TxDOT contract A00130461 bid tabulation
Transportation Non-Roadway, IH 30 (1.6 Mi W of US 67, WB to 1.0 Mi W of US 67, WB). Let by Texas DOT on May 7, 2026, Titus, Atlanta District. 6 bids received; low bid $9,498,729 by East Texas Bridge, Inc., -16% against the engineer's estimate of $11,312,219.
- Owner
- Texas DOT
- Letting
- 07 MAY 2026
- Pay items
- 138
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | East Texas Bridge, Inc. | $9,498,729 | Low | -16% |
| 2 | Baker & Company Construction, LLC | $10,553,425 | +11% | -7.0% |
| 3 | Longview Bridge and Road, LTD. | $10,622,365 | +12% | -6.0% |
| 4 | CDM Holdings | $11,081,707 | +17% | -2.0% |
| 5 | R Construction Civil, LLC | $11,291,701 | +19% | 0.0% |
| 6 | Drake Companies LLC | $12,337,809 | +30% | +9.0% |
Engineer's estimate: $11,312,219.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. East Texas Bridge, Inc. | 2. Baker & Company Construction, LLC | 3. Longview Bridge and Road, LTD. | 4. CDM Holdings | 5. R Construction Civil, LLC | 6. Drake Companies LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 68.40 | $1,500.00 | $1,500.00 | $1,050.00 | $5,000.00 | $1,100.00 | $2,500.00 | $2,000.00 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 485 | $25.00 | $10.00 | $23.60 | $25.00 | $23.50 | $6.00 | $10.00 |
| 3 | Removing concrete (traffic barrier) (104-7035) | LF | 165 | $30.00 | $15.00 | $46.25 | $37.00 | $15.00 | $61.00 | $25.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 31,343 | $12.00 | $10.00 | $7.40 | $10.50 | $7.60 | $23.00 | $13.00 |
| 5 | Excavation (channel) (110-7002) | CY | 358 | $20.00 | $12.00 | $10.65 | $8.00 | $15.90 | $30.00 | $25.00 |
| 6 | Embankment (final)(DC)(type A) (132-7002) | CY | 22,669 | $20.00 | $15.00 | $6.15 | $16.25 | $26.25 | $23.00 | $17.00 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 41,221 | $0.40 | $0.12 | $0.20 | $0.25 | $0.11 | $0.15 | $0.12 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 41,221 | $0.40 | $0.12 | $0.20 | $0.15 | $0.11 | $0.15 | $0.12 |
| 9 | Bond fiber MTRX seed (permanent)(rural)(sand) (164-7073) | SY | 82,438 | $0.35 | $0.54 | $0.75 | $0.15 | $0.50 | $0.20 | $0.54 |
| 10 | Vegetative watering (168-7001) | TGL | 1,970.50 | $26.00 | $6.00 | $5.00 | $16.00 | $1.00 | $200.00 | $8.75 |
| 11 | Cement (275-7001) | TON | 624 | $220.00 | $255.00 | $252.00 | $300.00 | $287.50 | $200.00 | $273.00 |
| 12 | Cement TRT (existing material)(8") (275-7003) | SY | 41,359 | $4.00 | $3.00 | $4.85 | $2.60 | $4.40 | $5.25 | $3.50 |
| 13 | Prime coat (MC-30) (310-7004) | GAL | 10,342 | $6.00 | $5.50 | $8.40 | $6.40 | $4.55 | $10.00 | $6.00 |
| 14 | SP mixes SP-C PG70-22 (344-7019) | TON | 3,656 | $150.00 | $148.00 | $147.00 | $143.00 | $145.00 | $167.00 | $154.00 |
| 15 | SP mixes SP-C sac-A PG76-22 (344-7030) | TON | 1,165 | $150.00 | $153.00 | $148.00 | $148.00 | $145.00 | $164.00 | $166.00 |
| 16 | SP mixes SP-D PG70-22 (344-7051) | TON | 7,441 | $170.00 | $148.00 | $151.00 | $144.00 | $146.50 | $165.00 | $164.00 |
| 17 | Tack coat (344-7077) | GAL | 6,337 | $3.00 | $5.00 | $6.30 | $4.90 | $7.15 | $6.50 | $5.00 |
| 18 | Planing asphalt concrete pavement(3") (354-7052) | SY | 4,580 | $6.00 | $4.50 | $3.65 | $6.80 | $5.00 | $3.00 | $5.25 |
| 19 | Concrete pavement (CPCD) (11") (360-7021) | SY | 31,948 | $95.00 | $82.00 | $113.30 | $105.00 | $103.00 | $96.00 | $132.00 |
| 20 | Cem stabil BKFL (400-7010) | CY | 20 | $250.00 | $275.00 | $240.00 | $220.00 | $300.00 | $88.00 | $260.00 |
| 21 | Flowable backfill (401-7001) | CY | 3 | $550.00 | $300.00 | $470.00 | $410.00 | $325.00 | $1,100.00 | $500.00 |
| 22 | Trench excavation protection (402-7001) | LF | 1,031 | $10.00 | $10.00 | $4.00 | $10.00 | $9.00 | $15.00 | $13.75 |
| 23 | Drilled shaft (high mast pole) (60 in) (416-7037) | LF | 96 | $800.00 | $1,065.00 | $580.00 | $1,100.00 | $1,020.00 | $1,050.00 | $1,100.00 |
| 24 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 210 | $300.00 | $285.00 | $245.00 | $290.00 | $275.00 | $280.00 | $295.00 |
| 25 | Class A concrete (miscellaneous) (420-7002) | CY | 50 | $640.00 | $250.00 | $710.00 | $515.00 | $600.00 | $785.00 | $665.00 |
| 26 | Class C concrete (collar) (420-7061) | EACH | 4 | $2,000.00 | $1,000.00 | $1,575.00 | $950.00 | $2,750.00 | $1,900.00 | $1,950.00 |
| 27 | Class C concrete (miscellaneous) (420-7067) | CY | 27 | $2,000.00 | $650.00 | $815.00 | $1,690.00 | $750.00 | $1,200.00 | $700.00 |
| 28 | Riprap (concrete)(4 in) (432-7001) | CY | 554 | $575.00 | $500.00 | $945.00 | $505.00 | $585.00 | $455.00 | $660.00 |
| 29 | Riprap (mow strip)(4 in) (432-7013) | CY | 60 | $678.00 | $515.00 | $815.00 | $510.00 | $650.00 | $475.00 | $630.00 |
| 30 | Riprap (stone protection)(12 in) (432-7041) | CY | 54 | $250.00 | $195.00 | $215.00 | $225.00 | $220.00 | $185.00 | $221.65 |
| 31 | Rail (handrail)(type F) (450-7063) | LF | 459 | $200.00 | $155.00 | $124.00 | $165.00 | $210.00 | $220.00 | $220.00 |
| 32 | RC pipe (CL III)(18 in) (464-7003) | LF | 94 | $70.00 | $60.00 | $73.00 | $61.00 | $56.00 | $122.00 | $61.00 |
| 33 | RC pipe (CL III)(24 in) (464-7005) | LF | 77 | $100.00 | $90.00 | $100.00 | $86.00 | $78.00 | $211.00 | $86.00 |
| 34 | RC pipe (CL III)(36 in) (464-7009) | LF | 734 | $150.00 | $155.00 | $132.00 | $136.00 | $142.00 | $197.00 | $132.00 |
| 35 | RC pipe (CL III)(42 in) (464-7010) | LF | 292 | $250.00 | $200.00 | $172.00 | $190.00 | $175.00 | $267.00 | $166.00 |
| 36 | Inlet (complete)(pco)(5FT)(left) (465-7022) | EACH | 3 | $12,000 | $11,000 | $9,700.00 | $9,100.00 | $9,142.50 | $7,100.00 | $10,250 |
| 37 | Inlet (complete)(pco)(5FT)(both) (465-7024) | EACH | 1 | $15,000 | $11,500 | $9,700.00 | $9,800.00 | $9,734.75 | $6,850.00 | $10,930 |
| 38 | Inl(CMP)(pazd-CZ)(FG)(3FTX3FT-3FTX3FT) (465-7163) | EACH | 1 | $7,000.00 | $7,000.00 | $6,110.00 | $5,800.00 | $8,567.50 | $4,000.00 | $7,000.00 |
| 39 | Inl(CMP)(pazd-CZ)(FG)(5FTX5FT-3FTX3FT) (465-7166) | EACH | 2 | $11,500 | $9,000.00 | $7,305.00 | $6,550.00 | $9,717.50 | $5,400.00 | $8,300.00 |
| 40 | Set (pipe runner assembly) (467-7001) | EACH | 1 | $10,000 | $1,500.00 | $7,150.00 | $4,750.00 | $1,500.00 | $4,900.00 | $7,000.00 |
| 41 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 2 | $2,500.00 | $900.00 | $1,550.00 | $1,250.00 | $1,023.50 | $2,700.00 | $1,250.00 |
| 42 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 1 | $2,700.00 | $1,325.00 | $1,945.00 | $1,700.00 | $1,403.00 | $2,900.00 | $2,270.00 |
| 43 | Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366) | EACH | 1 | $8,080.00 | $3,850.00 | $4,950.00 | $3,950.00 | $3,823.75 | $5,300.00 | $3,950.00 |
| 44 | Set (type II) (42 in) (RCP) (6: 1) (P) (467-7380) | EACH | 1 | $10,200 | $7,650.00 | $8,166.00 | $7,500.00 | $7,000.00 | $8,700.00 | $7,500.00 |
| 45 | Grate & frame (471-7003) | EACH | 90 | $1,000.00 | $1,250.00 | $1,050.00 | $1,560.00 | $1,606.55 | $1,700.00 | $2,000.00 |
| 46 | Pipe (PVC) (schedule 80) (6 in) (481-7027) | LF | 600 | $100.00 | $50.00 | $18.50 | $30.00 | $31.00 | $80.00 | $40.00 |
| 47 | Removing structure (set) (496-7004) | EACH | 2 | $600.00 | $300.00 | $954.00 | $465.00 | $250.00 | $575.00 | $275.00 |
| 48 | Removing structure (headwall) (496-7006) | EACH | 8 | $1,800.00 | $350.00 | $954.00 | $930.00 | $750.00 | $1,300.00 | $500.00 |
| 49 | Removing structure (pipe) (496-7007) | LF | 102 | $30.00 | $15.00 | $38.00 | $36.50 | $25.00 | $92.00 | $20.00 |
| 50 | Mobilization (500-7001) | LS | 1 | $1,042,000 | $525,000 | $630,000 | $1,000,000 | $1,000,000 | $300,000 | $1,000,000 |
| 51 | Barricades, signs and traffic handling (502-7001) | MO | 15 | $5,000.00 | $2,500.00 | $5,300.00 | $1,925.00 | $2,500.00 | $6,800.00 | $6,500.00 |
| 52 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $18,000 | $17,000 | $12,000 | $22,759 | $16,500 | $19,250 |
| 53 | TMA (stationary) (505-7001) | DAY | 15 | $200.00 | $300.00 | $471.00 | $330.00 | $241.25 | $225.00 | $265.00 |
| 54 | TMA (mobile operation) (505-7003) | DAY | 15 | $150.00 | $300.00 | $753.00 | $465.00 | $143.75 | $1,850.00 | $360.00 |
| 55 | Rock filter dams (install) (type 1) (506-7001) | LF | 315 | $50.00 | $42.00 | $61.00 | $35.00 | $40.00 | $75.00 | $40.00 |
| 56 | Rock filter dams (remove) (506-7011) | LF | 315 | $15.00 | $10.00 | $5.00 | $11.00 | $10.20 | $11.00 | $11.00 |
| 57 | Construction exits (install) (type 1) (506-7020) | SY | 112 | $30.00 | $35.00 | $31.00 | $51.00 | $38.00 | $49.00 | $36.00 |
| 58 | Construction exits (remove) (506-7024) | SY | 112 | $9.00 | $12.00 | $14.50 | $11.00 | $15.00 | $11.00 | $14.00 |
| 59 | Temporary sediment control fence (install) (506-7039) | LF | 2,040 | $7.00 | $4.30 | $3.70 | $5.50 | $4.00 | $5.00 | $4.50 |
| 60 | Temporary sediment control fence (remove) (506-7041) | LF | 2,040 | $4.00 | $1.00 | $1.05 | $0.70 | $1.25 | $0.65 | $1.50 |
| 61 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 403 | $8.00 | $5.50 | $8.40 | $5.50 | $5.10 | $5.00 | $6.00 |
| 62 | Biodegradable erosion control logs (remove) (506-7046) | LF | 403 | $4.00 | $1.00 | $2.10 | $0.70 | $1.25 | $0.65 | $2.00 |
| 63 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 5,310 | $85.00 | $82.00 | $59.00 | $32.00 | $57.50 | $95.00 | $94.50 |
| 64 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 3,600 | $15.00 | $6.00 | $11.50 | $7.00 | $11.25 | $5.25 | $7.50 |
| 65 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 5,310 | $20.00 | $10.00 | $38.00 | $9.00 | $36.75 | $6.00 | $11.00 |
| 66 | Concrete curb (type II) (529-7002) | LF | 2,397 | $40.00 | $8.00 | $4.20 | $8.25 | $7.25 | $7.00 | $10.00 |
| 67 | Concrete curb & gutter (armor curb) (529-7018) | LF | 100 | $500.00 | $550.00 | $281.00 | $375.00 | $585.00 | $485.00 | $300.00 |
| 68 | Concrete sidewalks (4") (531-7001) | SY | 1,542 | $75.00 | $70.00 | $100.00 | $62.00 | $137.70 | $73.00 | $73.20 |
| 69 | Curb ramps (type 1) (531-7005) | EACH | 1 | $2,200.00 | $2,500.00 | $4,725.00 | $2,600.00 | $2,281.50 | $1,900.00 | $1,920.00 |
| 70 | Curb ramps (type 2) (531-7006) | EACH | 5 | $2,200.00 | $2,500.00 | $4,200.00 | $2,600.00 | $2,281.50 | $1,900.00 | $1,700.00 |
| 71 | Curb ramps (type 10) (531-7011) | EACH | 1 | $2,200.00 | $2,500.00 | $6,825.00 | $2,500.00 | $2,223.00 | $1,900.00 | $1,920.00 |
| 72 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,100 | $30.00 | $24.00 | $25.00 | $24.75 | $24.00 | $25.00 | $31.00 |
| 73 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 1 | $1,600.00 | $1,750.00 | $1,600.00 | $1,760.00 | $2,400.00 | $1,700.00 | $1,675.00 |
| 74 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,250.00 | $1,400.00 | $1,340.00 | $1,430.00 | $1,750.00 | $1,400.00 | $1,400.00 |
| 75 | Remove metal beam guard fence (542-7001) | LF | 425 | $10.00 | $2.15 | $2.10 | $2.20 | $2.50 | $2.00 | $2.50 |
| 76 | Remove terminal anchor section (542-7002) | EACH | 1 | $443.68 | $215.00 | $210.00 | $220.00 | $225.00 | $215.00 | $220.00 |
| 77 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 1 | $250.00 | $160.00 | $210.00 | $165.00 | $225.00 | $160.00 | $220.00 |
| 78 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $4,315.00 | $3,300.00 | $3,255.00 | $3,400.00 | $3,475.00 | $3,300.00 | $3,410.00 |
| 79 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 1 | $2,500.00 | $2,150.00 | $2,625.00 | $2,200.00 | $2,550.00 | $2,200.00 | $1,375.00 |
| 80 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,500.00 | $535.00 | $1,575.00 | $550.00 | $1,530.00 | $530.00 | $880.00 |
| 81 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $13,200 | $9,500.00 | $10,500 | $9,500.00 | $10,200 | $9,200.00 | $9,020.00 |
| 82 | Pipe underdrains (type 8) (6") (556-7008) | LF | 2,585 | $60.00 | $42.00 | $29.50 | $31.00 | $53.50 | $35.00 | $38.50 |
| 83 | Remove RD IL asm (trans-base) (610-7009) | EACH | 21 | $800.00 | $800.00 | $910.00 | $825.00 | $765.00 | $840.00 | $830.00 |
| 84 | In RD IL (type SA) 50T-10 (400W EQ) LED (610-7198) | EACH | 21 | $5,000.00 | $6,300.00 | $5,885.00 | $6,500.00 | $6,015.00 | $6,600.00 | $6,500.00 |
| 85 | HI MST IL pole (150 FT)( 80 MPH) (613-7005) | EACH | 3 | $50,000 | $61,000 | $46,050 | $62,700 | $58,500 | $63,000 | $63,000 |
| 86 | LED HI MST IL asm (6 fixt) (type A) (614-7002) | EACH | 3 | $35,000 | $50,000 | $43,075 | $51,500 | $47,685 | $52,000 | $51,500 |
| 87 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 14,153 | $14.80 | $8.85 | $8.10 | $9.00 | $8.45 | $9.00 | $9.00 |
| 88 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 204 | $27.00 | $20.60 | $40.00 | $21.00 | $19.65 | $23.00 | $22.00 |
| 89 | Electrical conductor (no.8) insulated (620-7008) | LF | 13,926 | $2.25 | $2.65 | $2.20 | $2.70 | $2.50 | $3.00 | $3.00 |
| 90 | Electrical conductor (no.6) bare (620-7009) | LF | 11,133 | $2.80 | $2.90 | $2.20 | $3.00 | $2.75 | $3.00 | $3.00 |
| 91 | Ground box type A (122311) (624-7001) | EACH | 6 | $1,100.00 | $1,140.00 | $1,015.00 | $1,170.00 | $1,090.00 | $1,200.00 | $1,175.00 |
| 92 | Ground box type A (122311)W/apron (624-7002) | EACH | 29 | $1,500.00 | $1,400.00 | $735.00 | $1,430.00 | $1,330.00 | $1,450.00 | $1,450.00 |
| 93 | Ground box type D (162922)W/apron (624-7008) | EACH | 1 | $1,700.00 | $1,625.00 | $1,092.00 | $1,675.00 | $1,555.00 | $1,700.00 | $1,675.00 |
| 94 | Remove electrical services (628-7002) | EACH | 1 | $1,000.00 | $800.00 | $910.00 | $820.00 | $780.00 | $800.00 | $1,000.00 |
| 95 | Elc SRV type A 120/240 060(NS)SS(E)TP(O) (628-7011) | EACH | 1 | $8,500.00 | $6,550.00 | $8,870.00 | $6,750.00 | $6,250.00 | $6,500.00 | $6,750.00 |
| 96 | Elc SRV type A 240/480 060(SS)SS(E)SP(O) (628-7057) | EACH | 2 | $11,000 | $7,075.00 | $9,970.00 | $7,300.00 | $6,750.00 | $7,000.00 | $7,300.00 |
| 97 | Aluminum signs (type G) (636-7002) | SF | 245 | $50.00 | $43.00 | $36.50 | $44.00 | $41.00 | $40.00 | $44.00 |
| 98 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 3 | $850.00 | $765.00 | $690.00 | $785.00 | $675.00 | $825.00 | $785.00 |
| 99 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 1 | $950.00 | $1,100.00 | $815.00 | $1,140.00 | $800.00 | $1,250.00 | $1,150.00 |
| 100 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,000.00 | $1,410.00 | $1,360.00 | $1,450.00 | $1,325.00 | $1,700.00 | $1,500.00 |
| 101 | Install small roadside sign support and assembly TYS80(2)SA(P) (644-7048) | EACH | 1 | $1,500.00 | $2,000.00 | $2,370.00 | $2,040.00 | $2,300.00 | $2,800.00 | $2,050.00 |
| 102 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 4 | $1,000.00 | $660.00 | $625.00 | $675.00 | $625.00 | $650.00 | $675.00 |
| 103 | Remove SM RD SN sup&AM (644-7073) | EACH | 1 | $175.00 | $100.00 | $83.00 | $132.00 | $85.00 | $125.00 | $130.00 |
| 104 | Remove lrsa (647-7003) | EACH | 3 | $1,935.00 | $730.00 | $820.00 | $750.00 | $695.00 | $800.00 | $750.00 |
| 105 | Install delineator assembly (D-SW)SZ 1(WFLX)GND(BI) (658-7004) | EACH | 34 | $50.00 | $110.00 | $79.00 | $110.00 | $76.50 | $100.00 | $183.00 |
| 106 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 10 | $42.00 | $50.00 | $58.00 | $50.00 | $60.00 | $60.00 | $35.00 |
| 107 | Work zone pavement marking removing (traffic BTN) type W (662-7058) | LF | 10,882 | $3.00 | $1.90 | $1.85 | $1.95 | $1.80 | $1.75 | $1.10 |
| 108 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 533 | $2.00 | $2.15 | $2.10 | $2.20 | $2.05 | $2.00 | $2.20 |
| 109 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 5,132 | $1.00 | $1.30 | $1.30 | $1.35 | $1.25 | $1.25 | $1.10 |
| 110 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 749 | $4.00 | $4.30 | $4.20 | $4.40 | $4.10 | $4.00 | $2.20 |
| 111 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 2,623 | $8.00 | $6.45 | $6.30 | $6.60 | $6.15 | $6.00 | $6.60 |
| 112 | Ref pavement marking type I (W)(med nose)(100MIL) (666-7078) | EACH | 6 | $300.00 | $535.00 | $525.00 | $550.00 | $510.00 | $500.00 | $550.00 |
| 113 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 10,112 | $1.35 | $2.70 | $2.65 | $2.75 | $2.55 | $2.50 | $1.10 |
| 114 | All-wther PM type I (W)6"(broken)(100MIL) (666-7310) | LF | 2,316 | $1.35 | $1.07 | $1.05 | $1.10 | $1.05 | $1.00 | $2.20 |
| 115 | All-wther PM type I (Y)6"(solid)(100MIL) (666-7315) | LF | 4,248 | $1.35 | $1.07 | $1.05 | $1.10 | $1.05 | $1.00 | $1.10 |
| 116 | Pavement sler 6" (666-7347) | LF | 14,518 | $0.50 | $0.54 | $0.55 | $0.55 | $0.51 | $0.50 | $1.10 |
| 117 | Pavement sler 8" (666-7348) | LF | 4,089 | $0.60 | $0.54 | $0.55 | $0.55 | $0.55 | $0.50 | $1.10 |
| 118 | Pavement sler 12" (666-7350) | LF | 430 | $0.70 | $2.70 | $2.65 | $2.75 | $2.55 | $2.50 | $2.20 |
| 119 | Pavement sler 24" (666-7352) | LF | 2,623 | $1.15 | $3.50 | $3.40 | $3.60 | $3.35 | $3.50 | $4.40 |
| 120 | Pavement sler (med nose) (666-7355) | EACH | 6 | $100.00 | $270.00 | $262.00 | $275.00 | $255.00 | $260.00 | $275.00 |
| 121 | Pavement sler (symbol) (666-7363) | EACH | 2 | $200.00 | $110.00 | $105.00 | $110.00 | $102.00 | $100.00 | $220.00 |
| 122 | Prefabricated PM type B (W)(6")(broken)contrast (668-7012) | LF | 466 | $20.00 | $21.50 | $21.00 | $22.00 | $20.50 | $22.00 | $2.20 |
| 123 | Prefabricated PM type C (W)(symbol) (668-7109) | EACH | 2 | $524.50 | $270.00 | $262.00 | $275.00 | $255.00 | $260.00 | $275.00 |
| 124 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 339 | $5.00 | $6.45 | $6.30 | $6.60 | $6.25 | $6.00 | $5.50 |
| 125 | Eliminating existing PM & markers (6") (677-7002) | LF | 2,199 | $1.00 | $1.07 | $1.05 | $1.10 | $1.05 | $1.00 | $1.10 |
| 126 | Pavement surface preparation for marking (6") (678-7002) | LF | 14,518 | $1.00 | $0.11 | $0.11 | $0.15 | $0.10 | $0.10 | $1.10 |
| 127 | Pavement surface preparation for marking (8") (678-7004) | LF | 4,071 | $1.20 | $0.22 | $0.20 | $0.25 | $0.20 | $0.20 | $1.10 |
| 128 | Pavement surface preparation for marking (12") (678-7006) | LF | 430 | $1.50 | $0.53 | $0.55 | $0.55 | $0.55 | $0.50 | $2.20 |
| 129 | Pavement surface preparation for marking (24") (678-7008) | LF | 2,623 | $2.50 | $1.07 | $1.05 | $1.10 | $1.05 | $1.00 | $3.30 |
| 130 | Pavement surface preparation for marking (symbol) (678-7021) | EACH | 2 | $5.00 | $53.50 | $53.00 | $55.00 | $51.00 | $50.00 | $110.00 |
| 131 | Pavement surface preparation for marking (med nose) (678-7024) | EACH | 6 | $5.00 | $53.50 | $53.00 | $55.00 | $51.00 | $50.00 | $165.00 |
| 132 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 4 | $375.00 | $360.00 | $605.00 | $370.00 | $345.00 | $360.00 | $370.00 |
| 133 | Install RDSD flash beacon assembly (685-7001) | EACH | 2 | $6,250.00 | $6,700.00 | $7,120.00 | $6,875.00 | $6,375.00 | $6,600.00 | $6,875.00 |
| 134 | Remove traffic signal PL (686-7313) | EACH | 1 | $2,000.00 | $1,825.00 | $910.00 | $1,870.00 | $1,734.00 | $1,800.00 | $1,900.00 |
| 135 | Tree and brush removal (752-7014) | ACRE | 4 | $10,000 | $30,000 | $10,500 | $15,000 | $27,500 | $3,000.00 | $30,000 |
| 136 | Wide flange pavement terminals (3003-7001) | LF | 30 | $600.00 | $850.00 | $805.00 | $470.00 | $1,326.00 | $425.00 | $875.00 |
| 137 | Permeable concrete edge drain (4021-7001) | LF | 2,585 | $80.00 | $66.50 | $73.00 | $70.00 | $62.00 | $90.00 | $66.00 |
| 138 | Water filled barrier (5055-7001) | LF | 500 | $200.00 | $100.00 | $126.00 | $53.00 | $115.00 | $55.00 | $160.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 7, 2026. Compiled by Mirage Metrics.