TxDOT contract A00188143 bid tabulation

Rehabilitate Existing Roadway, FM 1344 (CR 209 to Wilson/Karnes County Line). Let by Texas DOT on December 2, 2025, Wilson, San Antonio District. 8 bids received; low bid $9,689,291 by Hunter Industries, LTD., -17% against the engineer's estimate of $11,652,395.

Owner
Texas DOT
Letting
02 DEC 2025
Pay items
97
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Hunter Industries, LTD.$9,689,291Low-17%
2CK Newberry, LLC$11,697,577+21%0.0%
3Salinas Construction Technologies, LTD.$11,800,154+22%+1.0%
4D & D Contractors, Inc.$12,038,285+24%+3.0%
5Texas Materials Group, Inc.$12,215,933+26%+5.0%
6Posillico Civil, Inc.$12,395,145+28%+6.0%
7Go Underground, Limited Liability Company$14,658,694+51%+26%
8Jordan Foster Construction, LLC$16,252,478+68%+39%
TxDOT contract A00188143: bids by rank

Engineer's estimate: $11,652,395.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Hunter Industries, LTD.2. CK Newberry, LLC3. Salinas Construction Technologies, LTD.4. D & D Contractors, Inc.5. Texas Materials Group, Inc.6. Posillico Civil, Inc.
1Preparing row (100-7002)STA257$778.00$492.60$250.00$109.76$169.76$2,000.00$1,800.00
2Removing concrete (driveways) (104-7011)SY237$17.00$19.68$30.00$36.23$20.05$20.65$10.00
3Remove (5"-9") TRT/untrt base & asphalt pavement (105-7005)SY72,847$5.25$4.05$3.50$5.49$4.66$7.74$2.00
4Excavation (roadway) (110-7001)CY20,479$17.30$15.32$10.00$11.26$15.81$16.90$6.00
5Embankment (final)(OC)(type C) (132-7005)CY11,388$13.25$15.32$10.00$9.97$7.12$13.60$10.00
6Furn & place topsoil (4") (160-7002)SY90,032$3.90$0.99$0.75$1.62$6.45$1.60$2.00
7Broadcast seed (temporary_warm) (164-7005)SY45,019$1.25$0.16$0.15$0.22$0.18$0.14$0.14
8Broadcast seed (temporary_cool) (164-7006)SY45,019$0.20$0.20$0.15$0.22$0.22$0.14$0.14
9Drill seed (permanent_rural_clay) (164-7010)SY90,032$0.29$0.25$0.20$0.34$0.27$0.17$0.15
10Vegetative watering (168-7001)TGL2,815$72.90$22.96$25.00$27.19$29.86$5.00$12.00
11Proof rolling (216-7001)HR100$102.00$77.00$75.00$75.19$76.26$145.00$150.00
12FL BS (compacted in place)(type D GR 5) (247-7016)TON65,280$15.00$28.43$32.00$37.31$32.08$36.60$48.00
13Lime (com or QK)(slurry) or QK(dry) (260-7001)TON1,226$340.00$316.44$350.00$348.46$323.87$315.00$350.00
14Lime TRT (subgrade) (8") (260-7020)SY58,851$2.00$1.65$3.50$2.23$3.83$3.77$4.00
15Cement (275-7001)TON1,418$228.00$194.40$200.00$209.98$215.16$196.00$290.00
16Cement TRT (new base)(10") (275-7012)SY114,208$4.39$1.65$2.00$1.87$3.35$1.80$3.75
17Prime coat (RC-250) (310-7006)GAL20,466$4.25$4.76$4.75$5.71$5.75$5.40$4.00
18Aggregate (type-B, GR-5)(sac-B) (316-7175)CY751$69.00$75.92$175.00$174.06$318.53$225.00$245.00
19D-GR HMA type-B PG64-22 (341-7001)TON10$100.00$214.52$500.00$597.01$64.15$380.00$700.00
20D-GR HMA type-C sac-B PG70-22 (341-7024)TON11,770$93.00$93.74$110.00$112.37$123.87$99.70$94.00
21D-GR HMA type D PG70-22 (level-UP) (341-7051)TON9,118$100.00$98.06$140.00$106.49$149.31$107.00$105.00
22Tack coat (341-7082)GAL248$90.00$3.08$4.00$10.89$7.74$3.75$3.00
23Flexible pavement structure repair(8") (351-7007)SY2,275$57.00$53.01$60.00$85.85$91.80$60.00$70.00
24Cut & restoring pavement (400-7006)SY232$109.00$125.00$100.00$176.79$77.08$158.00$140.00
25Cem stabil BKFL (400-7010)CY802$157.00$160.00$150.00$150.42$193.55$195.00$85.00
26Trench excavation protection (402-7001)LF329$17.50$101.00$20.00$13.41$16.59$17.00$10.00
27Temporary special shoring (403-7001)SF1,126$51.50$65.00$22.00$44.21$38.71$31.50$25.00
28Riprap (stone protection)(12 in) (432-7041)CY131$215.00$260.00$320.00$270.08$171.43$249.00$170.00
29Concrete box culvert (3 FT X 2 FT) (462-7001)LF72$750.00$355.00$350.00$428.61$568.95$398.00$380.00
30Concrete box culvert (4 FT X 2 FT) (462-7003)LF172$515.00$360.00$425.00$388.28$438.24$400.00$450.00
31Concrete box culvert (6 FT X 3 FT) (462-7011)LF236$750.00$650.00$775.00$587.61$760.20$553.00$700.00
32RC pipe (CL III)(18 in) (464-7003)LF1,004$65.00$68.00$110.00$73.49$106.00$125.00$85.00
33RC pipe (CL III)(24 in) (464-7005)LF140$89.00$80.00$130.00$105.63$119.46$130.00$175.00
34RC pipe (CL III)(42 in) (464-7010)LF175$220.00$250.00$285.00$277.38$277.68$392.00$275.00
35Headwall (CH - PW - 0) (diameter= 42 in) (466-7106)EACH3$16,000$18,000$12,500$19,052$16,037$17,200$15,000
36Wingwall (FW - S) (HW=3 FT) (466-7159)EACH1$11,500$4,500.00$7,150.00$20,835$5,408.34$14,750$18,000
37Wingwall (FW - S) (HW=4 FT) (466-7160)EACH1$9,350.00$5,500.00$7,500.00$21,266$5,945.86$15,225$20,000
38Wingwall (PW - 1) (HW=5 FT) (466-7175)EACH1$20,000$16,500$15,000$23,291$19,324$25,500$28,000
39Wingwall (PW - 2) (HW=4 FT) (466-7188)EACH2$14,500$8,200.00$13,500$22,747$17,559$25,800$25,000
40Wingwall (PW - 2) (HW=5 FT) (466-7189)EACH1$21,500$21,000$15,000$23,210$19,510$26,450$30,000
41Set (type I) (42 in) (3: 1) (C) (467-7020)EACH1$19,500$16,600$8,000.00$11,599$6,514.34$8,900.00$10,000
42Set (type I)(S= 6 FT)(HW= 4 FT)(3:1)(C) (467-7128)EACH2$23,000$15,000$21,000$18,415$9,843.40$30,500$25,000
43Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH38$1,060.00$1,800.00$2,500.00$1,183.43$1,631.35$2,100.00$1,500.00
44Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH4$1,505.00$2,300.00$2,250.00$1,477.38$2,322.60$2,290.00$2,000.00
45Removing structure (set) (496-7004)EACH20$175.00$590.00$1,500.00$462.70$446.72$620.00$400.00
46Removing structure (wingwall) (496-7005)EACH10$1,150.00$1,500.00$2,000.00$1,905.08$540.38$1,360.00$700.00
47Removing structure (pipe) (496-7007)LF348$10.00$21.00$35.00$14.37$43.24$25.00$13.00
48Remove STR (driveway culvert) (496-7038)EACH9$1,500.00$3,000.00$1,000.00$1,842.29$1,178.97$1,150.00$700.00
49Mobilization (500-7001)LS1$1,008,400$756,303$1,100,000$1,180,510$576,447$763,000$750,000
50Barricades, signs and traffic handling (502-7001)MO28$20,000$2,776.51$9,500.00$1,964.57$6,083.00$12,885$8,000.00
51TMA (stationary) (505-7001)DAY1,094$190.00$111.61$200.00$84.77$212.30$0.01$100.00
52TMA (mobile operation) (505-7002)HR40$92.00$111.61$225.00$317.32$196.32$89.00$500.00
53Rock filter dams (install) (type 1) (506-7001)LF1,560$45.00$30.66$40.00$21.06$33.18$40.60$25.00
54Rock filter dams (install) (type 2) (506-7002)LF780$46.45$40.88$50.00$29.52$44.24$47.30$30.00
55Rock filter dams (remove) (506-7011)LF2,340$10.30$9.20$12.00$5.29$9.95$12.14$5.00
56Temporary sediment control fence (install) (506-7039)LF24,360$3.03$3.01$3.25$3.60$3.26$3.20$2.00
57Temporary sediment control fence (remove) (506-7041)LF24,360$0.95$0.82$1.00$1.13$0.88$0.88$1.00
58Constructing detours (508-7001)SY14,540$82.00$40.32$65.00$49.96$44.18$65.90$70.00
59Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF240$29.00$39.00$30.00$29.61$63.53$39.00$110.00
60Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF80$29.00$38.00$45.00$29.53$123.71$33.00$110.00
61Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF960$10.00$22.00$25.00$12.10$8.20$31.40$10.00
62Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF320$11.00$41.00$38.00$14.56$8.20$31.40$10.00
63Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF240$9.00$22.00$30.00$16.88$13.15$32.00$15.00
64Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF80$13.51$42.00$45.00$17.50$20.68$32.00$15.00
65Intersections (ACP) (530-7002)SY2,939$65.00$46.88$70.00$93.53$87.80$53.80$71.00
66Driveways (concrete) (530-7006)SY120$105.00$130.00$125.00$157.36$135.21$158.00$160.00
67Driveways (ACP) (type 1) (530-7011)SY3,751$50.00$39.24$40.00$79.73$36.50$79.00$70.00
68Turnouts (ACP) (530-7018)SY153$70.00$39.24$35.00$93.43$86.27$79.00$135.00
69Mill rumble strips (asphalt) (shoulder) (533-7001)LF47,347$0.13$0.17$0.15$0.51$0.20$0.36$0.10
70Mill rumble strips (asphalt) (centerline) (533-7002)LF21,817$0.15$0.31$0.15$0.53$0.24$0.41$0.15
71Mailbox install-S (WC-post) type 3 (560-7004)EACH13$215.00$145.00$145.00$245.54$160.37$145.00$400.00
72Mailbox install-D (WC-post) type 3 (560-7005)EACH1$257.00$175.00$175.00$324.29$193.55$175.00$400.00
73Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH93$689.00$575.00$575.00$456.24$635.95$575.00$450.00
74Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH19$853.00$675.00$675.00$587.28$746.55$675.00$575.00
75Remove SM RD SN sup&AM (644-7073)EACH36$121.00$100.00$100.00$141.57$110.60$100.00$45.00
76Install object marker assembly (OM-2X)(WC)GND (658-7055)EACH28$79.00$65.00$65.00$88.70$71.89$65.00$55.00
77Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF51,368$0.20$0.24$0.35$0.26$0.23$0.21$0.20
78Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF4,702$0.22$0.28$0.40$0.28$0.28$0.25$0.20
79Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF53,308$0.23$0.24$0.35$0.24$0.23$0.21$0.20
80Work zone pavement marking non-removing (Y)24"(solid) (662-7042)LF254$2.13$3.36$6.50$6.08$3.32$3.00$4.00
81Work zone pavement marking removing (reflectorized) type II-A-A (662-7051)EACH1,436$3.86$3.92$4.50$3.74$3.87$3.50$4.50
82Work zone pavement marking removing (W)6"(solid) (662-7068)LF55,464$0.66$0.66$1.00$0.65$0.65$0.59$0.50
83Work zone pavement marking removing (W)24"(solid) (662-7077)LF1,886$6.32$4.48$6.50$4.69$4.42$4.00$6.00
84Work zone pavement marking removing (Y)6"(solid) (662-7100)LF51,534$0.63$0.66$1.00$0.66$0.65$0.59$0.50
85Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH11,966$0.84$1.53$0.55$1.33$0.74$1.50$0.50
86Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035)LF106$7.50$7.84$7.50$14.36$7.74$7.00$13.00
87Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041)EACH6$226.41$168.09$150.00$188.46$165.90$150.00$175.00
88Reflectorized pavement marking type I (Y)24"(solid)(090MIL) (666-7122)LF254$3.00$7.28$7.50$9.75$7.19$6.50$12.00
89Pavement sler 6" (666-7347)LF103,379$0.15$0.21$0.25$0.22$0.21$0.19$0.20
90Pavement sler 24" (666-7352)LF360$1.02$2.24$2.50$2.87$2.21$2.00$3.00
91Pavement sler (arrow) (666-7353)EACH6$100.00$33.62$30.00$46.98$33.18$30.00$65.00
92Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410)LF50,316$0.65$0.61$0.55$0.60$0.60$0.54$0.50
93Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419)LF7,021$0.79$0.67$0.60$0.64$0.66$0.60$0.50
94Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422)LF46,042$0.66$0.61$0.55$0.61$0.60$0.54$0.50
95Reflectorized pavement marker type II-A-A (672-7004)EACH742$4.00$4.15$4.50$4.39$4.09$3.70$5.00
96Bonding course (3007-7001)GAL12,427$6.00$3.14$4.00$11.33$4.98$3.90$4.00
97Natural gas pipeline (7080-7001)LF8,325$35.00$9.00$10.00$20.25$9.95$9.00$12.00
TxDOT contract A00188143: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of December 2, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy