ODOT contract 260235 bid tabulation

CUY-SR 8-00.52 Pedestrian (SIDEWALK). Let by Ohio DOT on May 7, 2026, CUY. 6 bids received; low bid $899,183 by R M H Concrete & Foundations Inc, -12% against the engineer's estimate of $1,018,000.

Owner
Ohio DOT
Letting
07 MAY 2026
Pay items
95
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1R M H Concrete & Foundations Inc$899,183Low-12%
2C A Agresta Construction Co$914,474+2.0%-10%
3Karvo Companies Inc$1,075,062+20%+6.0%
4Perk Company Inc$1,204,428+34%+18%
5Ruhlin Company$1,219,305+36%+20%
6Madex Construction Co$1,593,159+77%+56%
ODOT contract 260235: bids by rank

Engineer's estimate: $1,018,000.

Bid tabulation

LinePay itemUnitQuantity1. R M H Concrete & Foundations Inc2. C A Agresta Construction Co3. Karvo Companies Inc4. Perk Company Inc5. Ruhlin Company6. Madex Construction Co
1Clearing and grubbing, as per plan (201E11001)LS1$1,750.00$500.00$35,000$9,125.00$3,500.00$11,600
2Pavement removed, as per plan (202E23001)SY1,420$12.70$12.00$20.00$25.00$26.00$52.11
3Walk removed, as per plan (202E30001)SF2,505$1.80$1.00$5.00$2.65$4.35$5.79
4Curb removed, as per plan (202E32001)FT25$15.00$10.00$40.00$12.70$65.00$16.06
5Pipe removed, 24" and under (202E35100)FT42$12.75$5.00$80.00$35.10$45.00$104.21
6Guardrail removed (202E38000)FT8$80.00$75.00$200.00$6.30$125.00$86.84
7Catch basin removed (202E58100)EACH2$400.00$500.00$825.00$400.00$500.00$1,316.66
8Excavation (203E10000)CY107$55.00$40.00$125.00$63.15$40.00$110.00
9Embankment (203E20000)CY86$65.00$15.00$75.00$71.50$135.00$114.63
10Subgrade compaction (204E10000)SY1,420$1.10$1.00$2.00$1.50$5.00$4.63
11Reshaping under guardrail (209E15050)MI0.06$33,000$2,000.00$18,000$44,575$30,000$2,894.67
12Linear grading, misc.: cuyahoga county (209E98300)SY4,394$3.85$5.00$5.00$7.10$4.25$5.79
134" concrete walk (608E10000)SF24,599$7.25$9.50$6.75$12.00$10.50$11.58
14Curb ramp (608E52000)SF1,300$13.50$23.00$15.00$35.95$28.50$33.58
15Right-of-way monument, type B (623E40520)EACH24$110.00$350.00$200.00$315.00$615.00$1,013.15
16Preconstruction survey monument verification and report (623E50000)LS1$3,200.00$2,500.00$1,200.00$1,000.00$5,500.00$8,684.21
17Soil analysis test (659E00100)EACH2$275.00$100.00$250.00$500.00$400.00$289.47
18Topsoil (659E00300)CY488$79.00$40.00$65.00$96.00$51.00$75.26
19Seeding and mulching, as per plan (659E10001)SY4,394$2.95$3.50$1.00$2.75$3.00$4.63
20Commercial fertilizer (659E20000)TON0.62$1,700.00$600.00$1,125.00$1,250.00$1,500.00$2,894.74
21Lime (659E31000)ACRE0.91$1,100.00$50.00$1,625.00$1,250.00$1.00$1,389.47
22Water (659E35000)MGAL25$150.00$25.00$150.00$65.00$25.00$70.53
23Storm water pollution prevention plan (832E15000)LS1$3,100.00$3,000.00$5,000.00$2,800.00$2,800.00$2,894.74
24Storm water pollution prevention inspections (832E15002)LS1$7,500.00$500.00$15,000$4,960.00$4,494.00$5,789.47
25Storm water pollution prevention inspection software (832E15010)LS1$7,500.00$500.00$5,000.00$5,210.00$3,846.53$4,515.79
26Erosion control, as per plan (832E30001)EACH5,000$1.00$1.00$1.00$1.00$1.00$1.00
2712" conduit, type B (611E04400)FT42$51.00$120.00$500.00$117.00$400.00$202.63
2815" conduit, type B (611E05900)FT30$60.00$75.00$275.00$135.00$450.00$220.00
29Catch basin, no. 2-2B (611E98470)EACH2$2,800.00$2,500.00$3,500.00$4,380.00$4,500.00$3,357.89
30Catch basin adjusted to grade (611E98630)EACH6$950.00$650.00$1,250.00$1,600.00$500.00$1,621.05
31Catch basin reconstructed to grade (611E98634)EACH2$1,300.00$750.00$2,000.00$2,195.00$4,500.00$2,547.37
32Manhole adjusted to grade (611E99654)EACH1$470.00$650.00$1,250.00$1,605.00$750.00$2,894.74
33Special - miscellaneous metal (611E99820)LB10,000$2.65$2.00$3.00$0.75$3.00$1.00
34Manufactured water quality structure, type 2 (895E10020)EACH1$33,500$48,000$25,000$31,550$80,000$56,538
35Full depth pavement removal and rigid replacement, type 1, class QC MS (255E15000)SY72$210.00$170.00$150.00$250.00$220.00$94.32
36Full depth pavement sawing (255E20000)FT104$2.75$3.00$3.00$1.80$3.00$6.95
37Asphalt concrete base, PG64-22, (449), (driveways) (301E56100)CY6$1,600.00$500.00$750.00$1,070.00$1,500.00$2,315.79
38Aggregate base, as per plan (304E20001)CY171$80.00$85.00$125.00$86.75$240.00$149.37
39Tack coat, 702.13 (407E13900)GAL8$3.50$20.00$3.00$5.25$5.00$11.58
40Non-tracking tack coat (407E20000)GAL2$3.50$20.00$3.00$5.00$5.00$11.58
41Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY3$3,200.00$700.00$525.00$1,290.00$2,600.00$5,789.47
42Asphalt concrete intermediate course, type 2, (449) (441E70300)CY4$1,600.00$700.00$525.00$680.00$2,600.00$5,789.47
43Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY9$1,300.00$700.00$575.00$1,180.00$500.00$1,157.89
448" non-reinforced concrete pavement, class QC MS (452E12050)SY1,420$95.00$110.00$75.00$135.00$100.00$156.32
45Curb, type 6 (609E26000)FT25$45.00$40.00$35.00$100.00$115.00$115.79
46Manhole adjusted to grade, as per plan (611E99655)EACH8$475.00$650.00$1,250.00$1,600.00$750.00$2,894.74
47Valve box adjusted to grade, as per plan (638E10801)EACH9$365.00$300.00$500.00$1,130.00$450.00$926.32
48Service box adjusted to grade, as per plan (638E10901)EACH1$365.00$200.00$500.00$450.00$375.00$1,146.32
49Ground mounted support, no. 3 post (630E03100)FT72$16.00$15.00$14.50$15.00$24.45$34.74
50Sign hanger assembly, mast arm, as per plan (630E79101)EACH2$600.00$550.00$375.00$550.00$419.29$578.95
51Sign support assembly, pole mounted (630E79500)EACH4$135.00$125.00$130.00$125.00$130.00$144.74
52Sign, flat sheet (630E80100)SF37$19.00$18.00$28.09$18.00$28.00$34.74
53Removal of ground mounted sign and reerection (630E85100)EACH3$100.00$95.00$23.10$95.00$23.00$86.84
54Removal of pole mounted sign and reerection (630E87520)EACH3$135.00$125.00$55.12$125.00$55.00$162.11
55Removal of pavement marking (642E30000)FT112$21.00$20.00$19.00$20.00$10.00$17.37
56Removal of pavement marking (642E30020)EACH3$275.00$250.00$150.00$250.00$50.00$63.68
57Stop line (644E00500)FT81$10.50$10.00$12.00$10.00$9.00$11.58
58Crosswalk line, 12" (644E00620)FT887$5.50$5.00$6.00$5.00$7.00$9.26
59Crosswalk line, 24" (644E00630)FT230$10.00$9.50$8.75$9.50$9.00$11.58
60Lane arrow (644E01300)EACH3$145.00$135.00$150.00$135.00$120.00$144.74
61Conduit, 2", 725.051, as per plan (625E25409)FT169$9.00$8.50$8.50$8.50$14.50$28.95
62Conduit, 3", 725.051, as per plan (625E25505)FT4$11.00$10.00$10.00$10.00$37.00$34.74
63Conduit, jacked or drilled, 4" (625E25900)FT53$124.25$115.00$115.00$115.00$100.00$127.37
64Trench (625E29000)FT183$17.00$15.00$15.00$15.00$20.00$38.21
65Pull box, 725.08, 18" (625E30700)EACH4$1,000.00$1,000.00$950.00$950.00$1,600.00$1,852.63
66Pull box, 725.08, 24" (625E30706)EACH1$1,350.00$1,250.00$1,250.00$1,250.00$1,750.00$2,142.11
67Ground rod, as per plan (625E32001)EACH8$350.00$300.00$300.00$300.00$315.00$405.26
68Underground warning/marking tape, as per plan (625E36011)FT183$4.00$3.50$3.50$3.50$1.50$4.63
69Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH8$750.00$645.00$645.00$645.00$875.00$1,736.84
70Pedestrian pushbutton, as per plan (632E26001)EACH8$300.00$275.00$275.00$275.00$320.50$984.21
71Signal cable, 2 conductor, no. 14 AWG (632E40200)FT1,686$1.75$1.75$1.60$1.60$3.25$5.79
72Signal cable, 5 conductor, no. 14 AWG (632E40500)FT1,711$2.85$2.75$2.55$2.55$4.90$6.95
73Signal cable, 7 conductor, no. 14 AWG (632E40700)FT515$3.65$3.25$3.25$3.25$5.00$8.11
74Signal support foundation, as per plan (632E64011)EACH2$8,775.00$8,200.00$8,200.00$8,200.00$6,070.00$11,579
75Pedestal foundation (632E64020)EACH5$1,500.00$1,300.00$1,300.00$1,300.00$1,165.00$2,894.74
76Power cable, 3 conductor, no. 8 AWG (632E67300)FT13$6.50$6.00$6.00$6.00$24.00$17.37
77Service cable, 3 conductor, no. 8 AWG (632E69700)FT30$6.50$6.00$6.00$6.00$12.65$17.37
78Power service, as per plan (632E70001)EACH1$4,000.00$3,800.00$3,800.00$3,800.00$6,015.00$6,947.37
79Conduit riser, 2" diameter (632E70400)EACH1$375.00$350.00$350.00$350.00$1,220.00$1,273.68
80Signal support, type TC-81.22, design 4, as per plan (632E72111)EACH2$15,000$14,000$13,750$13,750$15,515$23,158
81Pedestal, 10.7' tall, transformer base, as per plan (632E89921)EACH5$2,300.00$2,100.00$2,100.00$2,100.00$2,435.00$4,052.63
82Signalization, misc.: foundation test hole (632E90400)EACH2$1,300.00$600.00$600.00$600.00$375.00$868.42
83Signalization, misc.: pedestrian hybrid beacon (632E90400)EACH5$1,400.00$1,250.00$1,250.00$1,250.00$1,795.00$4,978.95
84Cabinet foundation, as per plan (633E67101)EACH1$4,000.00$3,400.00$3,400.00$3,400.00$1,424.50$5,326.32
85Controller work pad, as per plan (633E67201)EACH1$1,000.00$900.00$900.00$900.00$515.00$1,968.42
86Uninterruptible power supply (UPS), as per plan (633E74001)EACH1$10,500$10,000$9,700.00$9,700.00$11,925$23,158
87Controller item, misc.: controller, actuated, 8 PH (633E99000)EACH1$30,200$30,000$28,750$28,750$36,900$63,684
88Law enforcement officer with patrol car for assistance (614E11110)HR100$95.00$90.00$125.00$125.00$150.00$115.79
89Portable changeable message sign, as per plan (614E18601)SNMT6$2,800.00$1,000.00$800.00$900.00$850.00$1,389.47
90Water (616E10000)MGAL10$210.00$10.00$5.00$100.00$100.00$70.53
91Calcium chloride (616E20000)TON1$1,100.00$10.00$250.00$260.00$1,350.00$1,157.89
92Premium for contract performance bond and for payment bond (103E05000)LS1$9,500.00$12,000$15,000$12,000$6,232.87$38,280
93Maintaining traffic (614E11000)LS1$24,000$28,750$150,000$57,000$43,500$34,800
94Construction layout stakes and surveying (623E10000)LS1$7,000.00$9,000.00$13,955$10,000$15,250$28,947
95Mobilization (624E10000)LS1$19,000$17,985$48,000$60,000$60,000$68,924
ODOT contract 260235: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy