TxDOT contract A00130805 bid tabulation
Bridge Replacement, GEBHARD RD (AT HAW CREEK to STR#AA04-89-001). Let by Texas DOT on June 4, 2025, Fayette, Yoakum District. 10 bids received; low bid $1,169,874 by Acme Bridge Company, Inc., -13% against the engineer's estimate of $1,339,013.
- Owner
- Texas DOT
- Letting
- 04 JUN 2025
- Pay items
- 45
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Acme Bridge Company, Inc. | $1,169,874 | Low | -13% |
| 2 | STX Civil | $1,210,697 | +3.0% | -10% |
| 3 | Trevway, Inc. | $1,215,300 | +4.0% | -9.0% |
| 4 | Knife River Corporation - South | $1,349,588 | +15% | +1.0% |
| 5 | Hodges and Son Construction Company, Inc. | $1,503,044 | +28% | +12% |
| 6 | E-Z Bel Construction, LLC | $1,532,368 | +31% | +14% |
| 7 | Dean Word Company, LTD. | $1,539,244 | +32% | +15% |
| 8 | Fuqua Construction Co., Inc. | $1,598,110 | +37% | +19% |
| 9 | Urban Infraconstruction LLC | $1,868,300 | +60% | +40% |
| 10 | C. E. Barker, LTD. | $1,885,410 | +61% | +41% |
Engineer's estimate: $1,339,013.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Acme Bridge Company, Inc. | 2. STX Civil | 3. Trevway, Inc. | 4. Knife River Corporation - South | 5. Hodges and Son Construction Company, Inc. | 6. E-Z Bel Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 7.40 | $3,000.00 | $1,730.00 | $2,000.00 | $2,000.00 | $2,174.00 | $5,400.00 | $3,500.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 479 | $23.00 | $28.60 | $25.00 | $27.19 | $30.34 | $20.00 | $16.00 |
| 3 | Excavation (channel) (110-7002) | CY | 636 | $24.00 | $24.90 | $15.00 | $10.00 | $10.00 | $20.00 | $19.00 |
| 4 | Embankment (final)(OC)(type C) (132-7005) | CY | 160 | $28.00 | $22.80 | $50.00 | $50.00 | $35.50 | $30.00 | $32.00 |
| 5 | Blading (150-7002) | HR | 32 | $100.00 | $96.90 | $70.00 | $50.00 | $158.00 | $20.00 | $50.00 |
| 6 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 1,452 | $2.00 | $0.53 | $1.00 | $1.26 | $1.36 | $3.00 | $2.00 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 363 | $2.00 | $1.05 | $1.00 | $1.26 | $1.36 | $2.00 | $8.00 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 363 | $2.00 | $1.05 | $1.00 | $1.26 | $1.36 | $2.00 | $8.00 |
| 9 | Vegetative watering (168-7001) | TGL | 16 | $120.00 | $79.00 | $50.00 | $100.00 | $70.00 | $1.00 | $15.00 |
| 10 | FL BS (compacted in place)(type E GR 5)(final pos) (247-7196) | CY | 450 | $135.00 | $139.00 | $140.00 | $187.00 | $143.00 | $120.00 | $125.00 |
| 11 | Asphalt (RC-250) (316-7016) | GAL | 392 | $15.00 | $13.10 | $15.00 | $26.00 | $13.40 | $15.00 | $21.00 |
| 12 | Aggregate (type-E, GR-5)(sac-B) (316-7194) | CY | 14.30 | $700.00 | $885.00 | $1,500.00 | $1,850.00 | $640.00 | $1,000.00 | $1,465.00 |
| 13 | Aggregate (type-PE, GR-4)(sac-B) (316-7232) | CY | 15.60 | $700.00 | $879.00 | $1,500.00 | $1,717.00 | $632.00 | $1,000.00 | $1,360.00 |
| 14 | Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264) | GAL | 666 | $15.00 | $9.60 | $20.00 | $21.89 | $10.50 | $20.00 | $17.00 |
| 15 | Cem stabil BKFL (400-7010) | CY | 168 | $215.00 | $183.00 | $180.00 | $100.00 | $175.00 | $270.00 | $450.00 |
| 16 | Temporary special shoring (403-7001) | SF | 800 | $20.80 | $5.00 | $15.00 | $79.00 | $10.00 | $1.00 | |
| 17 | Drilled shaft (24 in) (416-7004) | LF | 300 | $345.00 | $253.00 | $320.00 | $284.00 | $265.50 | $215.00 | $301.00 |
| 18 | Class C concrete (abutment) (420-7012) | CY | 21 | $1,250.00 | $1,460.00 | $1,200.00 | $1,074.35 | $1,830.00 | $2,000.00 | $2,600.00 |
| 19 | Class C concrete (cap) (420-7022) | CY | 13.80 | $1,400.00 | $2,130.00 | $1,900.00 | $1,200.00 | $2,535.00 | $2,200.00 | $2,600.00 |
| 20 | Class C concrete (column) (420-7038) | CY | 7 | $1,900.00 | $1,780.00 | $2,400.00 | $1,100.00 | $2,475.00 | $2,400.00 | $2,800.00 |
| 21 | Reinforced concrete slab (slab beam) (422-7007) | SF | 2,600 | $30.00 | $21.40 | $24.00 | $17.00 | $38.65 | $28.00 | $28.00 |
| 22 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 492.42 | $285.00 | $281.00 | $270.00 | $256.00 | $283.00 | $295.00 | $425.00 |
| 23 | Riprap (stone protection)(18 in) (432-7043) | CY | 865 | $220.00 | $154.00 | $180.00 | $200.00 | $163.00 | $200.00 | $281.00 |
| 24 | Rail (type SSTR) (450-7024) | LF | 339 | $125.00 | $276.00 | $170.00 | $120.00 | $220.40 | $150.00 | $250.00 |
| 25 | Armor joint (sealed) (454-7003) | LF | 46 | $155.00 | $214.00 | $185.00 | $100.00 | $178.00 | $200.00 | $241.00 |
| 26 | Concrete box culvert (9 FT X 6 FT) (462-7028) | LF | 54 | $1,560.00 | $1,750.00 | $1,756.00 | $1,416.00 | $4,150.00 | $1,900.00 | |
| 27 | Wingwall (PW - 2) (HW=8 FT) (466-7192) | EACH | 2 | $35,100 | $40,000 | $45,000 | $31,325 | $50,000 | $32,000 | |
| 28 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $40,000 | $12,000 | $15,000 | $25,000 | $9,900.00 | $20,000 | $23,500 |
| 29 | Removing structure (small) (496-7036) | EACH | 3 | $1,770.00 | $250.00 | $8,000.00 | $950.00 | $2,500.00 | $3,500.00 | |
| 30 | Mobilization (500-7001) | LS | 1 | $120,000 | $87,500 | $95,000 | $120,000 | $224,700 | $125,000 | $100,000 |
| 31 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $2,700.00 | $3,140.00 | $1,800.00 | $1,200.00 | $1,963.00 | $10,000 | $1,500.00 |
| 32 | Rock filter dams (install) (type 1) (506-7006) | CY | 12 | $320.00 | $12.70 | $140.00 | $50.00 | $163.00 | $1.00 | $250.00 |
| 33 | Rock filter dams (remove) (506-7012) | CY | 12 | $70.00 | $12.70 | $1.00 | $1.00 | $81.00 | $1.00 | $125.00 |
| 34 | Sandbags for erosion control (506-7035) | EACH | 60 | $25.00 | $63.60 | $10.00 | $2.00 | $27.00 | $1.00 | $9.00 |
| 35 | Temporary sediment control fence (install) (506-7039) | LF | 1,611 | $5.00 | $5.60 | $4.00 | $3.00 | $5.16 | $1.00 | $5.00 |
| 36 | Temporary sediment control fence (remove) (506-7041) | LF | 1,611 | $1.50 | $2.10 | $2.00 | $1.00 | $1.60 | $1.00 | $1.00 |
| 37 | Metal W-beam guard fence (timber post) (540-7001) | LF | 162.50 | $40.00 | $33.10 | $35.00 | $38.00 | $32.60 | $26.00 | $28.00 |
| 38 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 8 | $1,700.00 | $1,960.00 | $1,800.00 | $1,634.00 | $1,793.00 | $1,600.00 | $1,376.00 |
| 39 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,500.00 | $3,730.00 | $4,200.00 | $3,439.00 | $3,532.00 | $3,000.00 | $3,380.00 |
| 40 | Wire fence (type A) (552-7001) | LF | 748 | $25.00 | $19.10 | $25.00 | $15.00 | $8.42 | $25.00 | $37.00 |
| 41 | Wire fence (type C) (552-7003) | LF | 1,075 | $30.00 | $15.90 | $25.00 | $20.00 | $8.42 | $25.00 | $39.00 |
| 42 | Gate (type 2) (552-7007) | EACH | 2 | $1,750.00 | $636.00 | $770.00 | $1,000.00 | $520.00 | $3,000.00 | $950.00 |
| 43 | Wire fence (water gap) (552-7010) | LF | 50 | $53.00 | $65.00 | $42.00 | $9.00 | $100.00 | $235.00 | |
| 44 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 12 | $45.00 | $30.00 | $25.00 | $6.32 | $38.00 | $30.00 | $25.00 |
| 45 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 14 | $45.00 | $37.40 | $50.00 | $13.90 | $42.00 | $30.00 | $26.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.