TxDOT contract A00180383 bid tabulation
Drainage Improvements, SH 30 (CR 171 to 0.1 Mi E of FM 244). Let by Texas DOT on March 4, 2025, Grimes, Bryan District. 9 bids received; low bid $954,998 by Brazos Paving, Inc., -31% against the engineer's estimate of $1,381,357.
- Owner
- Texas DOT
- Letting
- 04 MAR 2025
- Pay items
- 55
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Brazos Paving, Inc. | $954,998 | Low | -31% |
| 2 | Lakey, Inc. | $1,166,334 | +22% | -16% |
| 3 | Garret Shields Infrastructure | $1,172,553 | +23% | -15% |
| 4 | Forde Construction Company, Inc. | $1,240,579 | +30% | -10% |
| 5 | MB Western Industrial Contracting Co. | $1,325,177 | +39% | -4.0% |
| 6 | C. E. Barker, LTD. | $1,374,186 | +44% | -1.0% |
| 7 | R Construction Civil, LLC | $1,435,589 | +50% | +4.0% |
| 8 | Fuqua Construction Co., Inc. | $1,499,778 | +57% | +9.0% |
| 9 | Yoko Excavating, LLC | $1,559,922 | +63% | +13% |
Engineer's estimate: $1,381,357.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Brazos Paving, Inc. | 2. Lakey, Inc. | 3. Garret Shields Infrastructure | 4. Forde Construction Company, Inc. | 5. MB Western Industrial Contracting Co. | 6. C. E. Barker, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7001) | ACRE | 3 | $20,228 | $6,660.00 | $4,012.84 | $1,000.00 | $25,000 | $2,083.00 | $10,000 |
| 2 | Preparing row (100-7002) | STA | 21.50 | $3,300.00 | $640.00 | $2,100.00 | $800.00 | $2,500.00 | $2,131.00 | $5,700.00 |
| 3 | Removing concrete (mowstrip) (104-7005) | LF | 130 | $18.00 | $25.00 | $15.00 | $30.00 | $50.00 | $9.25 | $9.00 |
| 4 | Removing concrete (riprap) (104-7006) | SY | 36 | $35.00 | $40.00 | $27.00 | $50.00 | $56.00 | $15.19 | $15.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 3,073 | $20.00 | $25.50 | $23.59 | $35.00 | $26.00 | $26.35 | $25.00 |
| 6 | Excavation (special) (110-7003) | CY | 6,130 | $50.00 | $16.00 | $34.00 | $30.00 | $29.00 | $30.50 | $29.00 |
| 7 | Embankment (final)(DC)(type C) (132-7006) | CY | 5,729 | $20.00 | $9.50 | $27.00 | $35.00 | $18.00 | $32.09 | $30.00 |
| 8 | Furn & place topsoil (4") (160-7002) | SY | 22,613 | $4.00 | $1.40 | $3.30 | $4.00 | $4.00 | $6.00 | $4.84 |
| 9 | Block sodding (162-7002) | SY | 843 | $9.00 | $7.60 | $7.00 | $10.00 | $9.30 | $7.20 | $7.00 |
| 10 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 22,613 | $1.00 | $0.70 | $0.75 | $0.80 | $0.55 | $0.66 | $0.65 |
| 11 | Hydro mulch seed (temporary_warm) (164-7021) | SY | 11,728 | $1.00 | $0.70 | $0.75 | $0.80 | $0.50 | $0.23 | $0.60 |
| 12 | Hydro mulch seed (temporary_cool) (164-7022) | SY | 11,728 | $1.00 | $0.70 | $0.75 | $0.80 | $0.50 | $0.28 | $0.60 |
| 13 | Vegetative watering (168-7001) | TGL | 470 | $34.00 | $85.25 | $30.00 | $50.00 | $60.00 | $129.00 | $115.00 |
| 14 | Cem stabil BKFL (400-7010) | CY | 48 | $201.00 | $109.00 | $300.00 | $300.00 | $236.00 | $246.00 | $212.00 |
| 15 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 10 | $250.00 | $286.00 | $318.50 | $400.00 | $227.00 | $476.00 | $350.00 |
| 16 | Riprap (concrete)(CL B) (432-7005) | CY | 23 | $948.00 | $450.00 | $500.00 | $600.00 | $1,060.00 | $535.50 | $950.00 |
| 17 | Riprap (mow strip)(4 in) (432-7013) | CY | 83 | $700.00 | $478.00 | $700.00 | $600.00 | $1,120.00 | $666.00 | $620.00 |
| 18 | Riprap (stone protection)(12 in) (432-7041) | CY | 461 | $225.00 | $204.00 | $165.00 | $200.00 | $218.00 | $228.00 | $150.00 |
| 19 | RC pipe (CL III)(15 in) (464-7002) | LF | 8 | $78.00 | $184.00 | $77.50 | $80.00 | $83.00 | $86.00 | $135.00 |
| 20 | RC pipe (CL III)(18 in) (464-7003) | LF | 22 | $116.00 | $185.00 | $90.70 | $100.00 | $90.00 | $94.00 | $155.00 |
| 21 | RC pipe (CL III)(24 in) (464-7005) | LF | 75 | $193.00 | $191.00 | $110.00 | $120.00 | $206.00 | $215.25 | $190.00 |
| 22 | Inlet (complete)(type A)(hou) (465-7313) | EACH | 1 | $5,000.00 | $6,720.00 | $8,138.50 | $8,000.00 | $5,300.00 | $5,535.00 | $6,800.00 |
| 23 | Set (type II) (15 in) (RCP) (4: 1) (C) (467-7298) | EACH | 1 | $1,800.00 | $2,013.00 | $1,155.00 | $800.00 | $1,000.00 | $1,045.00 | $1,750.00 |
| 24 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 1 | $1,596.00 | $2,055.00 | $1,155.00 | $1,000.00 | $1,120.00 | $1,169.00 | $1,800.00 |
| 25 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $2,402.00 | $2,560.00 | $1,775.00 | $1,500.00 | $2,400.00 | $2,460.00 | $2,400.00 |
| 26 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 1 | $2,613.00 | $2,956.00 | $1,775.00 | $1,500.00 | $2,950.00 | $3,075.00 | $3,200.00 |
| 27 | Mobilization (500-7001) | LS | 1 | $127,200 | $85,300 | $79,884 | $100,000 | $123,000 | $125,000 | $123,000 |
| 28 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $2,000.00 | $5,084.00 | $7,500.00 | $5,000.00 | $3,000.00 | $1,500.00 | $8,000.00 |
| 29 | Portable changeable message sign (503-7002) | EACH | 4 | $8,500.00 | $16,700 | $6,100.00 | $1.00 | $3,000.00 | $5,000.00 | $5,500.00 |
| 30 | TMA (stationary) (505-7001) | DAY | 113 | $345.00 | $267.00 | $205.00 | $300.00 | $170.00 | $300.00 | $220.00 |
| 31 | Rock filter dams (install) (type 2) (506-7002) | LF | 260 | $44.00 | $48.15 | $50.40 | $10.00 | $44.00 | $45.51 | $43.00 |
| 32 | Rock filter dams (install) (type 3) (506-7003) | LF | 81 | $79.00 | $97.50 | $81.00 | $10.00 | $95.00 | $92.25 | $86.00 |
| 33 | Rock filter dams (remove) (506-7011) | LF | 341 | $12.00 | $13.00 | $10.45 | $5.00 | $15.00 | $12.30 | $12.00 |
| 34 | Construction exits (install) (type 1) (506-7020) | SY | 224 | $32.00 | $44.20 | $34.00 | $10.00 | $46.00 | $41.83 | $40.00 |
| 35 | Construction exits (remove) (506-7024) | SY | 224 | $11.00 | $15.60 | $12.66 | $5.00 | $15.00 | $14.76 | $15.00 |
| 36 | Temporary sediment control fence (install) (506-7039) | LF | 1,657 | $4.00 | $4.90 | $4.50 | $6.00 | $4.25 | $4.61 | $4.50 |
| 37 | Temporary sediment control fence (remove) (506-7041) | LF | 1,657 | $1.00 | $1.30 | $1.38 | $1.00 | $1.25 | $1.23 | $1.25 |
| 38 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 24 | $7.50 | $5.85 | $7.55 | $8.00 | $12.00 | $5.54 | $5.25 |
| 39 | Biodegradable erosion control logs (remove) (506-7046) | LF | 24 | $2.00 | $1.30 | $3.00 | $2.00 | $6.00 | $1.23 | $1.25 |
| 40 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,013 | $27.00 | $32.20 | $29.00 | $40.00 | $26.00 | $30.44 | $35.00 |
| 41 | Remove metal beam guard fence (542-7001) | LF | 25 | $4.00 | $13.00 | $3.00 | $5.00 | $2.65 | $12.30 | $10.00 |
| 42 | Guardrail end treatment (install) (544-7001) | EACH | 5 | $3,338.00 | $4,192.25 | $3,200.00 | $3,500.00 | $3,075.00 | $3,967.00 | $3,500.00 |
| 43 | Guardrail end treatment (remove) (544-7003) | EACH | 1 | $300.00 | $455.00 | $286.68 | $500.00 | $265.00 | $430.50 | $400.00 |
| 44 | Wire fence (type C) (552-7003) | LF | 1,704 | $23.00 | $15.60 | $27.00 | $10.00 | $21.00 | $30.00 | $25.00 |
| 45 | Wire fence (remove) (552-7011) | LF | 1,168 | $9.00 | $5.20 | $5.00 | $1.00 | $3.50 | $7.00 | $4.00 |
| 46 | Remove RD IL asm (trans-base) (610-7009) | EACH | 1 | $750.00 | $1,720.00 | $590.00 | $800.00 | $1,400.00 | $2,113.00 | $1,550.00 |
| 47 | In RD IL (type SA) 40T-12 (250W EQ) LED (610-7128) | EACH | 1 | $7,000.00 | $11,451 | $4,911.25 | $6,000.00 | $9,000.00 | $11,500 | $10,000 |
| 48 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 153 | $18.00 | $17.70 | $16.00 | $20.00 | $14.00 | $13.50 | $15.00 |
| 49 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 50 | $30.00 | $24.81 | $27.00 | $25.00 | $20.00 | $18.28 | $17.00 |
| 50 | Electrical conductor (no.8) bare (620-7007) | LF | 355 | $2.00 | $2.31 | $2.00 | $3.00 | $2.00 | $2.39 | $2.25 |
| 51 | Electrical conductor (no.8) insulated (620-7008) | LF | 710 | $2.00 | $2.42 | $1.87 | $4.00 | $2.00 | $2.46 | $2.30 |
| 52 | Ground box type B (122322)W/apron (624-7004) | EACH | 3 | $2,700.00 | $1,346.00 | $2,500.00 | $2,000.00 | $1,060.00 | $1,489.00 | $1,400.00 |
| 53 | Remove ground box (624-7013) | EACH | 1 | $394.00 | $1,287.50 | $392.93 | $200.00 | $928.00 | $394.00 | $400.00 |
| 54 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (658-7015) | EACH | 4 | $34.00 | $24.70 | $36.73 | $30.00 | $25.00 | $23.50 | $30.00 |
| 55 | Install object marker assembly (OM-3R)(TWT)GND (658-7070) | EACH | 14 | $249.00 | $232.75 | $375.00 | $300.00 | $150.00 | $220.00 | $260.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 4, 2025. Compiled by Mirage Metrics.