ODOT contract 250254 bid tabulation
JEF-SR 43-08.40 (INTERSECTION). Let by Ohio DOT on May 8, 2025, JEF. 4 bids received; low bid $1,223,940 by Shelly & Sands Inc, +0.7% against the engineer's estimate of $1,215,000.
- Owner
- Ohio DOT
- Letting
- 08 MAY 2025
- Pay items
- 100
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $1,223,940 | Low | +1.0% |
| 2 | NLS Paving, Inc | $1,329,850 | +9.0% | +9.0% |
| 3 | Ohio-West Virginia Excavating Co | $1,447,483 | +18% | +19% |
| 4 | Tucson Inc | $1,538,958 | +26% | +27% |
Engineer's estimate: $1,215,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. NLS Paving, Inc | 3. Ohio-West Virginia Excavating Co | 4. Tucson Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,800.00 | $5,000.00 | $6,300.00 | $9,000.00 |
| 2 | Headwall removed (202E20010) | EACH | 1 | $500.00 | $700.00 | $1,137.26 | $380.00 |
| 3 | Pavement removed (202E23000) | SY | 1,561 | $17.00 | $36.00 | $12.65 | $33.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 65 | $8.00 | $55.00 | $14.59 | $22.00 |
| 5 | Guardrail removed (202E38000) | FT | 1,529 | $3.00 | $2.00 | $6.89 | $3.40 |
| 6 | Special - fill and plug existing conduit (202E70000) | FT | 66 | $30.00 | $65.00 | $113.37 | $43.00 |
| 7 | Removal misc.: private sign removed (202E98100) | EACH | 3 | $350.00 | $300.00 | $657.91 | $760.00 |
| 8 | Excavation (203E10000) | CY | 1,240 | $16.00 | $30.00 | $25.39 | $40.00 |
| 9 | Embankment (203E20000) | CY | 1,676 | $22.00 | $20.00 | $35.11 | $20.00 |
| 10 | Subgrade compaction (204E10000) | SY | 4,372 | $3.75 | $2.50 | $1.15 | $2.35 |
| 11 | Guardrail, type MGS (606E15050) | FT | 1,887.50 | $21.00 | $20.40 | $26.34 | $22.20 |
| 12 | Anchor assembly, MGS type E(MASH 2016) (606E26150) | EACH | 1 | $2,700.00 | $2,685.00 | $3,138.80 | $2,650.00 |
| 13 | Monument assembly adjusted to grade (623E39500) | EACH | 6 | $1,400.00 | $1,600.00 | $1,353.65 | $860.00 |
| 14 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 1 | $1,000.00 | $1,050.00 | $590.92 | $703.00 |
| 15 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $150.00 | $196.18 | $100.00 |
| 16 | Topsoil (659E00300) | CY | 662 | $21.00 | $35.00 | $83.04 | $62.00 |
| 17 | Seeding and mulching (659E10000) | SY | 5,906 | $0.90 | $1.00 | $1.18 | $3.60 |
| 18 | Repair seeding and mulching (659E14000) | SY | 295 | $0.90 | $1.00 | $1.18 | $1.00 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.80 | $1,250.00 | $1,500.00 | $1,634.79 | $2,720.00 |
| 20 | Lime (659E31000) | ACRE | 1.22 | $150.00 | $160.00 | $196.17 | $1,180.00 |
| 21 | Water (659E35000) | MGAL | 35 | $1.00 | $1.00 | $1.31 | $5.00 |
| 22 | Slope erosion protection (670E00500) | SY | 50 | $2.50 | $2.50 | $3.27 | $17.00 |
| 23 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,000.00 | $3,000.00 | $3,269.58 | $2,560.00 |
| 24 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $7,400.00 | $7,400.00 | $4,708.21 | $9,000.00 |
| 25 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $9,150.00 | $8,500.00 | $11,903 | $11,600 |
| 26 | Erosion control (832E30000) | EACH | 30,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 27 | Concrete masonry (602E20000) | CY | 0.20 | $5,000.00 | $4,500.00 | $6,499.45 | $7,050.00 |
| 28 | Aggregate drains (605E31100) | FT | 1,071 | $14.00 | $21.00 | $39.19 | $28.00 |
| 29 | 12" conduit, type B (611E04400) | FT | 98 | $182.00 | $150.00 | $185.99 | $116.00 |
| 30 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $3,000.00 | $3,025.00 | $4,512.22 | $4,000.00 |
| 31 | Pavement planing, asphalt concrete, (3") (254E01000) | SY | 2,282 | $9.00 | $8.00 | $4.68 | $10.00 |
| 32 | Pavement planing, asphalt concrete, (variable dept (254E01000) | SY | 1,160 | $13.00 | $16.00 | $4.68 | $14.35 |
| 33 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 1,083 | $210.00 | $225.00 | $270.58 | $232.00 |
| 34 | Aggregate base (304E20000) | CY | 986 | $115.00 | $135.00 | $123.02 | $121.00 |
| 35 | Tack coat (407E10000) | GAL | 1,136 | $3.50 | $3.50 | $5.89 | $4.00 |
| 36 | Prime coat, as per plan (408E10001) | GAL | 478 | $6.00 | $7.00 | $9.28 | $11.00 |
| 37 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 256 | $280.00 | $285.00 | $319.50 | $309.00 |
| 38 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 358 | $280.00 | $245.00 | $278.74 | $309.00 |
| 39 | Rumble stripes, edge line (asphalt concrete) (618E41000) | MI | 0.94 | $3,900.00 | $1,350.00 | $5,165.96 | $4,350.00 |
| 40 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 0.73 | $3,900.00 | $1,550.00 | $5,165.95 | $4,350.00 |
| 41 | 4" conduit, type E (611E00400) | FT | 60 | $5.00 | $5.00 | $13.08 | $11.00 |
| 42 | Connection, fused pull apart (625E00450) | EACH | 6 | $115.00 | $200.00 | $176.56 | $146.00 |
| 43 | Connection, unfused permanent (625E00480) | EACH | 12 | $115.00 | $200.00 | $130.78 | $108.25 |
| 44 | Light pole, conventional, design AT25B35 (625E10490) | EACH | 3 | $5,650.00 | $5,500.00 | $5,558.29 | $4,595.00 |
| 45 | Light pole foundation, 24" X 6' deep (625E14000) | EACH | 3 | $2,700.00 | $2,500.00 | $1,863.66 | $1,540.00 |
| 46 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 597 | $5.50 | $4.00 | $13.08 | $11.00 |
| 47 | No. 10 AWG pole and bracket cable (625E23400) | FT | 390 | $2.50 | $2.00 | $1.96 | $1.65 |
| 48 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 111 | $14.00 | $12.00 | $19.62 | $16.25 |
| 49 | Conduit, jacked or drilled, 725.04, 3" (625E25902) | FT | 179 | $62.00 | $65.00 | $134.71 | $111.25 |
| 50 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 3 | $590.00 | $500.00 | $817.40 | $680.00 |
| 51 | Trench, 24" deep (625E29002) | FT | 81 | $16.00 | $20.00 | $20.93 | $17.30 |
| 52 | Pull box, 725.08, 18" (625E30700) | EACH | 3 | $1,575.00 | $2,000.00 | $915.48 | $760.00 |
| 53 | Ground rod (625E32000) | EACH | 4 | $300.00 | $250.00 | $241.95 | $200.00 |
| 54 | Power service, as per plan (625E34001) | EACH | 1 | $9,950.00 | $9,000.00 | $8,239.36 | $6,805.00 |
| 55 | Underground warning marking tape (625E36010) | FT | 81 | $3.00 | $2.00 | $3.92 | $3.25 |
| 56 | Arc flash calculations and label, (jef-43-8.40) (625E76000) | EACH | 1 | $3,985.00 | $500.00 | $3,596.54 | $2,975.00 |
| 57 | RPM (621E00100) | EACH | 126 | $50.00 | $50.00 | $65.39 | $54.25 |
| 58 | Raised pavement marker removed (621E54000) | EACH | 66 | $8.00 | $10.00 | $52.95 | $8.50 |
| 59 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 41 | $12.00 | $12.00 | $14.39 | $12.00 |
| 60 | Ground mounted support, no. 2 post (630E02100) | FT | 11.40 | $12.00 | $14.00 | $18.31 | $13.00 |
| 61 | Ground mounted support, no. 3 post (630E03100) | FT | 142.90 | $13.00 | $16.00 | $19.62 | $14.00 |
| 62 | Ground mounted support, no. 4 post (630E04100) | FT | 59.30 | $22.00 | $20.00 | $24.85 | $23.75 |
| 63 | Sign post reflector (630E08600) | EACH | 11 | $35.00 | $45.00 | $39.24 | $38.00 |
| 64 | Sign, flat sheet (630E80100) | SF | 18 | $22.00 | $26.00 | $36.62 | $23.75 |
| 65 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $25.00 | $10.00 | $326.96 | $30.00 |
| 66 | Removal of ground mounted sign and reerection (630E85100) | EACH | 25 | $80.00 | $65.00 | $78.47 | $87.00 |
| 67 | Removal of ground mounted post support and disposal (630E86002) | EACH | 17 | $25.00 | $15.00 | $163.48 | $30.00 |
| 68 | Edge line, 6" (646E10010) | MI | 0.94 | $3,200.00 | $5,200.00 | $6,800.74 | $4,600.00 |
| 69 | Center line (646E10200) | MI | 0.74 | $5,300.00 | $5,900.00 | $7,716.22 | $5,675.00 |
| 70 | Channelizing line, 8" (646E10300) | FT | 760 | $2.50 | $2.20 | $2.88 | $1.65 |
| 71 | Stop line (646E10400) | FT | 34 | $9.00 | $17.00 | $22.23 | $11.00 |
| 72 | Transverse/diagonal line (646E10600) | FT | 367 | $7.00 | $13.00 | $17.00 | $11.00 |
| 73 | Island marking (646E10800) | SF | 66 | $7.00 | $13.00 | $17.00 | $16.25 |
| 74 | Lane arrow (646E20300) | EACH | 9 | $140.00 | $250.00 | $326.96 | $162.25 |
| 75 | Dotted line, 6" (646E20504) | FT | 100 | $2.25 | $4.00 | $5.23 | $1.10 |
| 76 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $108.00 | $95.00 | $100.70 | $115.00 |
| 77 | Increased barrier delineation (614E11630) | FT | 934 | $0.50 | $1.00 | $1.31 | $1.10 |
| 78 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 4 | $2,450.00 | $2,580.00 | $3,669.27 | $2,700.00 |
| 79 | Detour signing (614E12420) | LS | 1 | $5,000.00 | $4,950.00 | $6,473.78 | $5,450.00 |
| 80 | Work zone raised pavement marker (614E12800) | EACH | 482 | $12.95 | $12.95 | $16.94 | $14.25 |
| 81 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $910.00 | $500.00 | $1,059.00 | $370.00 |
| 82 | Barrier reflector, type 1 (bidirectional) (614E13310) | EACH | 64 | $8.00 | $25.00 | $32.70 | $27.75 |
| 83 | Object marker, two way (614E13360) | EACH | 64 | $12.00 | $38.00 | $49.70 | $42.00 |
| 84 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $1,500.00 | $1,500.00 | $1,961.75 | $1,655.00 |
| 85 | Work zone center line, class I, 642 paint (614E21100) | MI | 1.44 | $1,750.00 | $1,750.00 | $2,288.71 | $1,930.00 |
| 86 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.53 | $1,450.00 | $1,450.00 | $1,896.36 | $1,600.00 |
| 87 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 2.86 | $1,250.00 | $1,250.00 | $1,634.79 | $1,380.00 |
| 88 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 1.56 | $1,275.00 | $1,275.00 | $1,667.49 | $1,400.00 |
| 89 | Work zone channelizing line, class I, 8", 642 paint (614E23200) | FT | 760 | $1.65 | $1.65 | $2.16 | $2.00 |
| 90 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 595 | $1.50 | $1.50 | $1.96 | $1.75 |
| 91 | Work zone stop line, class I, 642 paint (614E26200) | FT | 42 | $14.00 | $14.00 | $18.31 | $15.50 |
| 92 | Work zone stop line, class III, 642 paint (614E26610) | FT | 21 | $13.00 | $13.00 | $17.00 | $14.35 |
| 93 | Work zone arrow, class I, 642 paint (614E30200) | EACH | 1 | $325.00 | $325.00 | $425.04 | $360.00 |
| 94 | Water (616E10000) | MGAL | 10 | $40.00 | $50.00 | $229.74 | $5.00 |
| 95 | Portable barrier, unanchored (622E41100) | FT | 3,040 | $20.00 | $20.00 | $18.09 | $50.00 |
| 96 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,000.00 | $6,395.40 | $15,446 | $20,100 |
| 97 | Maintaining traffic (614E11000) | LS | 1 | $70,000 | $80,000 | $60,700 | $110,000 |
| 98 | Field office, type B (619E16010) | MNTH | 6 | $4,400.00 | $2,500.00 | $4,180.00 | $3,000.00 |
| 99 | Construction layout stakes and surveying (623E10000) | LS | 1 | $14,400 | $30,000 | $10,400 | $25,300 |
| 100 | Mobilization (624E10000) | LS | 1 | $54,000 | $65,000 | $47,500 | $46,900 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 8, 2025. Compiled by Mirage Metrics.