TDOT letting results, December 6, 2024
56 contracts let by Tennessee DOT on December 6, 2024, $164,915,955 in low bids, a median of 2 bidders per contract.
- Owner
- Tennessee DOT
- Contracts
- 56
- Low bids, total
- $164,915,955
- Data through
- 02 OCT 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| CNY315 | The installation of soil nail reinforcement and rock anchors on i-40 near mile markers 450.7, 451.0, and 451.6 (hurricane helene) | Cocke County | 3 | Charles Blalock & Sons, Inc. | $26,534,619 | $32,454,890 | +22% | TDOT |
| CNY906 | The construction of a welded steel plate girder bridge on bakerville road over the duck river (l.m. 15.71), including grading, drainage, and paving | Humphreys County | 3 | Jones Bros. Contractors, LLC | $17,905,049 | $18,526,744 | +3.0% | TDOT |
| CNY270 | The grading, drainage, and paving on i-40 at the u.s. 641 (s.r. 69) interchange (l.m. 5.62) (exit 126), including lighting and signals | Benton And Decatur Counties | 3 | Delta Contracting Company, LLC | $11,064,831 | $13,984,926 | +26% | TDOT |
| CNY279 | The construction of a concrete i-beam bridge on s.r. 61 over brushy creek (l.m. 3.98), including grading, drainage, and paving | Anderson County | 3 | Whaley Construction, LLC | $8,219,307 | $9,375,028 | +14% | TDOT |
| CNY293 | The resurfacing on i-75 from near rarity mountain road (l.m. 24.52) to the kentucky state line (l.m. 31.64) | Campbell County | 2 | Rogers Group, Inc. | $8,052,744 | $9,524,977 | +18% | TDOT |
| CNY302 | The resurfacing on i-40 from near s.r. 58 and s.r. 326 (l.m. 16.24) to the loudon county line (l.m. 22.98) | Roane County | 2 | Rogers Group, Inc. | $7,164,670 | $9,245,570 | +29% | TDOT |
| CNY294 | The grading, drainage, signals, and paving on u.s. 11e (s.r. 34, east broadway boulevard) at the intersection of north chucky pike (l.m. 13.55) | Jefferson County | 1 | Southern Constructors, Inc. | $5,025,174 | TDOT | ||
| CNY306 | The resurfacing on u.s. 51 (s.r. 3) from east woodlawn avenue (l.m. 9.60) to winn street (l.m. 15.40), including bridge expansion joint repairs and thin epoxy o | Tipton County | 1 | Lehman-Roberts Company | $4,998,918 | TDOT | ||
| CNY281 | The resurfacing on s.r. 78 from near u.s. 51 (s.r. 3) (l.m. 1.51) to s.r. 103 (l.m. 9.52) | Dyer County | 1 | Ford Construction Company | $4,471,413 | TDOT | ||
| CNY273 | The resurfacing on i-24 from the robertson county line (l.m. 0.00, cheatham county seq. 1), crossing through robertson county to the davidson county line (l.m. | Cheatham And Robertson Counties | 3 | Jones Bros. Contractors, LLC | $4,242,698 | $4,250,444 | 0.0% | TDOT |
| CNY905 | The construction of a concrete box bridge on s.r. 131 over williams creek (l.m. 7.73), including grading, drainage, and paving | Grainger County | 1 | Southern Constructors, Inc. | $3,999,966 | TDOT | ||
| CNY287 | The resurfacing on i-40 from 46th avenue (l.m. 13.33) to near jefferson street (l.m. 16.44), including bridge expansion joint repair and thin epoxy overlay | Davidson County | 3 | Rogers Group, Inc. | $3,971,294 | $4,100,732 | +3.0% | TDOT |
| CNY291 | The interchange improvements on i-40 at s.r. 138 (exit 68) (l.m. 0.78 - l.m. 1.34), including grading, drainage, and paving | Madison County | 2 | Ford Construction Company | $3,640,994 | $3,875,677 | +6.0% | TDOT |
| CNY284 | The resurfacing on i-65 from i-40 (l.m. 8.44) to near the cumberland river bridge (l.m. 11.91), including thin epoxy overlay at l.m. 8.55 | Davidson County | 3 | Vulcan Construction Materials, LLC | $3,549,449 | $3,595,251 | +1.0% | TDOT |
| CNY118 | The resurfacing on u.s. 27 (s.r. 29) from south of boofer lane (l.m. 14.56) to south of metzger lane (l.m. 19.80), including bridge expansion joint repairs | Rhea County | 1 | Rogers Group, Inc. | $3,324,204 | TDOT | ||
| CNY215 | The intersection improvements including signals on u.s. 31a (s.r. 11, nolensville road) from south of sanford road (l.m. 13.25) to south of summerlyn drive (l.m | Williamson County | 5 | Rogers Group, Inc. | $3,289,730 | $3,542,183 | +8.0% | TDOT |
| CNY300 | The resurfacing with hot in-place recycling on u.s. 70 (s.r. 1) from near the rutherford fork obion river (l.m. 11.00) to s.r. 22 (l.m. 19.68), including bridge | Carroll County | 2 | Delta Contracting Company, LLC | $3,149,825 | $3,684,357 | +17% | TDOT |
| CNY292 | The grading, drainage, signals, and paving on a s.i.a. route serving project woolhawk (facebook data center), including u.s. 31e (s.r. 6) and s.r. 25 | Sumner County | 6 | Rogers Group, Inc. | $2,773,978 | $2,854,876 | +3.0% | TDOT |
| CNY266 | The random on-call concrete pavement repair on various interstate and state routes | Counties Benton, Carroll, Chester, Crockett, Decatur, Dyer, Fayette, Gibson, Hardeman, Hardin, Haywood, Henderson, Henry, Lake, Lauderdale, Madison, Mcnairy, Obion, Shelby, Tipton, And Weakley | 2 | Harper Construction, LLC | $2,365,675 | $2,488,666 | +5.0% | TDOT |
| CNY280 | The resurfacing (either microsurface or thin mix overlay) on u.s. 641 (s.r. 69) from the decatur county line (l.m. 0.00) to james walker road (l.m. 10.92) | Benton County | 5 | Delta Contracting Company, LLC | $2,194,468 | $2,380,566 | +8.0% | TDOT |
| CNY282 | The random on-call concrete pavement repair on various interstate and state routes | Counties Bedford, Cheatham, Davidson, Dickson, Giles, Hickman, Houston, Humphreys, Lawrence, Lewis, Lincoln, Macon, Marshall, Maury, Montgomery, Moore, Perry, Robertson, Rutherford, Smith, Stewart, Sumner, Trousdale, Wayne, Williamson, And Wilson | 2 | Capital City Construction Services, LLC | $2,098,694 | $2,160,798 | +3.0% | TDOT |
| CNY295 | N/a,r2bvar-m3-039 the random on-call concrete pavement repair on various interstate and state routes | Counties Bledsoe, Bradley, Cannon, Clay, Coffee, Cumberland, Dekalb, Fentress, Franklin, Grundy, Hamilton, Jackson, Marion, Mcminn, Meigs, Overton, Pickett, Polk, Putnam, Rhea, Sequatchie, Van Buren, Warren, And White | 2 | Bluegrass Contracting Corporation | $1,993,385 | $2,067,459 | +4.0% | TDOT |
| CNY151 | The resurfacing on u.s. 412 (s.r. 20) from s.r. 69 (l.m. 3.59) to the perry county line (l.m. 9.14) | Decatur County | 3 | Delta Contracting Company, LLC | $1,989,198 | $2,279,998 | +15% | TDOT |
| CNY265 | R1bvar-m3-052 the random on-call concrete pavement repair on various interstate and state routes | Counties Anderson, Blount, Campbell, Carter, Claiborne, Cocke, Grainger, Hamblen, Hancock, Hawkins, Jefferson, Johnson, Knox, Loudon, Monroe, Morgan, Roane, Scott, Sevier, Sullivan, Unicoi, Union, And Washington | 3 | Bluegrass Contracting Corporation | $1,987,850 | $2,043,300 | +3.0% | TDOT |
| CNY228 | The miscellaneous safety improvements including signals on u.s. 11w (s.r. 1) at the intersection of phyllis drive and main street in bean station (l.m. 30.30 - | Grainger County | 1 | Southern Constructors, Inc. | $1,742,727 | TDOT | ||
| CNY310 | The resurfacing on s.r. 81 from near ridgecrest drive (l.m. 10.97) to s.r. 75 (l.m. 17.99) | Washington County | 1 | Summers-Taylor, Inc. | $1,619,717 | TDOT | ||
| CNY276 | The resurfacing on s.r. 230 from s.r. 50 (l.m. 0.00) to s.r. 100 (l.m. 9.31) | Hickman County | 3 | Eubank Asphalt Paving & Sealing, LLC | $1,548,912 | $1,999,999 | +29% | TDOT |
| CNY274 | The resurfacing on s.r. 49 from s.r. 25 (l.m. 16.81) to north of s.r. 52 (l.m. 23.51) | Robertson County | 3 | Eubank Asphalt Paving & Sealing, LLC | $1,545,569 | $1,565,292 | +1.0% | TDOT |
| CNY277 | The resurfacing on s.r. 13 from south of chalk creek road (l.m. 21.50) to hill street west (l.m. 26.80) | Wayne County | 2 | Rogers Group, Inc. | $1,469,882 | $1,656,080 | +13% | TDOT |
| CNY301 | The resurfacing on s.r. 50 from collins lane (l.m. 25.25) to the maury county line (l.m. 31.66), and miscellaneous safety improvements from the highway 50 west | Hickman County | 5 | Eubank Asphalt Paving & Sealing, LLC | $1,464,858 | $1,962,181 | +34% | TDOT |
| CNY283 | The resurfacing on s.r. 420 from u.s. 45w (s.r. 5) (l.m. 0.00) to s.r. 186 (l.m. 4.57) | Gibson County | 1 | Delta Contracting Company, LLC | $1,448,906 | TDOT | ||
| CNY305 | The microsurfacing on s.r. 194 from north railroad street (l.m. 0.53) to s.r. 193 (l.m. 9.02), including bridge expansion joint repairs | Fayette County | 1 | Asphalt Paving Systems, Inc. | $1,377,155 | TDOT | ||
| CNY314 | The installation of soil nail reinforcement on u.s. 19e (s.r. 37) between l.m. 1.48 and l.m. 1.52 (hurricane helene) | Carter County | 2 | Summers-Taylor, Inc. | $1,198,964 | $1,707,041 | +42% | TDOT |
| CNY286 | The resurfacing on s.r. 48 from u.s. 79 (s.r. 13) (l.m. 6.86) to the kentucky state line (l.m. 12.44) | Montgomery County | 3 | Eubank Asphalt Paving & Sealing, LLC | $1,189,978 | $1,381,812 | +16% | TDOT |
| CNY308 | The resurfacing on u.s. 11e (s.r. 34) from near depot street (l.m. 15.24) to the hawkins county line (l.m. 21.00) | Hamblen County | 4 | APAC-Atlantic, Inc. | $1,105,703 | $1,138,202 | +3.0% | TDOT |
| CNY267 | The resurfacing on s.r. 55 from u.s. 41 (s.r. 2) (l.m. 13.79) to north of interstate drive (l.m. 15.32) | Coffee County | 2 | Volunteer Paving, LLC | $1,030,378 | $1,194,531 | +16% | TDOT |
| CNY298 | The resurfacing (either microsurface or thin mix overlay) on u.s. 412 (s.r. 20) from the decatur county line (l.m. 0.00) to west of deer valley road (l.m. 6.10) | Perry County | 6 | Eubank Asphalt Paving & Sealing, LLC | $989,541 | $1,083,637 | +10% | TDOT |
| CNY214 | The improvement of the intersection on u.s. 412 (s.r. 20) at old bells road (l.m. 5.62) in jackson, including grading, drainage, and paving | Madison County | 3 | Ford Construction Company | $959,576 | $987,449 | +3.0% | TDOT |
| CNY210 | The sweeping on various interstate and state routes | Counties Bradley, Grundy, Hamilton, Marion, Putnam, Sequatchie, And White | 1 | Sweeping Corporation of America, LLC | $868,403 | TDOT | ||
| CNY212 | R1bvar-m3-048 the sweeping on various interstate and state routes | Counties Anderson, Blount, Campbell, Cocke, Jefferson, Knox, Loudon, Monroe, Roane, And Sevier | 1 | Sweeping Corporation of America, LLC | $845,930 | TDOT | ||
| CNY296 | The miscellaneous safety improvements including high friction surface treatment (hfst) on various local roads | Grundy And Sequatchie Counties | 4 | Superior Traffic Control, LLC | $792,181 | $814,229 | +3.0% | TDOT |
| CNY303 | 35(79),78s035-f3-002,hsip-61(49),73014-3222-94 the miscellaneous safety improvements on u.s. 411/u.s. 441 (s.r. 35), s.r. 61, and various local roads | Counties Cocke, Greene, Roane, And Sevier | 3 | Superior Traffic Control, LLC | $640,837 | $653,970 | +2.0% | TDOT |
| CNY208 | The sweeping on various and state routes | Counties Davidson, Montgomery, Sumner, And Williamson | 1 | Sweeping Corporation of America, LLC | $488,308 | TDOT | ||
| CNY226 | The drain cleaning on various interstate and state routes | Counties Bradley, Grundy, Hamilton, Marion, Putnam, Sequatchie, And White | 1 | Sweeping Corporation of America, LLC | $447,100 | TDOT | ||
| CNY225 | The drain cleaning on various interstate and state routes | Fayette And Shelby Counties | 1 | Sweeping Corporation of America, LLC | $438,870 | TDOT | ||
| CNY271 | The miscellaneous safety improvements on various local roads | Lawrence And Marshall Counties | 2 | Superior Traffic Control, LLC | $426,138 | $458,026 | +7.0% | TDOT |
| CNY269 | The construction of a concrete box bridge on pleasant valley road over dry weakley creek (l.m. 1.07), including grading, drainage, and paving | Lawrence County | 4 | Capital City Construction Services, LLC | $421,934 | $585,365 | +39% | TDOT |
| CNY307 | The installation of multimodal signal and intersection upgrades on u.s. 51 (s.r. 3) at u.s. 78 (s.r. 4, lamar avenue) (l.m. 9.30) and at eastmoreland avenue (l. | Shelby County | 2 | Bluff City Construction Company, LLC | $418,876 | $430,240 | +3.0% | TDOT |
| CNY285 | The microsurfacing on s.r. 417 from near north ellington parkway (l.m. 0.12) to s.r. 373 (l.m. 1.90) | Marshall County | 2 | Asphalt Paving Systems, Inc. | $411,342 | $553,214 | +34% | TDOT |
| CNY275 | The resurfacing on u.s. 431 (s.r. 65) from brick school road (l.m. 14.49) to the kentucky state line (l.m. 16.20) | Robertson County | 2 | Eubank Asphalt Paving & Sealing, LLC | $379,130 | $479,415 | +26% | TDOT |
| CNY231 | R1bvar-m3-049 the drain cleaning on various interstate and state routes | Counties Anderson, Blount, Campbell, Cocke, Grainger, Jefferson, Knox, Loudon, Monroe, Roane, And Sevier | 1 | Sweeping Corporation of America, LLC | $368,970 | TDOT | ||
| CNY304 | The traffic signal modernization on u.s. 25w (s.r. 9) from near s.r. 297 (south main street) (l.m. 0.21) to near kentucky street (l.m. 0.37) in jellico | Campbell County | 1 | Stansell Electric Company, Inc. | $349,727 | TDOT | ||
| CNY278 | The installation of signals on u.s. 43 (s.r. 6) at the intersection of u.s. 64 (s.r. 15) (l.m. 18.04) in lawrenceburg | Lawrence County | 1 | Stansell Electric Company, Inc. | $322,806 | TDOT | ||
| CNY272 | The miscellaneous safety improvements on various local roads | Macon County | 3 | Superior Traffic Control, LLC | $252,319 | $254,657 | +1.0% | TDOT |
| CNY222 | The drain cleaning on various state routes | Counties Davidson, Sumner, And Williamson | 1 | Sweeping Corporation of America, LLC | $239,450 | TDOT | ||
| CNY213 | The sweeping on various interstate and state routes | Counties Carter, Sullivan, Unicoi, And Washington | 1 | Sweeping Corporation of America, LLC | $103,635 | TDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TDOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.