TDOT contract CNZ184 bid tabulation
The resurfacing on u.s. 27 (s.r. 27) from south of the i-24 overpass (l.m. 5.51) to the georgia state line (l.m. 7.93). Let by Tennessee DOT on August 15, 2025, Hamilton County. 2 bids received; low bid $4,050,263 by APAC-Atlantic, Inc..
- Owner
- Tennessee DOT
- Letting
- 15 AUG 2025
- Pay items
- 38
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | APAC-Atlantic, Inc. | $4,050,263 | Low |
| 2 | Wright Brothers Construction Company, Inc. | $4,068,688 | 0.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. APAC-Atlantic, Inc. | 2. Wright Brothers Construction Company, Inc. |
|---|---|---|---|---|---|
| 1 | Vacuum truck/sweeper for roadway debris (209-70.01) | HR | 80 | $207.32 | $260.00 |
| 2 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading cam (307-02.09) | TON | 6,889 | $176.60 | $145.00 |
| 3 | Trackless tack coat (403-02.01) | TON | 53 | $942.28 | $875.00 |
| 4 | Longitudinal joint sealant (411-01.21) | LM | 9.40 | $3,186.00 | $3,300.00 |
| 5 | Acs mix(PG76-22) grading D (411-03.10) | TON | 6,639 | $161.66 | $160.00 |
| 6 | Cold planing bituminous pavement (415-01.01) | TON | 13,152 | $30.50 | $46.00 |
| 7 | Portland cement concrete pavement (plain) 12" fast track (501-01.15) | SY | 110 | $1,395.00 | $1,275.00 |
| 8 | Adjustment of existing manhole (611-01.20) | EACH | 29 | $5,145.00 | $4,900.00 |
| 9 | Adjustment of existing catchbasin (611-09.01) | EACH | 99 | $3,518.00 | $3,350.00 |
| 10 | Traffic control (712-01) | LS | 1 | $132,307 | $150,000 |
| 11 | Flexible drums (channelizing) (712-04.01) | EACH | 91 | $34.56 | $36.20 |
| 12 | Signs (construction) (712-06) | SF | 1,770 | $7.83 | $8.20 |
| 13 | Arrow board (type C) (712-08.03) | EACH | 2 | $837.00 | $880.00 |
| 14 | Removal of signs, posts and footings (713-15) | LS | 1 | $216.00 | $226.00 |
| 15 | Changeable message sign unit (713-16.01) | EACH | 4 | $4,860.00 | $5,100.00 |
| 16 | Railroad advance warning sign and support (713-16.09) | EACH | 4 | $405.00 | $424.00 |
| 17 | Signs (R3-17 with R3-17BP) (713-16.20) | EACH | 1 | $372.60 | $390.00 |
| 18 | Signs (W10-2) (713-16.21) | EACH | 5 | $345.60 | $362.00 |
| 19 | Signs (W10-3) (713-16.22) | EACH | 2 | $345.60 | $362.00 |
| 20 | Signs (W10-4) (713-16.23) | EACH | 2 | $345.60 | $362.00 |
| 21 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 382 | $37.80 | $39.00 |
| 22 | Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23) | EACH | 280 | $37.80 | $39.00 |
| 23 | Removal of snowplowable reflective marker (716-01.30) | EACH | 506 | $10.80 | $11.15 |
| 24 | Plastic pavement marking (cross-walk) (716-02.03) | LF | 723 | $10.80 | $11.15 |
| 25 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 667 | $23.76 | $24.50 |
| 26 | Plastic pavement marking (stop line) (716-02.05) | LF | 2,072 | $10.80 | $11.15 |
| 27 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 31 | $162.00 | $167.00 |
| 28 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 1,242 | $1.89 | $1.95 |
| 29 | Plastic pavement marking (longitudinal cross-walk) (716-02.09) | LF | 2,471 | $23.22 | $24.00 |
| 30 | Plastic pavement marking (8IN line) (716-02.12) | LM | 0.25 | $13,500 | $13,900 |
| 31 | Plastic word pavement marking (RXR) (716-03.02) | EACH | 12 | $486.00 | $500.00 |
| 32 | Plastic pavement marking (straight-turn arrow) (716-04.01) | EACH | 7 | $189.00 | $195.00 |
| 33 | Plastic pavement marking (straight arrow) (716-04.05) | EACH | 10 | $162.00 | $165.00 |
| 34 | Plastic pavement marking (bikelane symbol & arrow) (716-04.13) | EACH | 48 | $378.00 | $390.00 |
| 35 | Painted pavement marking (4" line) (716-05.01) | LM | 15 | $1,296.00 | $1,300.00 |
| 36 | Painted pavement marking (stop line) (716-05.05) | LF | 2,072 | $5.40 | $5.55 |
| 37 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 13.70 | $6,750.00 | $7,200.00 |
| 38 | Mobilization (717-01) | LS | 1 | $141,446 | $188,100 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.