ODOT letting results, August 24, 2023
15 contracts let by Ohio DOT on August 24, 2023, $23,930,261 in low bids, a median of 4 bidders per contract. On the 15 with an engineer's estimate, the low bid came in under it 5 times; median low bid +2.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 15
- Low bids, total
- $23,930,261
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 230428 | HAM-IR 71-08.65 (INTERCHANGE) | HAM | 6 | KT Holden Construction LLC | $4,771,595 | $5,002,124 | +5.0% | +17% | ODOT |
| 230439 | SUM-SR 59-07.95 (FOUR LANE RESURFACING) | SUM | 5 | Ronyak Paving Inc | $3,546,322 | $3,636,130 | +3.0% | +2.0% | ODOT |
| 230435 | POR-SR 59-(06.05)(06.80) (FOUR LANE RESURFACING) | POR | 4 | Shelly Company | $2,773,695 | $2,788,000 | +1.0% | +5.0% | ODOT |
| 230429 | HAM-SIGNS-FY2023 (SIGNING) | HAM | 2 | Lake Erie Construction Company | $2,311,275 | $2,355,480 | +2.0% | +9.0% | ODOT |
| 230434 | MUS-SR 16-06.70 (SLIDE REPAIR) | MUS | 6 of 7 | Ohio-West Virginia Excavating Co | $1,814,264 | $1,960,973 | +8.0% | -18% | ODOT |
| 230430 | HOC-US 33-13.13/14.01 (BRIDGE REPAIR) | HOC | 4 | Complete General Construction Company | $1,808,368 | $1,904,852 | +5.0% | -13% | ODOT |
| 230436 | ROS-US 35-00.00 (MICROSURFACING) | ROS | 1 | Strawser Construction Inc | $1,799,979 | +28% | ODOT | ||
| 230441 | D05-GR FY2024 (Ding N Dent) (GUARDRAIL REBUILDING) | District 5 | 2 | Lake Erie Construction Company | $1,043,180 | $1,243,165 | +19% | -6.0% | ODOT |
| 230432 | MOT-Spinning Rd Ph 1-00.00-00.61 (MISCELLANEOUS) | MOT | 2 | Barrett Paving Materials Inc | $924,403 | $1,136,576 | +23% | +8.0% | ODOT |
| 230433 | MRG-CR 52-03.82 (BRIDGE REPLACEMENT (1 BRIDGE)) | MRG | 5 | Shelly & Sands Inc | $869,081 | $875,463 | +1.0% | 0.0% | ODOT |
| 234020 | HOL-SR 83-11.91 (BRIDGE REPAIR) | HOL | 3 | Bog Construction Inc | $849,150 | $997,489 | +17% | +9.0% | ODOT |
| 230413 | COS-VAR Signal Upgrades (SIGNALIZATION) | COS | 6 | Greenwich Electric Inc | $591,511 | $622,290 | +5.0% | -7.0% | ODOT |
| 230422 | BRO-SR 131/SR 251-03.89/00.00 (CHIP SEAL) | BRO | 3 | Allied Construction, LLC | $500,648 | $526,534 | +5.0% | -1.0% | ODOT |
| 230431 | JAC-US 35-0.00 (Safety) (SIGNING) | JAC | 2 | Lake Erie Construction Company | $212,275 | $248,162 | +17% | +2.0% | ODOT |
| 230440 | D03-PR FY2024 (PRUNING/OR TREE/BRUSH REMOVAL) | District 3 | 4 | Russell Tree Experts | $114,516 | $124,750 | +9.0% | 0.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.