TxDOT contract A00037264 bid tabulation
Bridge Replacement, OLD GRANBURY RD (OLD GRANBURY RD OVER WALNUT CREEK to .). Let by Texas DOT on April 8, 2026, Hood, Fort Worth District. 8 bids received; low bid $632,977 by Garret Shields Infrastructure, -20% against the engineer's estimate of $795,481.
- Owner
- Texas DOT
- Letting
- 08 APR 2026
- Pay items
- 51
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Garret Shields Infrastructure | $632,977 | Low | -20% |
| 2 | Tucan Contracting, LLC | $658,219 | +4.0% | -17% |
| 3 | Skyline Bridge LLC | $663,794 | +5.0% | -17% |
| 4 | Hodges and Son Construction Company, Inc. | $678,119 | +7.0% | -15% |
| 5 | Knife River Corporation - South | $721,367 | +14% | -9.0% |
| 6 | Delgado'S Contractors, LLC | $734,414 | +16% | -8.0% |
| 7 | Ed Bell Construction Company | $859,316 | +36% | +8.0% |
| 8 | Coppell Construction Co., Inc. | $945,897 | +49% | +19% |
Engineer's estimate: $795,481.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Garret Shields Infrastructure | 2. Tucan Contracting, LLC | 3. Skyline Bridge LLC | 4. Hodges and Son Construction Company, Inc. | 5. Knife River Corporation - South | 6. Delgado'S Contractors, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 4 | $5,000.00 | $1,000.00 | $2,200.00 | $1,000.00 | $3,700.00 | $7,500.00 | $750.00 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 2 | $400.00 | $1,000.00 | $1,650.00 | $1,200.00 | $2,000.00 | $1,000.00 | $500.00 |
| 3 | Remove (14"-18") TRT/untrt base & asphalt pavement (105-7014) | SY | 728 | $22.00 | $20.00 | $6.58 | $9.90 | $6.00 | $7.00 | $8.00 |
| 4 | Excavation (roadway & channel) (110-7004) | CY | 716 | $30.00 | $30.00 | $16.50 | $16.00 | $8.00 | $20.00 | $20.00 |
| 5 | Embankment (final)(DC)(type B) (132-7004) | CY | 858 | $50.00 | $30.00 | $13.20 | $34.00 | $12.00 | $15.00 | $30.00 |
| 6 | Compost manuf topsoil (4") (161-7002) | SY | 2,128 | $3.00 | $4.00 | $1.54 | $4.50 | $1.50 | $1.10 | $3.00 |
| 7 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 2,128 | $1.00 | $0.50 | $1.42 | $1.37 | $1.50 | $0.70 | $1.00 |
| 8 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 2,128 | $1.00 | $0.70 | $1.42 | $1.25 | $1.00 | $0.55 | $1.00 |
| 9 | Vegetative watering (168-7001) | TGL | 149 | $26.00 | $10.00 | $33.00 | $1.00 | $1.00 | $10.00 | $50.00 |
| 10 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 857 | $28.00 | $25.00 | $38.50 | $35.00 | $26.00 | $30.00 | $23.00 |
| 11 | Salvage, haul & stockpile reclaimed asphalt PV (0 to 2") (305-7002) | SY | 728 | $6.00 | $20.00 | $6.58 | $8.00 | $5.00 | $3.00 | $6.00 |
| 12 | Asphalt (RC-250) (316-7016) | GAL | 257 | $30.00 | $48.00 | $53.35 | $51.50 | $10.00 | $8.00 | $55.00 |
| 13 | Aggregate (type-B, GR-5)(sac-B) (316-7175) | CY | 8 | $135.00 | $1,900.00 | $2,090.00 | $2,120.00 | $1,500.00 | $900.00 | $1,955.00 |
| 14 | SP mixes SP-C sac-B PG70-22 (exempt) (344-7038) | TON | 90 | $200.00 | $385.00 | $423.50 | $445.00 | $200.00 | $300.00 | $395.00 |
| 15 | Tack coat (344-7077) | GAL | 171 | $10.00 | $19.00 | $1.65 | $5.00 | $8.00 | $2.50 | $2.50 |
| 16 | Cem stabil BKFL (400-7010) | CY | 92 | $300.00 | $200.00 | $220.00 | $265.00 | $250.00 | $330.00 | $265.00 |
| 17 | Drilled shaft (36 in) (416-7006) | LF | 180 | $320.00 | $300.00 | $236.50 | $275.00 | $265.00 | $325.00 | $290.00 |
| 18 | Class C concrete (abutment)(HPC) (420-7013) | CY | 36.10 | $1,580.00 | $1,000.00 | $1,320.00 | $950.00 | $1,000.00 | $1,500.00 | $1,250.00 |
| 19 | Reinforced concrete slab (HPC) (422-7002) | SF | 1,300 | $32.00 | $25.00 | $27.50 | $30.00 | $32.00 | $50.00 | $25.00 |
| 20 | Approach slab (422-7013) | CY | 38.50 | $900.00 | $800.00 | $935.00 | $715.00 | $800.00 | $875.00 | $1,000.00 |
| 21 | Prestressed concrete girder (TX28) (425-7001) | LF | 198 | $300.00 | $240.00 | $259.44 | $373.75 | $290.00 | $350.00 | $300.00 |
| 22 | Riprap (mow strip)(4 in) (432-7013) | CY | 25 | $725.00 | $500.00 | $715.00 | $690.00 | $700.00 | $825.00 | $650.00 |
| 23 | Riprap (stone protection)(24 in) (432-7045) | CY | 452 | $190.00 | $150.00 | $176.00 | $116.00 | $180.00 | $125.00 | $150.00 |
| 24 | Rail (type SSTR)(HPC) (450-7025) | LF | 148 | $125.00 | $150.00 | $165.00 | $140.00 | $200.00 | $180.00 | $115.00 |
| 25 | Armor joint (sealed) (454-7003) | LF | 44 | $175.00 | $200.00 | $198.00 | $135.00 | $150.00 | $190.00 | $200.00 |
| 26 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $30,000 | $10,000 | $8,800.00 | $8,600.00 | $15,000 | $25,000 | $20,000 |
| 27 | Mobilization (500-7001) | LS | 1 | $68,907 | $50,000 | $55,000 | $60,000 | $60,000 | $72,000 | $50,000 |
| 28 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $7,500.00 | $4,000.00 | $1,320.00 | $2,650.00 | $11,000 | $1,900.00 | $2,000.00 |
| 29 | Portable changeable message sign (503-7002) | EACH | 3 | $12,000 | $1,000.00 | $7,700.00 | $6,237.50 | $10,000 | $5,000.00 | $10,000 |
| 30 | Rock filter dams (install) (type 1) (506-7001) | LF | 27 | $50.00 | $35.00 | $82.50 | $58.00 | $1.00 | $39.00 | $75.00 |
| 31 | Rock filter dams (remove) (506-7011) | LF | 27 | $20.00 | $10.00 | $22.00 | $15.00 | $1.00 | $19.00 | $10.00 |
| 32 | Construction exits (install) (type 1) (506-7020) | SY | 78 | $40.00 | $30.00 | $38.50 | $10.00 | $1.00 | $35.00 | $55.00 |
| 33 | Construction exits (remove) (506-7024) | SY | 78 | $15.00 | $10.00 | $14.30 | $1.00 | $1.00 | $10.00 | $10.00 |
| 34 | Temporary sediment control fence (install) (506-7039) | LF | 792 | $5.00 | $5.00 | $4.13 | $4.00 | $1.00 | $5.75 | $65.00 |
| 35 | Temporary sediment control fence (remove) (506-7041) | LF | 792 | $1.00 | $1.00 | $1.10 | $1.50 | $1.00 | $1.20 | $10.00 |
| 36 | Metal W-beam guard fence (timber post) (540-7001) | LF | 125 | $28.00 | $30.00 | $24.75 | $28.00 | $28.00 | $25.00 | $28.00 |
| 37 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 2 | $1,400.00 | $1,000.00 | $1,375.00 | $1,275.00 | $1,200.00 | $1,400.00 | $1,350.00 |
| 38 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,335.00 | $1,500.00 | $1,375.00 | $1,500.00 | $1,500.00 | $1,400.00 | $1,250.00 |
| 39 | Metal beam guard fence trans (non - sym) (540-7016) | EACH | 2 | $970.00 | $1,000.00 | $825.00 | $1,000.00 | $1,000.00 | $850.00 | $1,000.00 |
| 40 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,200.00 | $3,500.00 | $3,245.00 | $3,390.00 | $3,200.00 | $3,250.00 | $3,250.00 |
| 41 | Wire fence (remove) (552-7011) | LF | 766 | $7.50 | $1.00 | $2.20 | $5.00 | $5.00 | $4.00 | $10.00 |
| 42 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 4 | $900.00 | $800.00 | $880.00 | $1,500.00 | $800.00 | $1,100.00 | $1,000.00 |
| 43 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $175.00 | $100.00 | $165.00 | $150.00 | $50.00 | $100.00 | $350.00 |
| 44 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 6 | $33.00 | $5.00 | $22.00 | $26.50 | $20.00 | $22.00 | $30.00 |
| 45 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016) | EACH | 6 | $23.00 | $5.00 | $22.00 | $26.50 | $20.00 | $22.00 | $30.00 |
| 46 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 4 | $75.00 | $40.00 | $66.00 | $150.00 | $500.00 | $66.00 | $30.00 |
| 47 | Pavement sler 6" (666-7347) | LF | 360 | $1.00 | $1.00 | $0.44 | $0.48 | $2.00 | $0.44 | $2.50 |
| 48 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 766 | $1.00 | $3.50 | $3.30 | $3.20 | $5.00 | $3.30 | $2.50 |
| 49 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 766 | $1.00 | $3.50 | $3.30 | $3.20 | $5.00 | $3.30 | $2.50 |
| 50 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 10 | $6.00 | $15.00 | $11.00 | $10.75 | $25.00 | $11.00 | $10.00 |
| 51 | Pavement surface preparation for marking (6") (678-7002) | LF | 1,532 | $1.00 | $0.20 | $0.11 | $0.12 | $1.00 | $0.11 | $1.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.