E80100) | SF | 404.10 | $20.00 | $20.00 | $25.00 |
| 103 | Sign, ground mounted extrusheet (630E80200) | SF | 168 | $25.00 | $25.00 | $35.00 |
| 104 | Sign, overhead extrusheet (630E80224) | SF | 196 | $25.00 | $25.00 | $35.00 |
| 105 | Ground mounted structural beam support foundation (630E84500) | EACH | 10 | $750.00 | $750.00 | $1,000.00 |
| 106 | Removal of ground mounted sign and disposal (630E84900) | EACH | 28 | $20.00 | $20.00 | $25.00 |
| 107 | Removal of ground mounted sign and reerection (630E85100) | EACH | 6 | $100.00 | $100.00 | $140.00 |
| 108 | Removal of ground mounted major sign and reerection (630E85600) | EACH | 2 | $650.00 | $650.00 | $880.00 |
| 109 | Removal of ground mounted post support and disposal (630E86002) | EACH | 29 | $20.00 | $20.00 | $25.00 |
| 110 | Removal of ground mounted structural beam support (630E86102) | EACH | 4 | $650.00 | $350.00 | $470.00 |
| 111 | Edge line, 6" (646E10010) | MI | 1.72 | $6,245.00 | $2,500.00 | $7,500.00 |
| 112 | Lane line, 6" (646E10110) | MI | 1.72 | $2,711.00 | $1,900.00 | $3,700.00 |
| 113 | Center line (646E10200) | MI | 0.28 | $10,095 | $3,700.00 | $14,000 |
| 114 | Channelizing line, 12" (646E10310) | FT | 5,632 | $2.50 | $1.60 | $3.00 |
| 115 | Stop line (646E10400) | FT | 48 | $14.00 | $11.00 | $20.00 |
| 116 | Transverse/diagonal line (646E10600) | FT | 1,059 | $9.15 | $9.00 | $10.00 |
| 117 | Chevron marking (646E10620) | FT | 151 | $10.00 | $9.00 | $15.00 |
| 118 | Lane arrow (646E20300) | EACH | 24 | $180.00 | $150.00 | $240.00 |
| 119 | Lane arrow, as per plan (646E20301) | EACH | 10 | $270.00 | $150.00 | $370.00 |
| 120 | Dotted line, 6" (646E20504) | FT | 950 | $1.95 | $1.55 | $2.50 |
| 121 | Yield line (646E20800) | FT | 30 | $14.50 | $9.00 | $20.00 |
| 122 | Removal of pavement marking (646E50300) | MI | 0.27 | $9,800.00 | $5,000.00 | $13,000 |
| 123 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $65.00 | $92.00 | $90.00 |
| 124 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 9 | $2,100.00 | $2,200.00 | $2,600.00 |
| 125 | Work zone increased penalties sign (614E12484) | EACH | 5 | $100.00 | $100.00 | $140.00 |
| 126 | Work zone raised pavement marker (614E12800) | EACH | 400 | $14.25 | $14.25 | $20.00 |
| 127 | Barrier reflector, type 1, one way (614E13310) | EACH | 190 | $19.00 | $7.00 | $30.00 |
| 128 | Object marker, one way (614E13350) | EACH | 190 | $32.00 | $14.00 | $35.00 |
| 129 | Portable changeable message sign, as per plan (614E18601) | SNMT | 18 | $1,500.00 | $1,500.00 | $1,800.00 |
| 130 | Work zone lane line, class I, 6", 740.06, type I (614E20210) | MI | 0.62 | $2,800.00 | $2,800.00 | $3,800.00 |
| 131 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 4.40 | $10,250 | $10,250 | $10,500 |
| 132 | Work zone channelizing line, class I, 12", 740.06, type I (614E23410) | FT | 3,404 | $3.75 | $3.75 | $4.00 |
| 133 | Work zone dotted line, class I, 6", 740.06, type I (614E24402) | FT | 1,260 | $2.95 | $2.95 | $4.00 |
| 134 | Water (616E10000) | MGAL | 60 | $1.00 | $65.00 | $0.10 |
| 135 | Portable barrier, unanchored (622E41100) | FT | 8,860 | $20.87 | $16.00 | $15.00 |
| 136 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 60 | $850.00 | $850.00 | $1,100.00 |
| 137 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $25,000 | $19,499 | $36,000 |
| 138 | Maintaining traffic (614E11000) | LS | 1 | $40,000 | $65,750 | $90,000 |
| 139 | Field office, type B (619E16010) | MNTH | 6 | $2,200.00 | $5,500.00 | $1,500.00 |
| 140 | Construction layout stakes and surveying (623E10000) | LS | 1 | $25,000 | $40,000 | $80,000 |
| 141 | Mobilization (624E10000) | LS | 1 | $70,000 | $160,000 | $142,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way