ODOT contract 260429 bid tabulation
MED-SR 3-20.63 (INTERSECTION). Let by Ohio DOT on October 1, 2026, MED. 6 bids received; low bid $1,840,224 by Fechko Excavating LLC, -8.2% against the engineer's estimate of $2,004,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 116
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fechko Excavating LLC | $1,840,224 | Low | -8.0% |
| 2 | Shelly & Sands Inc | $1,875,553 | +2.0% | -6.0% |
| 3 | Tri-Mor Corp | $2,029,451 | +10% | +1.0% |
| 4 | Karvo Companies Inc | $2,076,479 | +13% | +4.0% |
| 5 | S E T Inc | $2,143,016 | +16% | +7.0% |
| 6 | Anthony Allega Cement Contractor Inc | $2,381,803 | +29% | +19% |
Engineer's estimate: $2,004,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fechko Excavating LLC | 2. Shelly & Sands Inc | 3. Tri-Mor Corp | 4. Karvo Companies Inc | 5. S E T Inc | 6. Anthony Allega Cement Contractor Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,000.00 | $7,500.00 | $13,000 | $2,500.00 | $20,000 | $11,798 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $600.00 | $190.00 | $500.00 | $250.00 | $850.00 | $1,733.81 |
| 3 | Pavement removed (202E23000) | SY | 5,688 | $9.00 | $10.50 | $18.00 | $15.00 | $21.00 | $12.72 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 416 | $44.00 | $32.00 | $32.00 | $20.00 | $24.00 | $50.11 |
| 5 | Pipe removed, over 24" diameter (202E35200) | FT | 12 | $65.00 | $32.00 | $50.00 | $15.00 | $90.00 | $261.35 |
| 6 | Mailbox removed (202E53100) | EACH | 10 | $75.00 | $120.00 | $100.00 | $25.00 | $225.00 | $124.41 |
| 7 | Fence removed (202E75000) | FT | 163 | $11.00 | $11.50 | $5.00 | $5.00 | $7.00 | $11.90 |
| 8 | Removal misc.: landscape rock (202E98100) | EACH | 5 | $85.00 | $60.00 | $100.00 | $100.00 | $350.00 | $401.02 |
| 9 | Excavation (203E10000) | CY | 4,721 | $23.00 | $24.00 | $30.00 | $15.00 | $28.00 | $23.80 |
| 10 | Embankment (203E20000) | CY | 2,363 | $7.00 | $16.00 | $15.00 | $8.00 | $24.00 | $13.90 |
| 11 | Proof rolling (204E45000) | HR | 5 | $245.00 | $314.00 | $200.00 | $500.00 | $300.00 | $389.54 |
| 12 | Geotextile fabric (204E50000) | SY | 428 | $2.50 | $1.30 | $2.50 | $1.00 | $4.00 | $7.95 |
| 13 | Cement (206E10500) | TON | 262 | $195.00 | $205.00 | $226.00 | $205.00 | $210.00 | $218.77 |
| 14 | Curing coat (206E11000) | SY | 8,622 | $1.25 | $1.25 | $1.50 | $1.10 | $1.50 | $1.53 |
| 15 | Cement stabilized subgrade, 14 inches deep (206E15020) | SY | 8,622 | $4.65 | $4.52 | $6.00 | $4.00 | $4.00 | $5.29 |
| 16 | Monument assembly, type C (623E38500) | EACH | 5 | $1,885.00 | $2,980.00 | $1,800.00 | $1,500.00 | $1,250.00 | $1,783.30 |
| 17 | Reference monument, type A (623E40500) | EACH | 3 | $405.00 | $1,450.00 | $900.00 | $1,650.00 | $1,250.00 | $164.21 |
| 18 | Right-of-way monument, type B (623E40520) | EACH | 1 | $350.00 | $179.00 | $900.00 | $1,650.00 | $425.00 | $4,433.77 |
| 19 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $4,000.00 | $3,225.00 | $1,225.00 | $2,200.00 | $4,200.00 | $5,473.79 |
| 20 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,750.00 | $3,225.00 | $1,225.00 | $2,200.00 | $4,200.00 | $4,789.56 |
| 21 | Special - mailbox support system, single (690E50100) | EACH | 10 | $345.00 | $810.00 | $350.00 | $235.00 | $325.00 | $262.07 |
| 22 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 144 | $92.00 | $71.00 | $80.00 | $105.00 | $150.00 | $110.97 |
| 23 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 36 | $92.00 | $96.00 | $80.00 | $85.00 | $140.00 | $180.25 |
| 24 | Rock channel protection, type C with filter (601E32200) | CY | 4 | $1,600.00 | $571.00 | $400.00 | $600.00 | $280.00 | $1,845.22 |
| 25 | Topsoil (659E00300) | CY | 762 | $15.00 | $16.00 | $70.00 | $32.00 | $80.00 | $35.03 |
| 26 | Seeding and mulching, class 2 (659E00510) | SY | 6,858 | $1.85 | $1.00 | $3.25 | $1.00 | $1.00 | $0.92 |
| 27 | Repair seeding and mulching (659E14000) | SY | 343 | $1.50 | $0.78 | $3.25 | $2.00 | $1.00 | $2.19 |
| 28 | Inter-seeding (659E15000) | SY | 343 | $0.75 | $0.78 | $3.25 | $1.00 | $1.00 | $1.09 |
| 29 | Commercial fertilizer (659E20000) | TON | 0.96 | $975.00 | $939.00 | $2,800.00 | $1,800.00 | $1,000.00 | $1,970.56 |
| 30 | Lime (659E31000) | ACRE | 1.42 | $45.00 | $161.00 | $225.00 | $0.01 | $200.00 | $1.09 |
| 31 | Water (659E35000) | MGAL | 20 | $1.00 | $1.00 | $130.00 | $60.00 | $1.00 | $65.69 |
| 32 | Slope erosion protection mat, type B (670E00520) | SY | 1,763 | $5.00 | $1.50 | $2.50 | $2.50 | $2.00 | $2.74 |
| 33 | Ditch erosion protection (670E00700) | SY | 1,447 | $5.00 | $1.53 | $13.00 | $2.75 | $2.00 | $3.01 |
| 34 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,780.00 | $3,500.00 | $3,800.00 | $5,000.00 | $4,200.00 | $3,831.65 |
| 35 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $7,000.00 | $4,280.00 | $4,800.00 | $10,000 | $6,300.00 | $5,856.95 |
| 36 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $5,100.00 | $6,549.00 | $7,300.00 | $10,000 | $15,000 | $7,033.82 |
| 37 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 38 | Concrete masonry (602E20000) | CY | 2.30 | $2,600.00 | $3,350.00 | $4,060.00 | $1,000.00 | $4,000.00 | $5,512.05 |
| 39 | 6" unclassified pipe underdrains (605E13300) | FT | 85 | $17.00 | $26.00 | $15.00 | $15.00 | $24.00 | $83.80 |
| 40 | 6" base pipe underdrains (605E14000) | FT | 2,308 | $16.50 | $17.25 | $15.00 | $12.00 | $24.00 | $16.44 |
| 41 | Aggregate drains (605E31100) | FT | 118 | $25.00 | $21.25 | $10.00 | $20.00 | $22.00 | $84.18 |
| 42 | 4" conduit, type E (611E00400) | FT | 140 | $16.00 | $26.25 | $15.00 | $12.00 | $23.00 | $62.32 |
| 43 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 122 | $16.50 | $49.50 | $18.00 | $8.00 | $27.00 | $58.77 |
| 44 | 12" conduit, type B (611E04400) | FT | 112 | $70.00 | $117.00 | $118.00 | $125.00 | $120.00 | $96.16 |
| 45 | 12" conduit, type D (611E04900) | FT | 297 | $64.00 | $83.00 | $70.00 | $85.00 | $105.00 | $77.87 |
| 46 | 15" conduit, type A (611E05700) | FT | 72 | $100.00 | $130.00 | $125.00 | $105.00 | $150.00 | $138.19 |
| 47 | 36" conduit, type A (611E16200) | FT | 30 | $350.00 | $337.50 | $388.00 | $400.00 | $400.00 | $504.70 |
| 48 | Catch basin, no. 3A (611E98180) | EACH | 1 | $4,250.00 | $4,600.00 | $3,525.00 | $3,250.00 | $4,000.00 | $6,162.89 |
| 49 | Catch basin, no. 2-2A (611E98450) | EACH | 1 | $2,300.00 | $3,470.00 | $2,400.00 | $3,000.00 | $3,500.00 | $5,653.05 |
| 50 | Precast reinforced concrete outlet (611E99710) | EACH | 9 | $650.00 | $680.00 | $500.00 | $150.00 | $425.00 | $630.12 |
| 51 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 796 | $206.75 | $206.75 | $256.00 | $295.00 | $240.00 | $283.41 |
| 52 | Aggregate base (304E20000) | CY | 1,566 | $78.00 | $96.00 | $98.00 | $115.00 | $87.00 | $77.95 |
| 53 | Non-tracking tack coat (407E20000) | GAL | 691 | $3.05 | $3.05 | $3.50 | $3.50 | $4.00 | $3.80 |
| 54 | Prime coat (408E10000) | GAL | 134 | $3.50 | $3.50 | $10.00 | $10.00 | $8.00 | $9.82 |
| 55 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 18 | $1,123.00 | $1,123.00 | $1,050.00 | $400.00 | $1,000.00 | $1,153.27 |
| 56 | Asphalt concrete surface course, 12.5 MM, type A (446), as per plan (442E10001) | CY | 261 | $315.00 | $315.00 | $350.00 | $350.00 | $310.00 | $369.29 |
| 57 | Asphalt concrete intermediate course, 12.5 MM, type A (448), as per plan (442E20171) | CY | 301 | $219.00 | $219.00 | $350.00 | $300.00 | $310.00 | $368.06 |
| 58 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 151 | $68.00 | $92.00 | $90.00 | $60.00 | $90.00 | $76.63 |
| 59 | 8" non-reinforced concrete pavement, class QC 1P, as per plan (452E12011) | SY | 416 | $133.00 | $151.00 | $110.00 | $95.00 | $110.00 | $104.00 |
| 63 | Curb, type 6 (609E26000) | FT | 1,820 | $51.00 | $34.00 | $20.00 | $20.00 | $20.00 | $20.80 |
| 64 | 6" concrete traffic island, as per plan (609E54001) | SY | 509 | $122.00 | $116.00 | $88.00 | $75.00 | $90.00 | $94.15 |
| 65 | Connection, fused pull apart (625E00450) | EACH | 22 | $125.00 | $125.00 | $150.00 | $125.00 | $150.00 | $150.69 |
| 66 | Connection, unfused permanent (625E00480) | EACH | 17 | $110.00 | $110.00 | $120.00 | $110.00 | $85.00 | $132.60 |
| 67 | Light pole, conventional, AT12B30 (625E10490) | EACH | 1 | $3,500.00 | $3,500.00 | $4,600.00 | $3,500.00 | $3,800.00 | $4,219.21 |
| 68 | Light pole, conventional, AT12B35 (625E10490) | EACH | 10 | $3,675.00 | $3,675.00 | $4,600.00 | $3,675.00 | $4,200.00 | $4,430.17 |
| 69 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 11 | $1,880.00 | $1,880.00 | $2,400.00 | $1,880.00 | $1,800.00 | $2,266.32 |
| 70 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 4,947 | $6.00 | $6.00 | $4.50 | $6.00 | $5.00 | $7.23 |
| 71 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,716 | $2.00 | $2.00 | $1.50 | $2.00 | $2.00 | $2.41 |
| 72 | Conduit, 2", 725.04 (625E25400) | FT | 1,100 | $18.00 | $18.00 | $24.00 | $18.00 | $23.00 | $21.70 |
| 73 | Conduit, 3", 725.04 (625E25500) | FT | 173 | $44.00 | $44.00 | $44.00 | $44.00 | $45.00 | $53.04 |
| 74 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 10 | $685.00 | $685.00 | $810.00 | $685.00 | $900.00 | $825.76 |
| 75 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 1 | $725.00 | $725.00 | $950.00 | $725.00 | $950.00 | $873.98 |
| 76 | Trench, 24" deep (625E29002) | FT | 1,100 | $8.00 | $8.00 | $9.00 | $8.00 | $15.00 | $9.64 |
| 77 | Trench in paved area (625E29400) | FT | 173 | $12.00 | $12.00 | $23.00 | $12.00 | $21.00 | $14.47 |
| 78 | Pull box, 725.08, 24" (625E30706) | EACH | 7 | $785.00 | $785.00 | $1,500.00 | $785.00 | $1,200.00 | $946.31 |
| 79 | Ground rod (625E32000) | EACH | 11 | $150.00 | $150.00 | $235.00 | $150.00 | $275.00 | $180.82 |
| 80 | Power service, as per plan (625E34001) | EACH | 1 | $7,500.00 | $7,500.00 | $11,000 | $7,500.00 | $10,000 | $9,041.15 |
| 81 | Underground warning marking tape (625E36010) | FT | 1,273 | $2.00 | $2.00 | $2.50 | $2.00 | $1.00 | $2.41 |
| 82 | Special - maintain existing lighting (625E40000) | LS | 1 | $1,500.00 | $1,500.00 | $1,700.00 | $1,500.00 | $5,000.00 | $1,808.23 |
| 83 | Arc flash calculations and label, power service (625E76000) | EACH | 1 | $3,300.00 | $3,300.00 | $2,400.00 | $3,300.00 | $1,050.00 | $3,978.11 |
| 84 | Delineator, post ground mounted, as per plan (620E00501) | EACH | 4 | $80.00 | $190.00 | $90.00 | $225.00 | $235.00 | $87.23 |
| 85 | RPM (621E00100) | EACH | 157 | $55.00 | $45.00 | $65.00 | $45.00 | $55.00 | $60.21 |
| 86 | Raised pavement marker removed (621E54000) | EACH | 58 | $12.00 | $20.00 | $52.00 | $4.83 | $50.00 | $35.65 |
| 87 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 456 | $16.00 | $11.50 | $20.00 | $13.50 | $14.00 | $19.52 |
| 88 | Sign post reflector (630E08600) | EACH | 4 | $62.00 | $24.00 | $75.00 | $45.00 | $50.00 | $50.18 |
| 89 | Sign, flat sheet (630E80100) | SF | 231 | $18.00 | $26.00 | $20.00 | $25.00 | $26.00 | $22.30 |
| 90 | Removal of ground mounted sign and disposal (630E84900) | EACH | 51 | $18.00 | $25.00 | $20.00 | $5.00 | $5.00 | $11.15 |
| 91 | Removal of ground mounted post support and disposal (630E86002) | EACH | 26 | $23.00 | $32.00 | $25.00 | $5.00 | $5.00 | $16.73 |
| 92 | Edge line, 6" (644E00104) | MI | 0.69 | $6,000.00 | $6,000.00 | $6,650.00 | $8,500.00 | $9,000.00 | $6,568.55 |
| 93 | Center line (644E00300) | MI | 0.35 | $8,400.00 | $8,400.00 | $9,300.00 | $11,000 | $11,500 | $9,195.97 |
| 94 | Transverse/diagonal line (644E00700) | FT | 269 | $9.00 | $9.00 | $10.00 | $10.00 | $11.00 | $9.85 |
| 95 | Dotted line, 6" (644E01510) | FT | 212 | $4.00 | $4.00 | $5.00 | $5.00 | $5.00 | $4.38 |
| 96 | Yield line (644E20800) | FT | 73 | $15.00 | $15.00 | $17.00 | $17.50 | $18.00 | $16.42 |
| 97 | Removal of traffic signal installation (632E90100) | EACH | 1 | $4,500.00 | $2,200.00 | $5,000.00 | $4,500.00 | $1,650.00 | $5,424.70 |
| 98 | Riprap for tree protection, as per plan (657E10001) | SY | 428 | $90.00 | $47.00 | $60.00 | $52.50 | $60.00 | $57.47 |
| 99 | Deciduous shrub, 12" height, rhus aromatica, 3 gal (661E19000) | EACH | 16 | $350.00 | $139.00 | $150.00 | $81.00 | $150.00 | $88.68 |
| 100 | Evergreen tree, 2' height, pinus mugo, 5 gal (661E50040) | EACH | 5 | $660.00 | $216.00 | $240.00 | $227.00 | $230.00 | $248.51 |
| 101 | Traffic compacted surface, type A (410E10000) | CY | 50 | $62.00 | $260.00 | $98.00 | $60.00 | $115.00 | $63.42 |
| 102 | Detour signing (614E12420) | LS | 1 | $26,000 | $25,163 | $36,500 | $23,500 | $30,000 | $27,548 |
| 103 | Work zone lighting system (614E12740) | EACH | 1 | $2,000.00 | $2,000.00 | $2,500.00 | $2,000.00 | $2,500.00 | $2,410.97 |
| 104 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,074.00 | $700.00 | $1,200.00 | $1,000.00 | $1,050.00 | $1,174.95 |
| 105 | Water (616E10000) | MGAL | 22 | $1.00 | $120.00 | $215.00 | $5.00 | $145.00 | $74.62 |
| 106 | Special - work involving non-regulated materials (690E65000) | TON | 123 | $12.00 | $160.00 | $50.00 | $125.00 | $125.00 | $220.71 |
| 107 | Special - work involving petroleum contaminated soil (690E65016) | TON | 123 | $23.00 | $131.00 | $50.00 | $100.00 | $125.00 | $193.34 |
| 108 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,700 | $5,000.00 | $18,000 | $15,000 | $23,000 | $11,235 |
| 109 | Maintaining traffic (614E11000) | LS | 1 | $2,500.00 | $13,933 | $20,000 | $75,000 | $60,000 | $149,113 |
| 110 | Field office, type B (619E16010) | MNTH | 4 | $1,000.00 | $5,890.00 | $2,850.00 | $3,000.00 | $1,800.00 | $2,600.05 |
| 111 | Construction layout stakes and surveying (623E10000) | LS | 1 | $30,000 | $18,890 | $25,000 | $100,000 | $32,000 | $81,789 |
| 112 | Mobilization (624E10000) | LS | 1 | $92,000 | $94,000 | $39,000 | $225,000 | $120,000 | $247,141 |
| 200 | Special - tree removed, 4"-12" (201E20010) | EACH | 479 | $230.00 | $45.00 | $115.00 | $30.00 | $47.00 | $24.63 |
| 201 | Tree removed, 18" diameter (201E21800) | EACH | 15 | $475.00 | $1,740.00 | $665.00 | $975.00 | $1,800.00 | $1,904.88 |
| 202 | Tree removed, 30" diameter (201E23000) | EACH | 4 | $750.00 | $3,120.00 | $1,600.00 | $3,800.00 | $3,200.00 | $3,415.64 |
| 203 | Tree removed, 48" diameter (201E24800) | EACH | 1 | $3,975.00 | $3,600.00 | $3,000.00 | $6,000.00 | $3,800.00 | $3,941.13 |
| 204 | Combination curb and gutter, type 2 (609E12000) | FT | 1,332 | $25.00 | $37.00 | $30.00 | $28.00 | $28.00 | $29.56 |
| 205 | Combination curb and gutter, type 3 (609E18000) | FT | 297 | $32.00 | $79.00 | $30.00 | $35.00 | $28.00 | $29.56 |
| 206 | Combination curb and gutter, type 9, as per plan (609E31001) | FT | 327 | $65.00 | $38.50 | $30.00 | $30.00 | $28.00 | $29.56 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.