ODOT contract 260429 bid tabulation

MED-SR 3-20.63 (INTERSECTION). Let by Ohio DOT on October 1, 2026, MED. 6 bids received; low bid $1,840,224 by Fechko Excavating LLC, -8.2% against the engineer's estimate of $2,004,000.

Owner
Ohio DOT
Letting
01 OCT 2026
Pay items
116
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Fechko Excavating LLC$1,840,224Low-8.0%
2Shelly & Sands Inc$1,875,553+2.0%-6.0%
3Tri-Mor Corp$2,029,451+10%+1.0%
4Karvo Companies Inc$2,076,479+13%+4.0%
5S E T Inc$2,143,016+16%+7.0%
6Anthony Allega Cement Contractor Inc$2,381,803+29%+19%
ODOT contract 260429: bids by rank

Engineer's estimate: $2,004,000.

Bid tabulation

LinePay itemUnitQuantity1. Fechko Excavating LLC2. Shelly & Sands Inc3. Tri-Mor Corp4. Karvo Companies Inc5. S E T Inc6. Anthony Allega Cement Contractor Inc
1Clearing and grubbing (201E11000)LS1$3,000.00$7,500.00$13,000$2,500.00$20,000$11,798
2Headwall removed (202E20010)EACH2$600.00$190.00$500.00$250.00$850.00$1,733.81
3Pavement removed (202E23000)SY5,688$9.00$10.50$18.00$15.00$21.00$12.72
4Pipe removed, 24" and under (202E35100)FT416$44.00$32.00$32.00$20.00$24.00$50.11
5Pipe removed, over 24" diameter (202E35200)FT12$65.00$32.00$50.00$15.00$90.00$261.35
6Mailbox removed (202E53100)EACH10$75.00$120.00$100.00$25.00$225.00$124.41
7Fence removed (202E75000)FT163$11.00$11.50$5.00$5.00$7.00$11.90
8Removal misc.: landscape rock (202E98100)EACH5$85.00$60.00$100.00$100.00$350.00$401.02
9Excavation (203E10000)CY4,721$23.00$24.00$30.00$15.00$28.00$23.80
10Embankment (203E20000)CY2,363$7.00$16.00$15.00$8.00$24.00$13.90
11Proof rolling (204E45000)HR5$245.00$314.00$200.00$500.00$300.00$389.54
12Geotextile fabric (204E50000)SY428$2.50$1.30$2.50$1.00$4.00$7.95
13Cement (206E10500)TON262$195.00$205.00$226.00$205.00$210.00$218.77
14Curing coat (206E11000)SY8,622$1.25$1.25$1.50$1.10$1.50$1.53
15Cement stabilized subgrade, 14 inches deep (206E15020)SY8,622$4.65$4.52$6.00$4.00$4.00$5.29
16Monument assembly, type C (623E38500)EACH5$1,885.00$2,980.00$1,800.00$1,500.00$1,250.00$1,783.30
17Reference monument, type A (623E40500)EACH3$405.00$1,450.00$900.00$1,650.00$1,250.00$164.21
18Right-of-way monument, type B (623E40520)EACH1$350.00$179.00$900.00$1,650.00$425.00$4,433.77
19Preconstruction survey monument verification and report (623E50000)LS1$4,000.00$3,225.00$1,225.00$2,200.00$4,200.00$5,473.79
20Post construction survey monument verification and report (623E51000)LS1$2,750.00$3,225.00$1,225.00$2,200.00$4,200.00$4,789.56
21Special - mailbox support system, single (690E50100)EACH10$345.00$810.00$350.00$235.00$325.00$262.07
22Tied concrete block mat with type 1 underlayment (601E21050)SY144$92.00$71.00$80.00$105.00$150.00$110.97
23Tied concrete block mat with type 2 underlayment (601E21060)SY36$92.00$96.00$80.00$85.00$140.00$180.25
24Rock channel protection, type C with filter (601E32200)CY4$1,600.00$571.00$400.00$600.00$280.00$1,845.22
25Topsoil (659E00300)CY762$15.00$16.00$70.00$32.00$80.00$35.03
26Seeding and mulching, class 2 (659E00510)SY6,858$1.85$1.00$3.25$1.00$1.00$0.92
27Repair seeding and mulching (659E14000)SY343$1.50$0.78$3.25$2.00$1.00$2.19
28Inter-seeding (659E15000)SY343$0.75$0.78$3.25$1.00$1.00$1.09
29Commercial fertilizer (659E20000)TON0.96$975.00$939.00$2,800.00$1,800.00$1,000.00$1,970.56
30Lime (659E31000)ACRE1.42$45.00$161.00$225.00$0.01$200.00$1.09
31Water (659E35000)MGAL20$1.00$1.00$130.00$60.00$1.00$65.69
32Slope erosion protection mat, type B (670E00520)SY1,763$5.00$1.50$2.50$2.50$2.00$2.74
33Ditch erosion protection (670E00700)SY1,447$5.00$1.53$13.00$2.75$2.00$3.01
34Storm water pollution prevention plan (832E15000)LS1$3,780.00$3,500.00$3,800.00$5,000.00$4,200.00$3,831.65
35Storm water pollution prevention inspections (832E15002)LS1$7,000.00$4,280.00$4,800.00$10,000$6,300.00$5,856.95
36Storm water pollution prevention inspection software (832E15010)LS1$5,100.00$6,549.00$7,300.00$10,000$15,000$7,033.82
37Erosion control (832E30000)EACH10,000$1.00$1.00$1.00$1.00$1.00$1.00
38Concrete masonry (602E20000)CY2.30$2,600.00$3,350.00$4,060.00$1,000.00$4,000.00$5,512.05
396" unclassified pipe underdrains (605E13300)FT85$17.00$26.00$15.00$15.00$24.00$83.80
406" base pipe underdrains (605E14000)FT2,308$16.50$17.25$15.00$12.00$24.00$16.44
41Aggregate drains (605E31100)FT118$25.00$21.25$10.00$20.00$22.00$84.18
424" conduit, type E (611E00400)FT140$16.00$26.25$15.00$12.00$23.00$62.32
436" conduit, type F for underdrain outlets (611E00510)FT122$16.50$49.50$18.00$8.00$27.00$58.77
4412" conduit, type B (611E04400)FT112$70.00$117.00$118.00$125.00$120.00$96.16
4512" conduit, type D (611E04900)FT297$64.00$83.00$70.00$85.00$105.00$77.87
4615" conduit, type A (611E05700)FT72$100.00$130.00$125.00$105.00$150.00$138.19
4736" conduit, type A (611E16200)FT30$350.00$337.50$388.00$400.00$400.00$504.70
48Catch basin, no. 3A (611E98180)EACH1$4,250.00$4,600.00$3,525.00$3,250.00$4,000.00$6,162.89
49Catch basin, no. 2-2A (611E98450)EACH1$2,300.00$3,470.00$2,400.00$3,000.00$3,500.00$5,653.05
50Precast reinforced concrete outlet (611E99710)EACH9$650.00$680.00$500.00$150.00$425.00$630.12
51Asphalt concrete base, PG64-22, (449) (301E56000)CY796$206.75$206.75$256.00$295.00$240.00$283.41
52Aggregate base (304E20000)CY1,566$78.00$96.00$98.00$115.00$87.00$77.95
53Non-tracking tack coat (407E20000)GAL691$3.05$3.05$3.50$3.50$4.00$3.80
54Prime coat (408E10000)GAL134$3.50$3.50$10.00$10.00$8.00$9.82
55Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY18$1,123.00$1,123.00$1,050.00$400.00$1,000.00$1,153.27
56Asphalt concrete surface course, 12.5 MM, type A (446), as per plan (442E10001)CY261$315.00$315.00$350.00$350.00$310.00$369.29
57Asphalt concrete intermediate course, 12.5 MM, type A (448), as per plan (442E20171)CY301$219.00$219.00$350.00$300.00$310.00$368.06
586" non-reinforced concrete pavement, class QC 1P (452E10010)SY151$68.00$92.00$90.00$60.00$90.00$76.63
598" non-reinforced concrete pavement, class QC 1P, as per plan (452E12011)SY416$133.00$151.00$110.00$95.00$110.00$104.00
63Curb, type 6 (609E26000)FT1,820$51.00$34.00$20.00$20.00$20.00$20.80
646" concrete traffic island, as per plan (609E54001)SY509$122.00$116.00$88.00$75.00$90.00$94.15
65Connection, fused pull apart (625E00450)EACH22$125.00$125.00$150.00$125.00$150.00$150.69
66Connection, unfused permanent (625E00480)EACH17$110.00$110.00$120.00$110.00$85.00$132.60
67Light pole, conventional, AT12B30 (625E10490)EACH1$3,500.00$3,500.00$4,600.00$3,500.00$3,800.00$4,219.21
68Light pole, conventional, AT12B35 (625E10490)EACH10$3,675.00$3,675.00$4,600.00$3,675.00$4,200.00$4,430.17
69Light pole foundation, 24" X 8' deep (625E14100)EACH11$1,880.00$1,880.00$2,400.00$1,880.00$1,800.00$2,266.32
70No. 4 AWG 2400 volt distribution cable (625E23200)FT4,947$6.00$6.00$4.50$6.00$5.00$7.23
71No. 10 AWG pole and bracket cable (625E23400)FT1,716$2.00$2.00$1.50$2.00$2.00$2.41
72Conduit, 2", 725.04 (625E25400)FT1,100$18.00$18.00$24.00$18.00$23.00$21.70
73Conduit, 3", 725.04 (625E25500)FT173$44.00$44.00$44.00$44.00$45.00$53.04
74Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH10$685.00$685.00$810.00$685.00$900.00$825.76
75Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH1$725.00$725.00$950.00$725.00$950.00$873.98
76Trench, 24" deep (625E29002)FT1,100$8.00$8.00$9.00$8.00$15.00$9.64
77Trench in paved area (625E29400)FT173$12.00$12.00$23.00$12.00$21.00$14.47
78Pull box, 725.08, 24" (625E30706)EACH7$785.00$785.00$1,500.00$785.00$1,200.00$946.31
79Ground rod (625E32000)EACH11$150.00$150.00$235.00$150.00$275.00$180.82
80Power service, as per plan (625E34001)EACH1$7,500.00$7,500.00$11,000$7,500.00$10,000$9,041.15
81Underground warning marking tape (625E36010)FT1,273$2.00$2.00$2.50$2.00$1.00$2.41
82Special - maintain existing lighting (625E40000)LS1$1,500.00$1,500.00$1,700.00$1,500.00$5,000.00$1,808.23
83Arc flash calculations and label, power service (625E76000)EACH1$3,300.00$3,300.00$2,400.00$3,300.00$1,050.00$3,978.11
84Delineator, post ground mounted, as per plan (620E00501)EACH4$80.00$190.00$90.00$225.00$235.00$87.23
85RPM (621E00100)EACH157$55.00$45.00$65.00$45.00$55.00$60.21
86Raised pavement marker removed (621E54000)EACH58$12.00$20.00$52.00$4.83$50.00$35.65
87Ground mounted support, no. 3 post, as per plan (630E03101)FT456$16.00$11.50$20.00$13.50$14.00$19.52
88Sign post reflector (630E08600)EACH4$62.00$24.00$75.00$45.00$50.00$50.18
89Sign, flat sheet (630E80100)SF231$18.00$26.00$20.00$25.00$26.00$22.30
90Removal of ground mounted sign and disposal (630E84900)EACH51$18.00$25.00$20.00$5.00$5.00$11.15
91Removal of ground mounted post support and disposal (630E86002)EACH26$23.00$32.00$25.00$5.00$5.00$16.73
92Edge line, 6" (644E00104)MI0.69$6,000.00$6,000.00$6,650.00$8,500.00$9,000.00$6,568.55
93Center line (644E00300)MI0.35$8,400.00$8,400.00$9,300.00$11,000$11,500$9,195.97
94Transverse/diagonal line (644E00700)FT269$9.00$9.00$10.00$10.00$11.00$9.85
95Dotted line, 6" (644E01510)FT212$4.00$4.00$5.00$5.00$5.00$4.38
96Yield line (644E20800)FT73$15.00$15.00$17.00$17.50$18.00$16.42
97Removal of traffic signal installation (632E90100)EACH1$4,500.00$2,200.00$5,000.00$4,500.00$1,650.00$5,424.70
98Riprap for tree protection, as per plan (657E10001)SY428$90.00$47.00$60.00$52.50$60.00$57.47
99Deciduous shrub, 12" height, rhus aromatica, 3 gal (661E19000)EACH16$350.00$139.00$150.00$81.00$150.00$88.68
100Evergreen tree, 2' height, pinus mugo, 5 gal (661E50040)EACH5$660.00$216.00$240.00$227.00$230.00$248.51
101Traffic compacted surface, type A (410E10000)CY50$62.00$260.00$98.00$60.00$115.00$63.42
102Detour signing (614E12420)LS1$26,000$25,163$36,500$23,500$30,000$27,548
103Work zone lighting system (614E12740)EACH1$2,000.00$2,000.00$2,500.00$2,000.00$2,500.00$2,410.97
104Portable changeable message sign, as per plan (614E18601)SNMT12$1,074.00$700.00$1,200.00$1,000.00$1,050.00$1,174.95
105Water (616E10000)MGAL22$1.00$120.00$215.00$5.00$145.00$74.62
106Special - work involving non-regulated materials (690E65000)TON123$12.00$160.00$50.00$125.00$125.00$220.71
107Special - work involving petroleum contaminated soil (690E65016)TON123$23.00$131.00$50.00$100.00$125.00$193.34
108Premium for contract performance bond and for payment bond (103E05000)LS1$15,700$5,000.00$18,000$15,000$23,000$11,235
109Maintaining traffic (614E11000)LS1$2,500.00$13,933$20,000$75,000$60,000$149,113
110Field office, type B (619E16010)MNTH4$1,000.00$5,890.00$2,850.00$3,000.00$1,800.00$2,600.05
111Construction layout stakes and surveying (623E10000)LS1$30,000$18,890$25,000$100,000$32,000$81,789
112Mobilization (624E10000)LS1$92,000$94,000$39,000$225,000$120,000$247,141
200Special - tree removed, 4"-12" (201E20010)EACH479$230.00$45.00$115.00$30.00$47.00$24.63
201Tree removed, 18" diameter (201E21800)EACH15$475.00$1,740.00$665.00$975.00$1,800.00$1,904.88
202Tree removed, 30" diameter (201E23000)EACH4$750.00$3,120.00$1,600.00$3,800.00$3,200.00$3,415.64
203Tree removed, 48" diameter (201E24800)EACH1$3,975.00$3,600.00$3,000.00$6,000.00$3,800.00$3,941.13
204Combination curb and gutter, type 2 (609E12000)FT1,332$25.00$37.00$30.00$28.00$28.00$29.56
205Combination curb and gutter, type 3 (609E18000)FT297$32.00$79.00$30.00$35.00$28.00$29.56
206Combination curb and gutter, type 9, as per plan (609E31001)FT327$65.00$38.50$30.00$30.00$28.00$29.56
ODOT contract 260429: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy