ODOT contract 254012 bid tabulation
GEA-SR 528-10.71/14.87 (CULVERT REPLACEMENT). Let by Ohio DOT on March 27, 2025, GEA. 4 bids received; low bid $630,304 by Bog Construction Inc, +5.9% against the engineer's estimate of $595,000.
- Owner
- Ohio DOT
- Letting
- 27 MAR 2025
- Pay items
- 69
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Bog Construction Inc | $630,304 | Low | +6.0% |
| 2 | Northeast Ohio Trenching Service Inc | $556,624 | -12% | -6.0% |
| 3 | Shook Company LLC | $681,654 | +8.0% | +15% |
| 4 | Madex Construction Co | $789,630 | +25% | +33% |
Engineer's estimate: $595,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bog Construction Inc | 2. Northeast Ohio Trenching Service Inc | 3. Shook Company LLC | 4. Madex Construction Co |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,500.00 | $10,000 | $20,000 | $4,581.80 |
| 2 | Headwall removed (202E20010) | EACH | 4 | $500.00 | $500.00 | $1,500.00 | $916.37 |
| 3 | Pavement removed (202E23000) | SY | 427 | $40.00 | $25.00 | $35.00 | $27.97 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 4 | $300.00 | $35.00 | $50.00 | $100.07 |
| 5 | Pipe removed, over 24" diameter (202E35200) | FT | 140 | $65.00 | $50.00 | $20.00 | $85.30 |
| 6 | Guardrail removed (202E38000) | FT | 272 | $3.00 | $5.00 | $5.00 | $2.89 |
| 7 | Anchor assembly removed (202E42206) | EACH | 2 | $750.00 | $250.00 | $500.00 | $225.79 |
| 8 | Excavation (203E10000) | CY | 103 | $50.00 | $35.00 | $110.00 | $42.33 |
| 9 | Embankment (203E20000) | CY | 26 | $150.00 | $55.00 | $100.00 | $57.77 |
| 10 | Granular material, type C (203E35120) | CY | 17 | $150.00 | $85.00 | $65.00 | $186.42 |
| 11 | Subgrade compaction (204E10000) | SY | 460 | $5.00 | $2.00 | $2.00 | $2.61 |
| 12 | Proof rolling (204E45000) | HR | 2 | $50.00 | $100.00 | $100.00 | $225.78 |
| 13 | Geotextile fabric (204E50000) | SY | 98 | $10.00 | $10.00 | $5.00 | $7.44 |
| 14 | Reshaping under guardrail, as per plan (209E15001) | STA | 10 | $100.00 | $75.00 | $250.00 | $57.89 |
| 15 | Guardrail, type MGS (606E15050) | FT | 79 | $25.00 | $25.00 | $30.00 | $23.16 |
| 16 | Guardrail, type MGS with long posts (606E15100) | FT | 650 | $25.00 | $26.00 | $35.00 | $24.08 |
| 17 | Rounded end section (606E20050) | EACH | 4 | $125.00 | $100.00 | $50.00 | $98.42 |
| 18 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 4 | $3,000.00 | $2,975.00 | $3,000.00 | $3,068.42 |
| 19 | Anchor assembly, MGS type T (606E26550) | EACH | 4 | $1,500.00 | $1,600.00 | $1,500.00 | $1,597.89 |
| 20 | Riprap, type D (601E11000) | SY | 8 | $200.00 | $135.00 | $300.00 | $1,605.34 |
| 21 | Rock channel protection, type B with filter (601E32100) | CY | 20 | $150.00 | $175.00 | $200.00 | $201.63 |
| 22 | Soil analysis test (659E00100) | EACH | 2 | $50.00 | $150.00 | $25.00 | $289.47 |
| 23 | Topsoil (659E00300) | CY | 32 | $45.00 | $75.00 | $75.00 | $119.51 |
| 24 | Seeding and mulching, class 1 (659E00500) | SY | 284 | $18.00 | $1.50 | $10.00 | $8.17 |
| 25 | Repair seeding and mulching (659E14000) | SY | 15 | $10.00 | $0.75 | $0.10 | $5.02 |
| 26 | Inter-seeding (659E15000) | SY | 15 | $0.20 | $1.25 | $0.10 | $5.02 |
| 27 | Commercial fertilizer (659E20000) | TON | 0.05 | $1,000.00 | $1,100.00 | $100.00 | $4,515.60 |
| 28 | Lime (659E31000) | ACRE | 0.06 | $100.00 | $1,500.00 | $100.00 | $2,508.67 |
| 29 | Water (659E35000) | MGAL | 2 | $1.00 | $50.00 | $0.10 | $37.63 |
| 30 | Erosion control (832E30000) | EACH | 44,036 | $1.00 | $1.00 | $1.00 | $1.00 |
| 31 | Concrete masonry (602E20000) | CY | 17 | $1,100.00 | $1,200.00 | $3,155.00 | $2,161.94 |
| 32 | 6" conduit, type C (611E01100) | FT | 4 | $150.00 | $15.00 | $80.00 | $114.55 |
| 33 | 42" conduit, type A, 706.02, 707.33, 707.65 (611E19200) | FT | 51 | $500.00 | $575.00 | $600.00 | $448.58 |
| 34 | 42" conduit, type A, 706.02, or 48" type A, 707.33 (611E19200) | FT | 90 | $450.00 | $525.00 | $650.00 | $487.16 |
| 35 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 99 | $528.00 | $420.00 | $475.00 | $521.05 |
| 36 | Aggregate base (304E20000) | CY | 78 | $220.00 | $92.00 | $256.00 | $174.75 |
| 37 | Non-tracking tack coat (407E20000) | GAL | 75 | $17.00 | $35.00 | $15.00 | $17.37 |
| 38 | Asphalt concrete surface course, type 1, (449), as per plan (441E70101) | CY | 37 | $638.00 | $1,075.00 | $600.00 | $631.05 |
| 39 | Asphalt concrete intermediate course, type 1, (449), (under guardrail), as per plan (441E70801) | CY | 38 | $533.00 | $915.00 | $465.00 | $521.05 |
| 40 | RPM (621E00100) | EACH | 15 | $350.00 | $280.00 | $300.00 | $289.47 |
| 41 | Raised pavement marker removed (621E54000) | EACH | 15 | $50.00 | $25.00 | $50.00 | $57.89 |
| 42 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 15 | $15.00 | $15.00 | $10.00 | $17.37 |
| 43 | Edge line, 6", type 1 (642E00104) | MI | 0.34 | $4,200.00 | $4,000.00 | $3,200.00 | $3,687.88 |
| 44 | Center line, type 1 (642E00300) | MI | 0.18 | $500.00 | $5,000.00 | $5,500.00 | $6,339.44 |
| 45 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $35,000 | $5,000.00 | $40,000 | $68,845 |
| 46 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 112 | $40.00 | $90.00 | $85.00 | $104.21 |
| 47 | Special - work zone traffic signal (614E11300) | EACH | 1 | $45,000 | $55,000 | $44,000 | $57,895 |
| 48 | Increased barrier delineation (614E11630) | FT | 565 | $8.00 | $8.00 | $1.80 | $2.08 |
| 49 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 4 | $2,500.00 | $2,500.00 | $2,500.00 | $2,894.74 |
| 50 | Detour signing, as per plan (614E12421) | LS | 1 | $9,000.00 | $15,000 | $6,500.00 | $17,295 |
| 51 | Work zone lighting system (614E12740) | EACH | 1 | $5,000.00 | $7,500.00 | $2,000.00 | $17,368 |
| 52 | Barrier reflector, type 1 (bidirectional) (614E13310) | EACH | 12 | $15.00 | $11.50 | $30.00 | $34.74 |
| 53 | Object marker, two way (614E13360) | EACH | 12 | $25.00 | $25.00 | $35.00 | $40.53 |
| 54 | Portable changeable message sign, as per plan (614E18601) | SNMT | 8 | $1,300.00 | $1,250.00 | $1,000.00 | $1,047.89 |
| 55 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.20 | $20,000 | $18,000 | $15,600 | $18,063 |
| 56 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.35 | $7,000.00 | $3,750.00 | $7,000.00 | $8,105.26 |
| 57 | Work zone stop line, class I, 642 paint (614E26200) | FT | 24 | $30.00 | $10.00 | $7.50 | $9.26 |
| 58 | Business entrance sign, as per plan (614E40051) | EACH | 2 | $400.00 | $300.00 | $200.00 | $214.21 |
| 59 | Roads for maintaining traffic (615E10000) | LS | 1 | $10,000 | $5,000.00 | $5,000.00 | $7,562.53 |
| 60 | Water (616E10000) | MGAL | 1 | $1.00 | $5.00 | $1.00 | $75.26 |
| 61 | Portable barrier, unanchored (622E41100) | FT | 565 | $30.00 | $47.00 | $50.00 | $64.38 |
| 62 | Removal of pavement marking (642E30000) | FT | 1,331 | $3.00 | $5.00 | $5.00 | $5.33 |
| 63 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $25,000 | $9,000.00 | $20,000 | $28,526 |
| 64 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $10,000 | $35,000 | $19,958 |
| 65 | Field office, type B (619E16010) | MNTH | 5 | $1,500.00 | $500.00 | $1,750.00 | $750.00 |
| 66 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $2,500.00 | $5,000.00 | $22,158 |
| 67 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $5,500.00 | $1,000.00 | $1,000.00 | $7,242.20 |
| 68 | Post construction survey monument verification and report (623E51000) | LS | 1 | $6,500.00 | $500.00 | $1,000.00 | $5,372.20 |
| 69 | Mobilization (624E10000) | LS | 1 | $30,000 | $9,000.00 | $20,000 | $77,297 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 27, 2025. Compiled by Mirage Metrics.