TDOT contract CNZ003 bid tabulation

The resurfacing on u.s. 64 (s.r. 15) from the bridge over green river (l.m. 14.70) to the bridge over fortyeight creek (l.m. 20.95), including thin epoxy overlay on bridges. Let by Tennessee DOT on February 7, 2025, Wayne County. 2 bids received; low bid $4,398,382 by Rogers Group, Inc..

Owner
Tennessee DOT
Letting
07 FEB 2025
Pay items
34
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Rogers Group, Inc.$4,398,382Low
2Volunteer Paving, LLC$5,223,807+19%
TDOT contract CNZ003: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Rogers Group, Inc.2. Volunteer Paving, LLC
1Brooming & degrassing shoulders (208-01.05)LM23$1,650.00$1,277.81
2Mineral aggregate, type A base, grading D (303-01)TON2,889$30.00$41.13
3Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08)TON500$98.00$124.42
4Bituminous material for tack coat (TC) (403-01)TON131$800.00$1,018.10
5Bituminous material (BSC) (405-01.01)TON449$935.00$1,115.73
6Mineral aggregate (BSC) (405-01.02)TON3,927$54.00$96.45
7Longitudinal joint sealant (411-01.21)LM29$1,600.00$2,992.50
8Acs mix(PG70-22) grading D (411-02.10)TON20,010$122.00$141.79
9Scoring shoulders (continuous) (16IN width) (411-12.01)LM9.90$920.00$703.98
10Scoring shoulders (non-continuous) (16IN width) (411-12.02)LM12.10$920.00$551.25
11Cold planing bituminous pavement (415-01.01)TON3,100$27.00$38.42
12Traffic control (712-01)LS1$91,500$167,701
13Flexible drums (channelizing) (712-04.01)EACH90$32.00$32.55
14Signs (construction) (712-06)SF1,822$8.00$7.88
15Arrow board (type C) (712-08.03)EACH1$1,210.00$1,260.00
16Flexible delineator (white) (713-02.14)EACH54$66.00$68.25
17Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH310$41.00$45.00
18Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH660$41.00$45.00
19Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23)EACH290$41.00$45.00
20Removal of snowplowable reflective marker (716-01.30)EACH1,260$16.00$10.00
21Plastic pavement marking(channelization striping) (716-02.04)SY817$11.00$35.00
22Plastic pavement marking (stop line) (716-02.05)LF450$21.00$20.00
23Plastic pavement marking (turn lane arrow) (716-02.06)EACH37$200.00$225.00
24Plastic pavement marking (8" dotted line) (716-02.08)LF111$3.00$5.00
25Plastic pavement marking (8IN line) (716-02.12)LM0.30$10,100$12,000
26Painted pavement markings(8" line) (716-05.49)LM30.30$2,050.00$1,750.00
27Removal of pavement marking (line) (716-08.01)LF159,984$0.75$0.89
28Contrast pavement marking 6" (716-09.86)LM0.30$25,200$40,000
29Contrast pavement shadow marking 6" (716-09.94)LM0.30$40,200$40,000
30Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM30.30$8,100.00$7,000.00
31Mobilization (717-01)LS1$86,464$32,186
32Saw slot (730-14.02)LF896$5.50$6.30
33Loop wire (730-14.03)LF1,792$1.25$1.05
34Type 1 thin epoxy overlay (epoxy-urethane) (617-04.01)SY3,357$42.00$48.56
TDOT contract CNZ003: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of February 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy