TDOT contract CNZ233 bid tabulation
The emergency slope stabilization on s.r. 141 from near l.m. 14.68 to l.m. 14.77. Let by Tennessee DOT on July 25, 2025, Smith County. 3 bids received; low bid $2,926,195 by Dement Construction Group, LLC.
- Owner
- Tennessee DOT
- Letting
- 25 JUL 2025
- Pay items
- 39
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dement Construction Group, LLC | $2,926,195 | Low |
| 2 | Cleary Construction, Inc. | $3,326,633 | +14% |
| 3 | Rogers Group, Inc. | $3,530,506 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dement Construction Group, LLC | 2. Cleary Construction, Inc. | 3. Rogers Group, Inc. |
|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $50,000 | $95,500 | $14,245 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $300,000 | $100,000 | $80,000 |
| 3 | Removal of structures and obstructions (202-01) | LS | 1 | $50,000 | $120,000 | $37,000 |
| 4 | Road & drainage excavation (unclassified) (203-01) | CY | 3,500 | $50.00 | $28.50 | $46.00 |
| 5 | Sediment removal (209-05) | CY | 5 | $150.00 | $330.00 | $97.00 |
| 6 | Catch basin protection (type E) (209-40.34) | EACH | 2 | $750.00 | $1,200.00 | $1,260.00 |
| 7 | Mineral aggregate, type A base, grading D (303-01) | TON | 250 | $70.00 | $64.00 | $74.00 |
| 8 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01) | TON | 95 | $193.00 | $265.00 | $230.00 |
| 9 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 63 | $228.00 | $315.00 | $315.00 |
| 10 | Bituminous material for prime coat (PC) (402-01) | TON | 1 | $1,750.00 | $2,500.00 | $1,960.00 |
| 11 | Aggregate for cover material (PC) (402-02) | TON | 3 | $335.00 | $500.00 | $245.00 |
| 12 | Bituminous material for tack coat (TC) (403-01) | TON | 0.60 | $945.00 | $1,300.00 | $1,160.00 |
| 13 | Acs mix(PG64-22) grading D (411-01.10) | TON | 75 | $331.00 | $450.00 | $315.00 |
| 14 | Scoring for rumble stripe (non-continuous) (4IN width) (411-12.04) | LM | 0.20 | $52,500 | $69,000 | $44,720 |
| 15 | Cold planing bituminous pavement (415-01.01) | TON | 37 | $385.00 | $532.00 | $435.00 |
| 16 | 18" pipe culvert (607-03.30) | LF | 34 | $150.00 | $300.00 | $230.00 |
| 17 | Catch basins, type 42, 0' - 4' depth (611-42.01) | EACH | 1 | $6,500.00 | $9,000.00 | $9,230.00 |
| 18 | Catch basins, type 42, > 4' - 8' depth (611-42.02) | EACH | 1 | $8,500.00 | $10,000 | $11,665 |
| 19 | Earth pad for guard rail end treatment (705-04.10) | EACH | 2 | $800.00 | $2,500.00 | $1,780.00 |
| 20 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 300 | $33.25 | $48.00 | $32.00 |
| 21 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 2 | $3,175.00 | $4,400.00 | $3,560.00 |
| 22 | Machined rip-rap (class C) (709-05.09) | TON | 438 | $60.00 | $90.00 | $68.00 |
| 23 | Traffic control (712-01) | LS | 1 | $50,850 | $90,000 | $5,000.00 |
| 24 | Warning lights (type A) (712-05.01) | EACH | 4 | $42.50 | $60.00 | $48.00 |
| 25 | Signs (construction) (712-06) | SF | 283 | $8.20 | $25.00 | $9.15 |
| 26 | Temporary barricades (type III) (712-07.03) | LF | 35 | $18.00 | $65.00 | $20.00 |
| 27 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 6 | $100.00 | $140.00 | $280.00 |
| 28 | Removal of snowplowable reflective marker (716-01.30) | EACH | 6 | $100.00 | $140.00 | $112.00 |
| 29 | Painted pavement marking (6" line) (716-05.20) | LM | 0.40 | $15,000 | $2,765.00 | $8,335.00 |
| 30 | Mobilization (717-01) | LS | 1 | $225,000 | $166,000 | $280,505 |
| 31 | Temporary sediment tube 18IN (740-11.03) | LF | 450 | $15.00 | $10.00 | $62.00 |
| 32 | Drilled caisson - earth (2'-6" dia.) (204-02.10) | LF | 469 | $190.00 | $260.00 | $215.00 |
| 33 | Drilled caisson - rock (2'-6" dia.) (204-02.20) | LF | 280 | $190.00 | $260.00 | $2,905.00 |
| 34 | Mineral aggregate (size 57) (303-10.01) | TON | 2,500 | $65.00 | $95.00 | $46.00 |
| 35 | Structural steel (602-01) | LB | 182,028 | $3.50 | $2.25 | $1.65 |
| 36 | Class A concrete (roadway) (604-01.01) | CY | 136 | $1,000.00 | $2,900.00 | $430.00 |
| 37 | Applied texture finish (new structures) (604-04.01) | SY | 544 | $15.00 | $25.00 | $17.00 |
| 38 | Retaining wall (precast concrete panels) (604-07.01) | SF | 5,032 | $80.00 | $150.00 | $60.00 |
| 39 | Temporary shoring (621-05.02) | LS | 1 | $400,000 | $400,000 | $1,022,425 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of July 25, 2025. Compiled by Mirage Metrics.