TxDOT contract A00183588 bid tabulation
Bridge Replacement, FM 94 (@ Draw to .). Let by Texas DOT on July 1, 2025, Motley, Childress District. 7 bids received; low bid $1,837,101 by STX Civil, -13% against the engineer's estimate of $2,112,424.
- Owner
- Texas DOT
- Letting
- 01 JUL 2025
- Pay items
- 51
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | STX Civil | $1,837,101 | Low | -13% |
| 2 | Talbert Companies LLC | $1,941,370 | +6.0% | -8.0% |
| 3 | Earth Builders, L.P. | $2,045,616 | +11% | -3.0% |
| 4 | Gilvin-Terrill, LTD. | $2,491,791 | +36% | +18% |
| 5 | Hodges and Son Construction Company, Inc. | $2,746,723 | +50% | +30% |
| 6 | L A Fuller & Sons Construction, LTD. | $2,896,756 | +58% | +37% |
| 7 | J. Lee Milligan, Inc. | $3,386,966 | +84% | +60% |
Engineer's estimate: $2,112,424.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. STX Civil | 2. Talbert Companies LLC | 3. Earth Builders, L.P. | 4. Gilvin-Terrill, LTD. | 5. Hodges and Son Construction Company, Inc. | 6. L A Fuller & Sons Construction, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 75 | $65.00 | $20.00 | $59.40 | $25.00 | $75.00 | $70.00 | $36.05 |
| 2 | Removing concrete (curb & gutter) (104-7017) | LF | 33 | $29.45 | $6.00 | $44.00 | $25.00 | $75.00 | $100.00 | $36.25 |
| 3 | Remove (8") TRT/untrt base & asphalt pavement (105-7028) | SY | 1,285 | $11.00 | $8.00 | $8.80 | $20.00 | $15.00 | $15.00 | $19.35 |
| 4 | Excavation (roadway) (110-7001) | CY | 842 | $35.00 | $33.00 | $25.00 | $40.00 | $30.00 | $43.70 | |
| 5 | Excavation (channel) (110-7002) | CY | 145 | $17.00 | $33.00 | $25.00 | $40.00 | $30.00 | $79.95 | |
| 6 | Embankment (final)(OC)(type B) (132-7003) | CY | 852 | $22.00 | $66.00 | $40.00 | $45.00 | $45.00 | $28.40 | |
| 7 | Drill seed (permanent_rural_sand) (164-7041) | ACRE | 0.70 | $2,000.00 | $2,500.00 | $869.42 | $7,000.00 | $9,000.00 | $7,000.00 | $11,000 |
| 8 | Drill seed (temporary_warm) (164-7045) | ACRE | 0.35 | $2,000.00 | $1,000.00 | $596.20 | $7,000.00 | $6,000.00 | $5,000.00 | $11,000 |
| 9 | Drill seed (temporary_cool) (164-7046) | ACRE | 0.35 | $2,000.00 | $1,000.00 | $860.20 | $7,000.00 | $6,000.00 | $5,000.00 | $11,000 |
| 10 | Vegetative watering (168-7001) | TGL | 32.60 | $200.00 | $60.00 | $33.00 | $50.00 | $60.00 | $1.00 | $497.20 |
| 11 | Proof rolling (216-7001) | HR | 20 | $165.00 | $110.00 | $125.00 | $185.00 | $20.00 | $234.30 | |
| 12 | FL BS (compacted in place)(type A GR 3) (6") (247-7045) | SY | 2,504 | $30.00 | $49.50 | $40.00 | $30.00 | $35.00 | $43.65 | |
| 13 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 1,285 | $25.00 | $35.00 | $33.00 | $60.00 | $35.00 | $45.00 | $60.50 |
| 14 | Prime coat (MC-30) (310-7004) | GAL | 385 | $9.46 | $14.00 | $11.00 | $20.00 | $25.00 | $20.00 | $9.15 |
| 15 | Asphalt (CRS-2P) (316-7012) | GAL | 1,285 | $4.82 | $8.00 | $16.50 | $20.00 | $15.00 | $20.00 | $7.70 |
| 16 | Aggregate (type-B, GR-4)(sac-A) (316-7099) | CY | 24 | $125.00 | $3,000.00 | $330.00 | $500.00 | $500.00 | $1,700.00 | $564.15 |
| 17 | Trench excavation protection (402-7001) | LF | 168 | $10.11 | $60.00 | $20.90 | $1.00 | $30.00 | $5.00 | $20.30 |
| 18 | Class C concrete (rac-R) (420-7055) | CY | 9.25 | $1,475.00 | $3,000.00 | $500.00 | $650.00 | $1,500.00 | $800.00 | $1,662.80 |
| 19 | Riprap (concrete)(CL B) (432-7005) | CY | 21.80 | $778.76 | $800.00 | $990.00 | $650.00 | $1,000.00 | $800.00 | $935.00 |
| 20 | Riprap (mow strip)(4 in) (432-7013) | CY | 16 | $760.14 | $820.00 | $880.00 | $650.00 | $1,000.00 | $800.00 | $990.00 |
| 21 | Riprap (stone protection)(24 in) (432-7045) | CY | 255 | $231.34 | $210.00 | $330.00 | $230.00 | $300.00 | $300.00 | $275.00 |
| 22 | Rail (type T221) (450-7004) | LF | 156 | $275.00 | $235.00 | $120.00 | $220.00 | $250.00 | $180.00 | $271.50 |
| 23 | Rail (type T631LS) (450-7021) | LF | 268 | $187.00 | $128.98 | $120.00 | $85.00 | $75.00 | $78.50 | |
| 24 | Concrete box culvert (8 FT X 3 FT) (462-7020) | LF | 170 | $800.00 | $770.00 | $900.00 | $1,000.00 | $1,600.00 | $2,044.95 | |
| 25 | Concrete box culvert (10 FT X 5 FT) (462-7033) | LF | 170 | $1,100.00 | $1,320.00 | $1,350.00 | $1,500.00 | $1,800.00 | $2,311.70 | |
| 26 | Concrete box culvert (10 FT X 10 FT) (462-7038) | LF | 289 | $1,562.50 | $1,400.00 | $1,210.00 | $1,850.00 | $2,500.00 | $2,000.00 | $1,662.60 |
| 27 | Wingwall (FW - S) (HW=11 FT) (466-7167) | EACH | 1 | $55,341 | $53,100 | $52,800 | $40,000 | $30,000 | $120,000 | $67,072 |
| 28 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 2 | $25,000 | $15,400 | $14,000 | $12,000 | $35,000 | $20,890 | |
| 29 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 2 | $30,800 | $24,200 | $20,000 | $17,500 | $60,000 | $28,390 | |
| 30 | Wingwall (PW - 1) (HW=11 FT) (466-7181) | EACH | 1 | $80,339 | $60,000 | $66,000 | $45,000 | $55,000 | $100,000 | $59,439 |
| 31 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 3 | $66,086 | $22,000 | $16,500 | $40,000 | $66,500 | $75,000 | $44,612 |
| 32 | Mobilization (500-7001) | LS | 1 | $187,293 | $150,000 | $266,100 | $200,000 | $245,000 | $240,000 | $289,007 |
| 33 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $10,100 | $2,300.00 | $2,750.00 | $2,500.00 | $15,000 | $12,000 | $34,198 |
| 34 | Rock filter dams (install) (type 1) (506-7001) | LF | 290 | $40.00 | $40.00 | $48.97 | $75.00 | $45.00 | $1.00 | $49.50 |
| 35 | Rock filter dams (remove) (506-7011) | LF | 290 | $14.50 | $5.00 | $9.30 | $20.00 | $15.00 | $1.00 | $16.50 |
| 36 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 580 | $7.50 | $8.00 | $8.81 | $12.00 | $10.00 | $5.00 | $12.10 |
| 37 | Concrete curb & gutter (type II) (529-7009) | LF | 17 | $57.00 | $100.00 | $55.00 | $40.00 | $100.00 | $150.00 | $110.00 |
| 38 | Intersections (surface treat) (530-7005) | SY | 110 | $125.00 | $110.00 | $71.50 | $40.00 | $60.00 | $80.00 | $614.60 |
| 39 | Curb ramps (type 10) (531-7011) | EACH | 1 | $2,950.00 | $4,000.00 | $3,300.00 | $2,500.00 | $4,500.00 | $10,000 | $4,950.00 |
| 40 | Metal W-beam guard fence (steel post) (540-7002) | LF | 300 | $43.10 | $40.00 | $36.86 | $32.00 | $34.00 | $30.00 | $39.25 |
| 41 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 3 | $3,543.00 | $3,100.00 | $2,500.00 | $2,100.00 | $2,750.00 | $1,950.00 | $3,012.35 |
| 42 | TL-2 31" short radius (complete) (540-7036) | EACH | 1 | $1,060.00 | $23,500 | $38,118 | $21,000 | $3,000.00 | $20,000 | $3,384.65 |
| 43 | Guardrail end treatment (install) (544-7001) | EACH | 11 | $3,306.60 | $3,970.00 | $4,246.00 | $3,200.00 | $3,250.00 | $3,000.00 | $4,061.60 |
| 44 | Wire fence (type C) (552-7003) | LF | 610 | $25.00 | $71.50 | $30.00 | $65.00 | $25.00 | $36.90 | |
| 45 | Wire fence (water gap) (552-7010) | LF | 50 | $100.00 | $110.00 | $75.00 | $100.00 | $100.00 | $36.90 | |
| 46 | Wire fence (remove) (552-7011) | LF | 610 | $2.00 | $11.00 | $5.00 | $10.00 | $5.00 | $6.75 | |
| 47 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 24 | $65.00 | $45.10 | $35.00 | $35.00 | $25.00 | $41.95 | |
| 48 | Pavement sler 6" (666-7347) | LF | 115 | $0.49 | $4.85 | $4.40 | $5.00 | $4.00 | $5.00 | $4.40 |
| 49 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 910 | $1.21 | $8.49 | $7.70 | $8.00 | $7.00 | $8.00 | $7.70 |
| 50 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 910 | $1.24 | $8.49 | $7.70 | $8.00 | $7.00 | $8.00 | $7.70 |
| 51 | Pavement surface preparation for marking (6") (678-7002) | LF | 115 | $0.38 | $4.85 | $4.40 | $5.00 | $4.00 | $5.00 | $4.40 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.