TxDOT contract A00134101 bid tabulation

Reconstruct Existing Roadway, FM 1829 (US 84 to FM 107). Let by Texas DOT on February 6, 2025, Coryell, Waco District. 6 bids received; low bid $4,787,272 by Big Creek Construction, LTD., -14% against the engineer's estimate of $5,558,480.

Owner
Texas DOT
Letting
06 FEB 2025
Pay items
80
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Big Creek Construction, LTD.$4,787,272Low-14%
2Texas Materials Group, Inc.$5,167,110+8.0%-7.0%
3Knife River Corporation - South$5,342,313+12%-4.0%
4TTG Utilities, LP$5,498,498+15%-1.0%
5James Construction Group, LLC$6,031,382+26%+9.0%
6C. E. Barker, LTD.$7,263,535+52%+31%
TxDOT contract A00134101: bids by rank

Engineer's estimate: $5,558,480.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Big Creek Construction, LTD.2. Texas Materials Group, Inc.3. Knife River Corporation - South4. TTG Utilities, LP5. James Construction Group, LLC6. C. E. Barker, LTD.
1Preparing row (100-7002)STA122$2,500.00$1,000.00$732.00$800.00$565.00$4,925.00$6,000.00
2Removing concrete (riprap) (104-7006)SY508$45.00$20.00$8.00$25.00$18.00$16.32$23.15
3Remove (6"-10") TRT/untrt base & asphalt pavement (105-7006)SY59$25.00$20.00$25.00$7.00$30.00$40.00$34.05
4Obliterating abandoned road (106-7002)SY902$25.00$15.00$4.00$9.00$20.00$11.15$9.26
5Excavation (roadway) (110-7001)CY672$25.00$25.00$14.50$29.00$15.00$20.00$35.00
6Embankment (final)(DC)(type C) (132-7006)CY9,599$18.00$25.00$43.50$29.00$16.00$27.67$35.02
7Backfill (type B) (134-7002)STA100$200.00$150.00$130.00$415.00$675.00$747.27$243.16
8Blading (150-7001)STA4$110.16$800.00$850.00$400.00$360.00$2,962.38$231.52
9Furn & place topsoil (4") (160-7002)SY47,461$1.50$0.50$1.10$1.25$1.75$0.31$1.87
10Drill seed (permanent_rural_clay) (164-7010)SY47,461$0.22$0.23$0.19$0.21$0.38$0.16$0.54
11Drill seed (temporary_warm_cool) (164-7015)SY47,461$0.17$0.21$0.17$0.19$0.31$0.16$0.42
12Vegetative watering (168-7001)TGL772$37.00$20.00$42.00$1.00$35.00$36.95$46.30
13Soil ret BLKT(SL_mod_clay_short_roll) (169-7009)SY4,894$5.00$2.30$2.00$2.25$1.68$2.83$2.72
14FL BS (compacted in place)(tyd GR1-2)(final pos) (247-7188)CY10,040$70.00$60.00$62.00$65.00$62.00$52.45$102.50
15FL BS (roadway del)(type D GR 3)(final pos) (247-7272)CY4,822$55.00$47.00$44.00$45.00$60.00$53.58$102.50
16Rework BS metal (type C)(8")(ord comp) (251-7043)STA119$800.00$430.00$700.00$750.00$1,185.00$1,527.93$385.87
17Cement (275-7001)TON526$255.00$240.00$250.00$232.00$280.00$244.82$381.33
18Cement TRT (existing material)(8") (275-7003)SY43,868$2.25$3.00$4.15$3.00$3.00$5.85$3.86
19Emuls asphalt (BS or subgr TRT)(CSS-1H) (314-7004)GAL70,189$3.27$3.40$3.60$2.00$3.35$5.00$6.54
20Fog seal (CSS-1H) (315-7004)GAL4,387$4.08$5.25$5.00$4.00$4.80$2.60$8.72
21Asphalt (AC-20-5TR) (316-7007)GAL15,354$5.00$3.60$4.50$4.30$6.55$5.85$8.72
22Asphalt (CRS-2P) (316-7012)GAL26,321$5.50$3.50$3.90$3.50$4.40$3.90$8.72
23Aggregate (type-PD or PL, GR-4) (316-7258)CY325$125.00$140.00$240.00$195.00$270.00$240.00$272.38
24Aggregate (type-D or L,GR-3) (316-7278)CY462$230.00$100.00$170.00$185.00$201.00$180.00$250.59
25Cut & restoring pavement (400-7006)SY288$125.00$25.00$150.00$87.00$98.00$59.60$141.79
26Cem stabil BKFL (400-7010)CY448.80$275.00$200.00$239.00$275.00$250.00$155.17$198.83
27Temporary special shoring (403-7001)SF3,961$40.00$12.00$0.75$2.00$22.50$4.12$9.26
28Drilled shaft (18 in) (416-7002)LF80$200.00$180.00$133.05$200.00$146.00$105.34$173.65
29Drilled shaft (36 in) (416-7006)LF650$280.00$300.00$236.99$375.00$333.00$203.05$355.40
30Class C concrete (abutment)(HPC) (420-7013)CY111.20$1,200.00$1,280.00$1,200.00$1,250.00$1,240.00$954.01$1,681.11
31Reinforced concrete slab (422-7001)SF7,600$25.00$28.00$30.00$31.00$43.00$45.00$34.17
32Approach slab (422-7013)CY153.70$700.00$920.00$680.00$650.00$660.00$550.82$637.28
33Prestressed concrete girder (TX40) (425-7003)LF944.75$187.50$220.00$259.00$310.00$330.00$226.93$281.40
34Riprap (mow strip)(4 in) (432-7013)CY99$650.00$650.00$550.00$750.00$705.00$450.00$343.34
35Riprap (stone protection)(18 in) (432-7043)CY3,117$200.00$150.00$110.00$145.00$140.00$126.27$100.23
36Rail (type T223) (450-7008)LF478$154.67$190.00$155.00$155.00$185.00$89.08$260.19
37Armor joint (454-7002)LF156$150.00$95.00$110.00$125.00$150.00$82.33$83.26
38RC pipe (CL III)(24 in) (464-7005)LF568$125.00$85.00$105.00$102.00$118.00$125.79$78.53
39RC pipe (CL IV)(30 in) (464-7023)LF198$178.60$150.00$155.00$342.00$210.00$286.13$137.55
40Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH32$1,800.00$1,500.00$1,825.00$1,920.00$1,600.00$1,653.01$1,798.04
41Set (type II) (30 in) (RCP) (3: 1) (C) (467-7345)EACH3$3,000.00$1,600.00$2,425.00$1,935.00$2,050.00$2,201.58$1,906.63
42Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346)EACH5$3,200.00$1,700.00$2,425.00$2,265.00$2,450.00$2,384.41$2,168.11
43Removing structure (pipe) (496-7007)LF671$18.00$14.00$20.00$12.00$34.00$10.12$20.70
44Removing structure (bridge 0 - 99 FT length) (496-7009)EACH2$36,000$30,000$35,000$47,000$23,000$90,000$36,716
45Mobilization (500-7001)LS1$342,050$372,000$510,000$485,000$375,000$596,577$615,000
46Barricades, signs and traffic handling (502-7001)MO8$10,000$4,000.00$9,600.00$19,800$6,890.00$8,500.00$6,408.46
47Portable changeable message sign (503-7002)EACH4$12,040$12,000$2,700.00$15,000$19,500$15,458$6,101.22
48Rock filter dams (install) (type 2) (506-7002)LF60$35.00$40.00$35.00$55.00$67.00$55.12$51.75
49Rock filter dams (remove) (506-7011)LF60$12.84$10.00$10.00$25.00$45.00$24.23$40.86
50Temporary sediment control fence (install) (506-7039)LF3,030$4.63$4.00$2.95$6.20$4.75$8.37$4.90
51Temporary sediment control fence (remove) (506-7041)LF3,030$1.50$1.00$1.00$1.10$1.40$1.24$1.09
52Driveways (ACP) (530-7010)SY1,067$59.15$40.00$95.78$55.00$70.00$84.54$54.48
53Metal W-beam guard fence (steel post) (540-7002)LF1,406$32.00$40.00$28.50$32.00$33.00$27.00$33.50
54Metal beam guard fence trans (thrie-beam) (540-7005)EACH8$2,400.00$2,500.00$2,700.00$3,000.00$2,850.00$2,200.00$2,287.96
55Guardrail end treatment (install) (544-7001)EACH8$3,000.00$3,300.00$2,877.50$3,000.00$3,575.00$2,800.00$3,186.80
56Mailbox install-M (TWG-post) type 1 (560-7001)EACH1$500.00$700.00$605.22$670.00$680.00$605.22$653.70
57Mailbox install-S (TWG-post) type 2 (560-7002)EACH6$320.00$250.00$374.22$400.00$420.00$374.22$245.14
58Mailbox install-D (TWG-post) type 2 (560-7003)EACH1$300.00$300.00$377.22$420.00$425.00$377.22$288.72
59Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH4$810.95$800.00$721.42$800.00$800.00$721.42$800.79
60Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH4$1,000.00$1,500.00$1,041.34$1,150.00$1,165.00$1,041.34$1,500.00
61Install small roadside sign support and assembly TYS80(1)SA(T-2EXT) (644-7029)EACH4$1,100.00$1,500.00$1,292.38$1,425.00$1,445.00$1,292.38$1,500.00
62Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH1$1,200.00$1,200.00$1,033.02$1,145.00$1,160.00$1,033.02$1,250.00
63Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057)EACH17$668.03$600.00$482.26$535.00$540.00$482.26$600.00
64Install small roadside sign support and assembly tytwt(1)WS(T) (644-7058)EACH1$650.00$700.00$563.96$625.00$630.00$563.96$700.00
65Remove SM RD SN sup&AM (644-7073)EACH2$200.00$150.00$742.00$165.00$825.55$742.00$200.00
66Relocate SM RD SN sup & AM type temporary (644-7077)EACH31$297.40$750.00$450.00$222.00$104.00$92.74$729.97
67Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH4$20.00$30.00$20.00$45.00$41.00$36.94$25.06
68Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH25$25.00$60.00$45.00$60.00$67.00$59.75$48.48
69Install object marker assembly (OM-2Y)(WC)GND (658-7056)EACH8$75.00$80.00$50.00$100.00$67.00$59.81$70.82
70Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF23,930$0.54$0.50$0.30$0.27$0.27$0.37$0.40
71Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF1,500$0.17$0.50$1.00$0.39$0.39$0.38$0.41
72Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF18,260$0.93$0.50$0.30$0.38$0.38$0.37$0.40
73Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH1,197$1.14$1.50$1.20$1.00$2.17$3.20$2.72
74Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH1,336$0.25$1.50$1.20$1.50$2.17$1.50$2.72
75Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF69$12.00$15.00$15.00$22.00$22.35$13.50$14.71
76Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266)LF26,915$0.82$0.90$0.87$1.20$1.23$0.88$0.96
77Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270)LF20,972$0.75$0.90$0.87$1.20$1.23$0.88$0.96
78Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274)LF1,880$0.88$0.90$1.40$1.20$1.23$0.88$0.96
79Reflectorized pavement marker type II-A-A (672-7004)EACH608$4.95$7.00$6.25$6.75$7.24$4.95$5.39
80Preformed in-lane (trans) rumble strip (6024-7001)LF160$20.00$25.00$15.00$21.00$21.23$20.50$20.65
TxDOT contract A00134101: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way