TxDOT contract A00185701 bid tabulation

Bridge Replacement, COUNTY ROAD 3689 (CR 3689 at Cypress Creek to .). Let by Texas DOT on August 7, 2025, Shelby, Lufkin District. 8 bids received; low bid $1,630,098 by Hodges and Son Construction Company, Inc., -25% against the engineer's estimate of $2,163,444.

Owner
Texas DOT
Letting
07 AUG 2025
Pay items
53
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Hodges and Son Construction Company, Inc.$1,630,098Low-25%
2THK Construction LLC$1,695,871+4.0%-22%
3Talbert Companies LLC$1,854,462+14%-14%
4True Roads Construction, LLC$1,965,519+21%-9.0%
5Blacksmith Ventures LLC$1,979,075+21%-9.0%
6Texas Steel Industrial Placing, LLC$1,997,699+23%-8.0%
7Lakey, Inc.$2,052,166+26%-5.0%
8Skyline Bridge LLC$2,087,399+28%-4.0%
TxDOT contract A00185701: bids by rank

Engineer's estimate: $2,163,444.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Hodges and Son Construction Company, Inc.2. THK Construction LLC3. Talbert Companies LLC4. True Roads Construction, LLC5. Blacksmith Ventures LLC6. Texas Steel Industrial Placing, LLC
1Preparing row (100-7002)STA12.75$2,000.00$3,000.00$2,000.00$3,000.00$3,000.00$4,705.00$2,000.00
2Excavation (roadway) (110-7001)CY977$20.00$20.00$18.00$26.00$20.00$5.00$25.00
3Embankment (final)(OC)(type B) (132-7003)CY746$30.00$20.00$18.00$31.00$32.00$25.00$30.00
4Furn & place topsoil (4") (160-7002)SY2,743$4.00$3.00$3.50$9.00$5.00$5.00$3.00
5Block sodding (162-7002)SY624$10.00$8.00$9.63$9.00$12.00$15.00$8.00
6Broadcast seed (temporary_warm) (164-7005)SY1,645$2.00$0.50$1.07$1.00$1.20$0.50$1.00
7Broadcast seed (temporary_cool) (164-7006)SY1,645$2.00$0.50$1.07$1.00$1.20$0.50$1.00
8Bond fiber MTRX seed (permanent)(rural)(sand) (164-7076)SY3,289$2.50$1.50$1.56$1.45$1.75$0.50$1.25
9Vegetative watering (168-7001)TGL132$10.00$1.00$10.00$50.00$22.00$10.00$10.00
10Soil ret BLKT(SL_mod_sand_short_roll) (169-7011)SY140$6.00$4.00$7.49$7.00$8.40$10.00$10.00
11FL BS (compacted in place)(type D GR 1-2) (4") (247-7033)SY1,372$35.00$40.00$31.50$25.00$40.00$25.00
12FL BS (compacted in place)(type D GR 1-2) (6") (247-7056)SY1,288$50.00$40.00$40.00$31.50$32.00$40.00$30.00
13Asphalt (RC-250) (316-7032)TON1.42$5,000.00$3,521.00$7,010.05$4,000.00$2,450.00$2,000.00
14Aggregate (type E or L, GR-5) (316-7254)CY10$1,500.00$500.00$874.50$850.00$500.00$1,000.00
15SP mixes SP-C sac-B PG64-22 (344-7011)TON148$200.00$300.00$180.00$280.00$200.00$250.00
16Cem stabil BKFL (400-7010)CY151$350.00$300.00$350.00$213.00$350.00$250.00$250.00
17Drilled shaft (18 in) (416-7002)LF168$140.00$206.11$145.00$375.00$325.00$400.00
18Drilled shaft (30 in) (416-7005)LF417$325.00$230.00$266.63$230.00$495.00$425.00$500.00
19Drilled shaft (36 in) (416-7006)LF252$230.00$301.47$250.00$460.00$390.00$550.00
20Class C concrete (abutment) (420-7012)CY97.60$1,200.00$1,400.00$1,050.00$1,350.00$1,400.00$2,500.00$1,250.00
21Reinforced concrete slab (422-7001)SF1,950$30.00$30.00$29.00$40.00$22.00$28.00
22Reinforced concrete slab (box beam) (422-7005)SF3,402$30.00$25.00$21.00$28.00$25.00$22.00$25.00
23Shear key (422-7020)CY17.20$900.00$600.00$800.00$750.00$565.00$1,000.00$650.00
24Prestressed concrete girder (TX28) (425-7001)LF297.69$300.00$322.52$207.22$305.00$275.00$330.00
25Prestressed concrete box beam (4B20) (425-7026)LF516$350.00$310.00$305.21$244.95$295.00$300.00$310.00
26Prestressed concrete box beam (5B20) (425-7027)LF258$350.00$310.00$366.06$244.95$295.00$300.00$395.00
27Riprap (stone protection)(24 in) (432-7045)CY703$290.00$225.00$200.00$216.00$200.00$225.00$200.00
28Rail (type T223) (450-7008)LF530$200.00$150.00$180.00$165.00$140.00$175.00$150.00
29Armor joint (sealed) (454-7003)LF139$155.00$190.00$150.00$165.00$140.00$75.00$150.00
30Removing structure (bridge 0 - 99 FT length) (496-7009)EACH3$20,000$5,000.00$5,000.00$15,000$13,500$20,000$28,000
31Mobilization (500-7001)LS1$200,000$140,000$160,000$343,200$200,000$225,000$200,000
32Barricades, signs and traffic handling (502-7001)MO19$2,000.00$1,800.00$1,008.06$2,800.00$2,000.00$263.00$1,250.00
33Rock filter dams (install) (type 2) (506-7002)LF112$50.00$1.00$42.80$40.00$48.00$50.00$40.00
34Rock filter dams (remove) (506-7011)LF112$15.00$1.00$14.98$14.00$17.00$1.00$10.00
35Construction exits (install) (type 1) (506-7020)SY305$30.00$1.00$42.80$40.00$48.00$1.00$40.00
36Construction exits (remove) (506-7024)SY305$10.00$1.00$13.91$13.00$16.00$1.00$10.00
37Construction perimeter fence (506-7034)LF281$12.00$2.00$6.42$6.00$7.00$15.00$6.00
38Temporary sediment control fence (install) (506-7039)LF2,469$4.00$1.00$4.28$4.00$5.00$4.00$5.00
39Temporary sediment control fence (remove) (506-7041)LF2,469$1.10$1.00$1.07$1.00$1.50$1.00$2.00
40Driveways (ACP) (530-7010)SY20$105.00$300.00$77.00$120.00$200.00$200.00
41Driveways (base) (530-7015)SY30$60.00$40.00$35.00$95.00$75.00$80.00
42Metal W-beam guard fence (timber post) (540-7001)LF512.50$35.00$25.00$25.92$23.00$28.00$29.00$26.00
43Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$1,600.00$1,658.50$1,575.00$1,900.00$2,379.00$2,000.00
44Metal beam guard fence trans (TL2) (540-7006)EACH8$1,900.00$1,200.00$1,257.25$1,175.00$1,500.00$1,755.00$1,600.00
45Downstream anchor terminal section (540-7015)EACH6$1,500.00$1,300.00$1,364.25$1,300.00$1,500.00$1,500.00$1,725.00
46Guardrail end treatment (install) (544-7001)EACH6$3,500.00$3,000.00$3,210.00$2,900.00$3,600.00$3,000.00$3,250.00
47Wire fence (type C) (552-7003)LF775$50.00$20.00$30.00$25.00$18.00$10.00$30.00
48Gate (type 1) (552-7006)EACH2$2,500.00$1,000.00$500.00$2,535.83$1,800.00$250.00$1,000.00
49Wire fence (water gap) (552-7010)LF100$200.00$60.00$10.00$64.00$36.00$25.00$50.00
50Remove SM RD SN sup&AM (644-7073)EACH6$250.00$50.00$250.00$152.38$120.00$1.00$200.00
51Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH10$30.00$15.00$16.05$25.00$18.00$50.00$30.00
52Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH20$30.00$30.00$26.75$31.00$30.00$50.00$50.00
53Bonding course (3007-7001)GAL66$8.00$20.00$25.00$15.00$45.00$40.00
TxDOT contract A00185701: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy