TxDOT contract A00134101 bid tabulation
Reconstruct Existing Roadway, FM 1829 (US 84 to FM 107). Let by Texas DOT on February 6, 2025, Coryell, Waco District. 6 bids received; low bid $4,787,272 by Big Creek Construction, LTD., -14% against the engineer's estimate of $5,558,480.
- Owner
- Texas DOT
- Letting
- 06 FEB 2025
- Pay items
- 80
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Big Creek Construction, LTD. | $4,787,272 | Low | -14% |
| 2 | Texas Materials Group, Inc. | $5,167,110 | +8.0% | -7.0% |
| 3 | Knife River Corporation - South | $5,342,313 | +12% | -4.0% |
| 4 | TTG Utilities, LP | $5,498,498 | +15% | -1.0% |
| 5 | James Construction Group, LLC | $6,031,382 | +26% | +9.0% |
| 6 | C. E. Barker, LTD. | $7,263,535 | +52% | +31% |
Engineer's estimate: $5,558,480.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Big Creek Construction, LTD. | 2. Texas Materials Group, Inc. | 3. Knife River Corporation - South | 4. TTG Utilities, LP | 5. James Construction Group, LLC | 6. C. E. Barker, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 122 | $2,500.00 | $1,000.00 | $732.00 | $800.00 | $565.00 | $4,925.00 | $6,000.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 508 | $45.00 | $20.00 | $8.00 | $25.00 | $18.00 | $16.32 | $23.15 |
| 3 | Remove (6"-10") TRT/untrt base & asphalt pavement (105-7006) | SY | 59 | $25.00 | $20.00 | $25.00 | $7.00 | $30.00 | $40.00 | $34.05 |
| 4 | Obliterating abandoned road (106-7002) | SY | 902 | $25.00 | $15.00 | $4.00 | $9.00 | $20.00 | $11.15 | $9.26 |
| 5 | Excavation (roadway) (110-7001) | CY | 672 | $25.00 | $25.00 | $14.50 | $29.00 | $15.00 | $20.00 | $35.00 |
| 6 | Embankment (final)(DC)(type C) (132-7006) | CY | 9,599 | $18.00 | $25.00 | $43.50 | $29.00 | $16.00 | $27.67 | $35.02 |
| 7 | Backfill (type B) (134-7002) | STA | 100 | $200.00 | $150.00 | $130.00 | $415.00 | $675.00 | $747.27 | $243.16 |
| 8 | Blading (150-7001) | STA | 4 | $110.16 | $800.00 | $850.00 | $400.00 | $360.00 | $2,962.38 | $231.52 |
| 9 | Furn & place topsoil (4") (160-7002) | SY | 47,461 | $1.50 | $0.50 | $1.10 | $1.25 | $1.75 | $0.31 | $1.87 |
| 10 | Drill seed (permanent_rural_clay) (164-7010) | SY | 47,461 | $0.22 | $0.23 | $0.19 | $0.21 | $0.38 | $0.16 | $0.54 |
| 11 | Drill seed (temporary_warm_cool) (164-7015) | SY | 47,461 | $0.17 | $0.21 | $0.17 | $0.19 | $0.31 | $0.16 | $0.42 |
| 12 | Vegetative watering (168-7001) | TGL | 772 | $37.00 | $20.00 | $42.00 | $1.00 | $35.00 | $36.95 | $46.30 |
| 13 | Soil ret BLKT(SL_mod_clay_short_roll) (169-7009) | SY | 4,894 | $5.00 | $2.30 | $2.00 | $2.25 | $1.68 | $2.83 | $2.72 |
| 14 | FL BS (compacted in place)(tyd GR1-2)(final pos) (247-7188) | CY | 10,040 | $70.00 | $60.00 | $62.00 | $65.00 | $62.00 | $52.45 | $102.50 |
| 15 | FL BS (roadway del)(type D GR 3)(final pos) (247-7272) | CY | 4,822 | $55.00 | $47.00 | $44.00 | $45.00 | $60.00 | $53.58 | $102.50 |
| 16 | Rework BS metal (type C)(8")(ord comp) (251-7043) | STA | 119 | $800.00 | $430.00 | $700.00 | $750.00 | $1,185.00 | $1,527.93 | $385.87 |
| 17 | Cement (275-7001) | TON | 526 | $255.00 | $240.00 | $250.00 | $232.00 | $280.00 | $244.82 | $381.33 |
| 18 | Cement TRT (existing material)(8") (275-7003) | SY | 43,868 | $2.25 | $3.00 | $4.15 | $3.00 | $3.00 | $5.85 | $3.86 |
| 19 | Emuls asphalt (BS or subgr TRT)(CSS-1H) (314-7004) | GAL | 70,189 | $3.27 | $3.40 | $3.60 | $2.00 | $3.35 | $5.00 | $6.54 |
| 20 | Fog seal (CSS-1H) (315-7004) | GAL | 4,387 | $4.08 | $5.25 | $5.00 | $4.00 | $4.80 | $2.60 | $8.72 |
| 21 | Asphalt (AC-20-5TR) (316-7007) | GAL | 15,354 | $5.00 | $3.60 | $4.50 | $4.30 | $6.55 | $5.85 | $8.72 |
| 22 | Asphalt (CRS-2P) (316-7012) | GAL | 26,321 | $5.50 | $3.50 | $3.90 | $3.50 | $4.40 | $3.90 | $8.72 |
| 23 | Aggregate (type-PD or PL, GR-4) (316-7258) | CY | 325 | $125.00 | $140.00 | $240.00 | $195.00 | $270.00 | $240.00 | $272.38 |
| 24 | Aggregate (type-D or L,GR-3) (316-7278) | CY | 462 | $230.00 | $100.00 | $170.00 | $185.00 | $201.00 | $180.00 | $250.59 |
| 25 | Cut & restoring pavement (400-7006) | SY | 288 | $125.00 | $25.00 | $150.00 | $87.00 | $98.00 | $59.60 | $141.79 |
| 26 | Cem stabil BKFL (400-7010) | CY | 448.80 | $275.00 | $200.00 | $239.00 | $275.00 | $250.00 | $155.17 | $198.83 |
| 27 | Temporary special shoring (403-7001) | SF | 3,961 | $40.00 | $12.00 | $0.75 | $2.00 | $22.50 | $4.12 | $9.26 |
| 28 | Drilled shaft (18 in) (416-7002) | LF | 80 | $200.00 | $180.00 | $133.05 | $200.00 | $146.00 | $105.34 | $173.65 |
| 29 | Drilled shaft (36 in) (416-7006) | LF | 650 | $280.00 | $300.00 | $236.99 | $375.00 | $333.00 | $203.05 | $355.40 |
| 30 | Class C concrete (abutment)(HPC) (420-7013) | CY | 111.20 | $1,200.00 | $1,280.00 | $1,200.00 | $1,250.00 | $1,240.00 | $954.01 | $1,681.11 |
| 31 | Reinforced concrete slab (422-7001) | SF | 7,600 | $25.00 | $28.00 | $30.00 | $31.00 | $43.00 | $45.00 | $34.17 |
| 32 | Approach slab (422-7013) | CY | 153.70 | $700.00 | $920.00 | $680.00 | $650.00 | $660.00 | $550.82 | $637.28 |
| 33 | Prestressed concrete girder (TX40) (425-7003) | LF | 944.75 | $187.50 | $220.00 | $259.00 | $310.00 | $330.00 | $226.93 | $281.40 |
| 34 | Riprap (mow strip)(4 in) (432-7013) | CY | 99 | $650.00 | $650.00 | $550.00 | $750.00 | $705.00 | $450.00 | $343.34 |
| 35 | Riprap (stone protection)(18 in) (432-7043) | CY | 3,117 | $200.00 | $150.00 | $110.00 | $145.00 | $140.00 | $126.27 | $100.23 |
| 36 | Rail (type T223) (450-7008) | LF | 478 | $154.67 | $190.00 | $155.00 | $155.00 | $185.00 | $89.08 | $260.19 |
| 37 | Armor joint (454-7002) | LF | 156 | $150.00 | $95.00 | $110.00 | $125.00 | $150.00 | $82.33 | $83.26 |
| 38 | RC pipe (CL III)(24 in) (464-7005) | LF | 568 | $125.00 | $85.00 | $105.00 | $102.00 | $118.00 | $125.79 | $78.53 |
| 39 | RC pipe (CL IV)(30 in) (464-7023) | LF | 198 | $178.60 | $150.00 | $155.00 | $342.00 | $210.00 | $286.13 | $137.55 |
| 40 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 32 | $1,800.00 | $1,500.00 | $1,825.00 | $1,920.00 | $1,600.00 | $1,653.01 | $1,798.04 |
| 41 | Set (type II) (30 in) (RCP) (3: 1) (C) (467-7345) | EACH | 3 | $3,000.00 | $1,600.00 | $2,425.00 | $1,935.00 | $2,050.00 | $2,201.58 | $1,906.63 |
| 42 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 5 | $3,200.00 | $1,700.00 | $2,425.00 | $2,265.00 | $2,450.00 | $2,384.41 | $2,168.11 |
| 43 | Removing structure (pipe) (496-7007) | LF | 671 | $18.00 | $14.00 | $20.00 | $12.00 | $34.00 | $10.12 | $20.70 |
| 44 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 2 | $36,000 | $30,000 | $35,000 | $47,000 | $23,000 | $90,000 | $36,716 |
| 45 | Mobilization (500-7001) | LS | 1 | $342,050 | $372,000 | $510,000 | $485,000 | $375,000 | $596,577 | $615,000 |
| 46 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $10,000 | $4,000.00 | $9,600.00 | $19,800 | $6,890.00 | $8,500.00 | $6,408.46 |
| 47 | Portable changeable message sign (503-7002) | EACH | 4 | $12,040 | $12,000 | $2,700.00 | $15,000 | $19,500 | $15,458 | $6,101.22 |
| 48 | Rock filter dams (install) (type 2) (506-7002) | LF | 60 | $35.00 | $40.00 | $35.00 | $55.00 | $67.00 | $55.12 | $51.75 |
| 49 | Rock filter dams (remove) (506-7011) | LF | 60 | $12.84 | $10.00 | $10.00 | $25.00 | $45.00 | $24.23 | $40.86 |
| 50 | Temporary sediment control fence (install) (506-7039) | LF | 3,030 | $4.63 | $4.00 | $2.95 | $6.20 | $4.75 | $8.37 | $4.90 |
| 51 | Temporary sediment control fence (remove) (506-7041) | LF | 3,030 | $1.50 | $1.00 | $1.00 | $1.10 | $1.40 | $1.24 | $1.09 |
| 52 | Driveways (ACP) (530-7010) | SY | 1,067 | $59.15 | $40.00 | $95.78 | $55.00 | $70.00 | $84.54 | $54.48 |
| 53 | Metal W-beam guard fence (steel post) (540-7002) | LF | 1,406 | $32.00 | $40.00 | $28.50 | $32.00 | $33.00 | $27.00 | $33.50 |
| 54 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 8 | $2,400.00 | $2,500.00 | $2,700.00 | $3,000.00 | $2,850.00 | $2,200.00 | $2,287.96 |
| 55 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,000.00 | $3,300.00 | $2,877.50 | $3,000.00 | $3,575.00 | $2,800.00 | $3,186.80 |
| 56 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 1 | $500.00 | $700.00 | $605.22 | $670.00 | $680.00 | $605.22 | $653.70 |
| 57 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 6 | $320.00 | $250.00 | $374.22 | $400.00 | $420.00 | $374.22 | $245.14 |
| 58 | Mailbox install-D (TWG-post) type 2 (560-7003) | EACH | 1 | $300.00 | $300.00 | $377.22 | $420.00 | $425.00 | $377.22 | $288.72 |
| 59 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 4 | $810.95 | $800.00 | $721.42 | $800.00 | $800.00 | $721.42 | $800.79 |
| 60 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 4 | $1,000.00 | $1,500.00 | $1,041.34 | $1,150.00 | $1,165.00 | $1,041.34 | $1,500.00 |
| 61 | Install small roadside sign support and assembly TYS80(1)SA(T-2EXT) (644-7029) | EACH | 4 | $1,100.00 | $1,500.00 | $1,292.38 | $1,425.00 | $1,445.00 | $1,292.38 | $1,500.00 |
| 62 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,200.00 | $1,200.00 | $1,033.02 | $1,145.00 | $1,160.00 | $1,033.02 | $1,250.00 |
| 63 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 17 | $668.03 | $600.00 | $482.26 | $535.00 | $540.00 | $482.26 | $600.00 |
| 64 | Install small roadside sign support and assembly tytwt(1)WS(T) (644-7058) | EACH | 1 | $650.00 | $700.00 | $563.96 | $625.00 | $630.00 | $563.96 | $700.00 |
| 65 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $200.00 | $150.00 | $742.00 | $165.00 | $825.55 | $742.00 | $200.00 |
| 66 | Relocate SM RD SN sup & AM type temporary (644-7077) | EACH | 31 | $297.40 | $750.00 | $450.00 | $222.00 | $104.00 | $92.74 | $729.97 |
| 67 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 4 | $20.00 | $30.00 | $20.00 | $45.00 | $41.00 | $36.94 | $25.06 |
| 68 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 25 | $25.00 | $60.00 | $45.00 | $60.00 | $67.00 | $59.75 | $48.48 |
| 69 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 8 | $75.00 | $80.00 | $50.00 | $100.00 | $67.00 | $59.81 | $70.82 |
| 70 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 23,930 | $0.54 | $0.50 | $0.30 | $0.27 | $0.27 | $0.37 | $0.40 |
| 71 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 1,500 | $0.17 | $0.50 | $1.00 | $0.39 | $0.39 | $0.38 | $0.41 |
| 72 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 18,260 | $0.93 | $0.50 | $0.30 | $0.38 | $0.38 | $0.37 | $0.40 |
| 73 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 1,197 | $1.14 | $1.50 | $1.20 | $1.00 | $2.17 | $3.20 | $2.72 |
| 74 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,336 | $0.25 | $1.50 | $1.20 | $1.50 | $2.17 | $1.50 | $2.72 |
| 75 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 69 | $12.00 | $15.00 | $15.00 | $22.00 | $22.35 | $13.50 | $14.71 |
| 76 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 26,915 | $0.82 | $0.90 | $0.87 | $1.20 | $1.23 | $0.88 | $0.96 |
| 77 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 20,972 | $0.75 | $0.90 | $0.87 | $1.20 | $1.23 | $0.88 | $0.96 |
| 78 | Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274) | LF | 1,880 | $0.88 | $0.90 | $1.40 | $1.20 | $1.23 | $0.88 | $0.96 |
| 79 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 608 | $4.95 | $7.00 | $6.25 | $6.75 | $7.24 | $4.95 | $5.39 |
| 80 | Preformed in-lane (trans) rumble strip (6024-7001) | LF | 160 | $20.00 | $25.00 | $15.00 | $21.00 | $21.23 | $20.50 | $20.65 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.