ODOT letting results, June 8, 2023
19 contracts let by Ohio DOT on June 8, 2023, $80,289,882 in low bids, a median of 2 bidders per contract. On the 19 with an engineer's estimate, the low bid came in under it 8 times; median low bid +4.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 19
- Low bids, total
- $80,289,882
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 233005 | WAY-SR 21-00.00 (MAJOR RECONSTRUCTION) | WAY | 3 | Kenmore Construction Co Inc | $30,843,350 | $38,108,050 | +24% | -14% | ODOT |
| 230351 | HAM-SR 562-00.54 (BRIDGE REPAIR) | HAM | 2 | Great Lakes Construction Co | $21,404,364 | $27,392,782 | +28% | +61% | ODOT |
| 230350 | GAL-SR 141-07.70 and SR 775-00.00 (TWO LANE RESURFACING) | GAL | 1 | Shelly Company | $5,755,276 | +2.0% | ODOT | ||
| 230347 | BRO-/ADA-SR 32-(00.00)(04.54)/23.67 (FOUR LANE RESURFACING) | BRO | 2 | Shelly Company | $5,631,434 | $6,038,346 | +7.0% | +26% | ODOT |
| 230346 | ATB-SR 307-03.21 (INTERSECTION) | ATB | 5 | Eclipse Co LLC | $2,739,970 | $2,779,518 | +1.0% | +16% | ODOT |
| 230363 | WYA-SR 294-00.00 (TWO LANE RESURFACING) | WYA | 3 | Shelly & Sands Inc | $1,853,861 | $1,895,149 | +2.0% | -3.0% | ODOT |
| 230359 | FRA-GR FY24 (GUARDRAIL REBUILDING) | FRA | 2 | M P Dory Co | $1,825,254 | $2,161,825 | +18% | -4.0% | ODOT |
| 230353 | JAC-US 35-00.00 (FOUR LANE RESURFACING) | JAC | 1 | Shelly & Sands Inc | $1,588,986 | +11% | ODOT | ||
| 230360 | HAM-Embshoff Woods Resurfacing (PARKING AREAS) | HAM | 2 | Barrett Paving Materials Inc | $1,465,956 | $1,758,389 | +20% | +70% | ODOT |
| 230348 | BUT-SR 4-24.00 (TWO LANE RESURFACING) | BUT | 2 | John R Jurgensen Company | $1,386,962 | $1,493,122 | +8.0% | +4.0% | ODOT |
| 230356 | MOT-SR 201-04.48 (FOUR LANE RESURFACING) | MOT | 2 | John R Jurgensen Company | $1,298,099 | $1,534,344 | +18% | -5.0% | ODOT |
| 230349 | D05-Spot Paving FY2024 (SPOT PATCHING / PAVEMENT REPAIR) | District 5 | 1 | Shelly Company | $956,551 | +7.0% | ODOT | ||
| 230352 | HAM-SR 747-00.86 (FOUR LANE RESURFACING) | HAM | 2 | John R Jurgensen Company | $917,592 | $924,513 | +1.0% | +31% | ODOT |
| 230358 | D06-GR FY24 (GUARDRAIL REBUILDING) | District 6 | 2 | Lake Erie Construction Company | $643,645 | $733,612 | +14% | -3.0% | ODOT |
| 230354 | JEF-SR 213-04.21 (SLIDE REPAIR) | JEF | 3 | Shelly & Sands Inc | $500,016 | $523,146 | +5.0% | -1.0% | ODOT |
| 230355 | MER-SR 118-21.81 (INTERSECTION) | MER | 1 | Shelly Company | $463,871 | +24% | ODOT | ||
| 230357 | D01-RPM FY24 (RAISED PAVEMENT MARKERS) | District 1 | 2 | W L Markers Inc | $407,904 | $472,085 | +16% | -17% | ODOT |
| 230361 | MOE-SR 78-06.78 (CULVERT REPLACEMENT) | MOE | 4 | Ohio-West Virginia Excavating Co | $318,403 | $369,692 | +16% | -6.0% | ODOT |
| 230362 | MOT-IR 75-22.92 (SIGNALIZATION) | MOT | 6 | Bansal Construction Inc | $288,388 | $290,290 | +1.0% | +6.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.