TxDOT contract A00134449 bid tabulation
Bridge Replacement, COUNTY ROAD 302 (At South Concho river to .). Let by Texas DOT on July 2, 2025, Schleicher, San Angelo District. 8 bids received; low bid $1,387,935 by Talbert Companies LLC, -17% against the engineer's estimate of $1,665,837.
- Owner
- Texas DOT
- Letting
- 02 JUL 2025
- Pay items
- 45
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Talbert Companies LLC | $1,387,935 | Low | -17% |
| 2 | Acme Bridge Company, Inc. | $1,398,568 | +1.0% | -16% |
| 3 | 3LW Civil LLC | $1,400,785 | +1.0% | -16% |
| 4 | Reece Albert, Inc. | $1,438,158 | +4.0% | -14% |
| 5 | E-Z Bel Construction, LLC | $1,533,652 | +10% | -8.0% |
| 6 | Delgado'S Contractors, LLC | $1,575,001 | +13% | -5.0% |
| 7 | Allen Keller Company | $1,837,417 | +32% | +10% |
| 8 | C. E. Barker, LTD. | $1,839,401 | +33% | +10% |
Engineer's estimate: $1,665,837.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Talbert Companies LLC | 2. Acme Bridge Company, Inc. | 3. 3LW Civil LLC | 4. Reece Albert, Inc. | 5. E-Z Bel Construction, LLC | 6. Delgado'S Contractors, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 4.60 | $3,250.00 | $3,542.50 | $3,850.00 | $3,560.64 | $13,141 | $6,000.00 | $750.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 100 | $35.00 | $62.13 | $26.20 | $88.65 | $99.06 | $25.00 | $20.00 |
| 3 | Remove (3"-7") TRT/untrt base & asphalt pavement (105-7003) | SY | 787 | $30.00 | $7.63 | $12.70 | $15.33 | $11.55 | $11.00 | $20.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 25 | $150.00 | $189.37 | $32.40 | $48.11 | $26.31 | $52.00 | $40.00 |
| 5 | Embankment (final)(OC)(type A) (132-7001) | CY | 218 | $100.00 | $59.95 | $38.30 | $96.34 | $55.03 | $145.00 | $40.00 |
| 6 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 144 | $105.00 | $163.50 | $190.00 | $41.54 | $145.48 | $248.00 | $125.00 |
| 7 | Cement (275-7001) | TON | 11 | $350.00 | $319.24 | $525.00 | $520.70 | $385.65 | $494.00 | $350.00 |
| 8 | Cement TRT (existing material)(6") (275-7002) | SY | 869 | $5.00 | $3.42 | $16.60 | $6.99 | $10.67 | $9.00 | $20.00 |
| 9 | Prime coat (multi option) (310-7015) | GAL | 157 | $10.00 | $7.63 | $33.10 | $57.15 | $11.81 | $19.00 | $50.00 |
| 10 | Aggregate (type-PB, GR-3)(sac-B) (316-7208) | CY | 7 | $225.00 | $163.50 | $1,380.00 | $3,498.85 | $1,177.69 | $1,045.00 | $350.00 |
| 11 | Aggregate (type-PB, GR-4)(sac-B) (316-7211) | CY | 6 | $200.00 | $163.50 | $1,600.00 | $3,663.95 | $1,354.81 | $1,180.00 | $350.00 |
| 12 | Asphalt (multi option) (316-7263) | GAL | 197 | $8.00 | $7.63 | $29.10 | $87.31 | $15.44 | $18.00 | $50.00 |
| 13 | Cem stabil BKFL (400-7010) | CY | 32 | $300.00 | $272.50 | $342.00 | $603.72 | $588.83 | $1,510.00 | $300.00 |
| 14 | Drilled shaft (24 in) (416-7004) | LF | 315 | $300.00 | $343.35 | $377.00 | $475.93 | $415.73 | $237.00 | $500.00 |
| 15 | Class C concrete (abutment) (420-7012) | CY | 22.40 | $1,500.00 | $1,526.00 | $1,710.00 | $2,393.64 | $2,093.96 | $4,200.00 | $1,800.00 |
| 16 | Class C concrete (cap) (420-7022) | CY | 24.90 | $2,000.00 | $1,853.00 | $2,510.00 | $3,436.66 | $2,874.90 | $2,400.00 | $2,000.00 |
| 17 | Class C concrete (column) (420-7038) | CY | 11.20 | $2,000.00 | $1,962.00 | $2,780.00 | $2,187.97 | $3,334.33 | $2,981.00 | $2,200.00 |
| 18 | Reinforced concrete slab (slab beam) (422-7007) | SF | 5,140 | $25.00 | $32.70 | $25.60 | $30.70 | $34.34 | $33.00 | $35.00 |
| 19 | Approach slab (422-7013) | CY | 66.80 | $1,200.00 | $686.70 | $919.00 | $572.37 | $1,308.98 | $1,100.00 | $1,800.00 |
| 20 | Prestressed concrete slab beam (4SB15) (425-7018) | LF | 1,263.86 | $275.00 | $225.74 | $331.00 | $220.02 | $236.93 | $315.00 | $300.00 |
| 21 | Riprap (mow strip)(4 in) (432-7013) | CY | 20 | $700.00 | $695.42 | $1,160.00 | $906.90 | $1,197.96 | $1,005.00 | $800.00 |
| 22 | Riprap (stone protection)(18 in) (432-7043) | CY | 312 | $275.00 | $381.50 | $249.00 | $244.05 | $171.15 | $225.00 | $300.00 |
| 23 | Rail (type T223) (450-7008) | LF | 344 | $200.00 | $174.40 | $137.00 | $222.72 | $179.61 | $224.00 | $210.00 |
| 24 | Type A joint (454-7001) | LF | 96 | $150.00 | $109.00 | $40.60 | $59.50 | $90.44 | $19.00 | $100.00 |
| 25 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $300,000 | $43,600 | $30,500 | $34,290 | $54,879 | $27,000 | $90,000 |
| 26 | Mobilization (500-7001) | LS | 1 | $151,440 | $232,500 | $100,000 | $133,207 | $140,773 | $150,000 | $145,000 |
| 27 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $12,000 | $2,725.00 | $3,660.00 | $3,650.99 | $1,311.58 | $2,500.00 | $2,500.00 |
| 28 | Portable changeable message sign (503-7001) | DAY | 14 | $250.00 | $130.80 | $178.00 | $96.89 | $35.94 | $70.00 | $200.00 |
| 29 | Rock filter dams (install) (type 3) (506-7003) | LF | 95 | $90.00 | $163.50 | $141.00 | $107.30 | $86.81 | $110.00 | $85.00 |
| 30 | Rock filter dams (remove) (506-7011) | LF | 95 | $10.00 | $32.70 | $45.20 | $30.35 | $15.49 | $15.00 | $10.00 |
| 31 | Construction exits (install) (type 1) (506-7020) | SY | 215 | $100.00 | $32.70 | $56.50 | $40.89 | $15.21 | $35.00 | $30.00 |
| 32 | Construction exits (remove) (506-7024) | SY | 215 | $15.00 | $10.90 | $17.00 | $12.22 | $2.67 | $8.00 | $4.00 |
| 33 | Temporary sediment control fence (install) (506-7039) | LF | 690 | $6.00 | $5.78 | $7.40 | $4.36 | $3.23 | $4.00 | $7.00 |
| 34 | Temporary sediment control fence (remove) (506-7041) | LF | 690 | $2.00 | $2.73 | $2.85 | $1.13 | $1.34 | $1.80 | $2.00 |
| 35 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 140 | $10.00 | $18.20 | $13.60 | $9.33 | $7.43 | $4.00 | $15.00 |
| 36 | Biodegradable erosion control logs (remove) (506-7046) | LF | 140 | $3.00 | $2.73 | $3.40 | $1.02 | $2.64 | $1.00 | $1.00 |
| 37 | Metal W-beam guard fence (steel post) (540-7002) | LF | 100 | $35.00 | $39.46 | $47.20 | $44.09 | $43.37 | $36.00 | $50.00 |
| 38 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $3,500.00 | $3,234.03 | $4,310.00 | $1,866.85 | $3,554.36 | $2,967.00 | $3,300.00 |
| 39 | Remove metal beam guard fence (542-7001) | LF | 220 | $5.00 | $7.09 | $8.50 | $6.88 | $7.79 | $7.00 | $3.70 |
| 40 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $4,000.00 | $4,366.54 | $5,220.00 | $2,689.81 | $4,799.04 | $4,006.00 | $4,200.00 |
| 41 | Wire fence (type A) (552-7001) | LF | 455 | $30.00 | $27.25 | $22.60 | $38.85 | $17.97 | $37.00 | $30.00 |
| 42 | Wire fence (remove) (552-7011) | LF | 455 | $5.00 | $10.90 | $5.70 | $8.72 | $5.99 | $5.00 | $4.00 |
| 43 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $270.00 | $109.00 | $325.00 | $252.27 | $179.70 | $250.00 | $397.00 |
| 44 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 6 | $30.00 | $43.60 | $33.90 | $31.18 | $59.90 | $2.00 | $35.00 |
| 45 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 4 | $30.00 | $27.25 | $33.90 | $53.45 | $59.90 | $10.00 | $35.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 2, 2025. Compiled by Mirage Metrics.