ODOT contract 260391 bid tabulation
CUY-IR 480-11.64 BH (BRIDGE REPAIR). Let by Ohio DOT on August 27, 2026, CUY. 6 bids received; low bid $435,132 by Ohio Concrete Maintenance LLC, -4.2% against the engineer's estimate of $454,000.
- Owner
- Ohio DOT
- Letting
- 27 AUG 2026
- Pay items
- 36
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ohio Concrete Maintenance LLC | $435,132 | Low | -4.0% |
| 2 | Catts Construction Inc | $562,249 | +29% | +24% |
| 3 | Perk Company Inc | $585,320 | +35% | +29% |
| 4 | Madex Construction Co | $594,945 | +37% | +31% |
| 5 | S E T Inc | $619,502 | +42% | +36% |
| 6 | Jadco Construction Service Inc | $688,217 | +58% | +52% |
Engineer's estimate: $454,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ohio Concrete Maintenance LLC | 2. Catts Construction Inc | 3. Perk Company Inc | 4. Madex Construction Co | 5. S E T Inc | 6. Jadco Construction Service Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Guardrail removed (202E38000) | FT | 358.60 | $3.00 | $3.00 | $11.00 | $11.58 | $2.65 | $5.00 |
| 2 | Anchor assembly removed, type A (202E42000) | EACH | 1 | $400.00 | $390.00 | $990.00 | $2,894.74 | $345.00 | $500.00 |
| 3 | Bridge terminal assembly removed (202E47000) | EACH | 3 | $95.00 | $100.00 | $970.00 | $1,736.84 | $90.00 | $80.00 |
| 4 | Guardrail, type MGS (606E15050) | FT | 250 | $29.00 | $32.00 | $26.40 | $34.74 | $27.75 | $30.00 |
| 5 | Anchor assembly, MGS type E (606E26150) | EACH | 1 | $2,800.00 | $3,050.00 | $2,540.00 | $3,473.68 | $2,670.00 | $3,500.00 |
| 6 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 3 | $2,900.00 | $3,150.00 | $2,620.00 | $3,763.16 | $2,750.00 | $3,500.00 |
| 7 | Soil analysis test (659E00100) | EACH | 2 | $500.00 | $120.00 | $500.00 | $89.47 | $50.00 | $500.00 |
| 8 | Topsoil (659E00300) | CY | 33 | $80.00 | $92.00 | $100.00 | $16.84 | $80.00 | $150.00 |
| 9 | Seeding and mulching (659E10000) | SY | 290 | $7.00 | $3.00 | $5.00 | $0.98 | $5.75 | $10.00 |
| 10 | Commercial fertilizer (659E20000) | TON | 0.05 | $1,000.00 | $750.00 | $1,000.00 | $115.80 | $1,500.00 | $1,500.00 |
| 11 | Lime (659E31000) | ACRE | 0.06 | $1,000.00 | $1,000.00 | $1,000.00 | $57.83 | $750.00 | $1,000.00 |
| 12 | Water (659E35000) | MGAL | 2 | $50.00 | $4.00 | $100.00 | $7.53 | $10.00 | $50.00 |
| 13 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 14 | Connection, fused pull apart (625E00450) | EACH | 2 | $300.00 | $225.00 | $250.00 | $214.21 | $135.00 | $500.00 |
| 15 | Connection, unfused pull apart (625E00460) | EACH | 2 | $300.00 | $225.00 | $250.00 | $214.21 | $75.00 | $500.00 |
| 16 | Light pole, conventional, A6B30 (625E10490) | EACH | 2 | $4,200.00 | $6,335.00 | $3,800.00 | $6,021.05 | $3,350.00 | $6,000.00 |
| 18 | No. 12 AWG pole and bracket cable (625E23410) | FT | 216 | $3.75 | $6.00 | $3.00 | $5.79 | $3.10 | $10.00 |
| 19 | Luminaire, conventional, solid state (LED), type I (625E26252) | EACH | 2 | $1,000.00 | $1,460.00 | $850.00 | $1,389.47 | $800.00 | $1,500.00 |
| 20 | Light pole removed (625E75400) | EACH | 2 | $800.00 | $1,160.00 | $600.00 | $1,100.00 | $300.00 | $1,200.00 |
| 21 | Luminaire removed (625E75506) | EACH | 2 | $250.00 | $300.00 | $200.00 | $289.47 | $125.00 | $500.00 |
| 22 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $120.00 | $120.00 | $125.00 | $115.79 | $105.00 | $95.00 |
| 23 | Replacement sign (614E12500) | EACH | 2 | $365.00 | $335.00 | $250.00 | $277.89 | $250.00 | $250.00 |
| 24 | Replacement drum (614E12600) | EACH | 10 | $65.00 | $85.00 | $55.00 | $63.68 | $58.00 | $100.00 |
| 25 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,200.00 | $1,000.00 | $2,500.00 | $1,020.37 | $1,000.00 | $800.00 |
| 26 | Vandal protection fence removed, as per plan (202E75261) | FT | 630 | $13.00 | $14.00 | $24.00 | $13.89 | $15.25 | $30.00 |
| 27 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 405 | $12.00 | $20.00 | $14.00 | $17.37 | $9.00 | $10.00 |
| 28 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 687 | $45.00 | $58.00 | $42.00 | $52.11 | $24.50 | $35.00 |
| 29 | Concrete repair by epoxy injection (512E10600) | FT | 150 | $75.00 | $108.00 | $150.00 | $160.47 | $77.00 | $50.00 |
| 30 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 1,092 | $33.00 | $70.00 | $34.00 | $35.53 | $34.00 | $45.00 |
| 31 | Patching concrete structure, as per plan (519E11101) | SF | 34 | $200.00 | $200.00 | $175.00 | $247.37 | $190.00 | $250.00 |
| 32 | Vandal protection fence, 6' straight, coated fabric, as per plan (607E39901) | FT | 610 | $330.00 | $355.00 | $295.00 | $347.37 | $319.00 | $320.00 |
| 33 | Signing, misc.: logo sign panel and attachment (630E95000) | LS | 1 | $21,000 | $23,000 | $18,395 | $23,158 | $20,000 | $25,000 |
| 34 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $13,000 | $6,000.00 | $5,750.00 | $19,842 | $14,000 | $11,504 |
| 35 | Maintaining traffic (614E11000) | LS | 1 | $20,000 | $66,000 | $140,000 | $85,263 | $188,000 | $184,000 |
| 36 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,500.00 | $1,000.00 | $7,500.00 | $9,684.21 | $1,000.00 | $25,000 |
| 37 | Mobilization (624E10000) | LS | 1 | $12,000 | $22,150 | $33,000 | $42,080 | $60,000 | $60,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.