TxDOT contract A00188143 bid tabulation
Rehabilitate Existing Roadway, FM 1344 (CR 209 to Wilson/Karnes County Line). Let by Texas DOT on December 2, 2025, Wilson, San Antonio District. 8 bids received; low bid $9,689,291 by Hunter Industries, LTD., -17% against the engineer's estimate of $11,652,395.
- Owner
- Texas DOT
- Letting
- 02 DEC 2025
- Pay items
- 97
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hunter Industries, LTD. | $9,689,291 | Low | -17% |
| 2 | CK Newberry, LLC | $11,697,577 | +21% | 0.0% |
| 3 | Salinas Construction Technologies, LTD. | $11,800,154 | +22% | +1.0% |
| 4 | D & D Contractors, Inc. | $12,038,285 | +24% | +3.0% |
| 5 | Texas Materials Group, Inc. | $12,215,933 | +26% | +5.0% |
| 6 | Posillico Civil, Inc. | $12,395,145 | +28% | +6.0% |
| 7 | Go Underground, Limited Liability Company | $14,658,694 | +51% | +26% |
| 8 | Jordan Foster Construction, LLC | $16,252,478 | +68% | +39% |
Engineer's estimate: $11,652,395.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hunter Industries, LTD. | 2. CK Newberry, LLC | 3. Salinas Construction Technologies, LTD. | 4. D & D Contractors, Inc. | 5. Texas Materials Group, Inc. | 6. Posillico Civil, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 257 | $778.00 | $492.60 | $250.00 | $109.76 | $169.76 | $2,000.00 | $1,800.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 237 | $17.00 | $19.68 | $30.00 | $36.23 | $20.05 | $20.65 | $10.00 |
| 3 | Remove (5"-9") TRT/untrt base & asphalt pavement (105-7005) | SY | 72,847 | $5.25 | $4.05 | $3.50 | $5.49 | $4.66 | $7.74 | $2.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 20,479 | $17.30 | $15.32 | $10.00 | $11.26 | $15.81 | $16.90 | $6.00 |
| 5 | Embankment (final)(OC)(type C) (132-7005) | CY | 11,388 | $13.25 | $15.32 | $10.00 | $9.97 | $7.12 | $13.60 | $10.00 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 90,032 | $3.90 | $0.99 | $0.75 | $1.62 | $6.45 | $1.60 | $2.00 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 45,019 | $1.25 | $0.16 | $0.15 | $0.22 | $0.18 | $0.14 | $0.14 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 45,019 | $0.20 | $0.20 | $0.15 | $0.22 | $0.22 | $0.14 | $0.14 |
| 9 | Drill seed (permanent_rural_clay) (164-7010) | SY | 90,032 | $0.29 | $0.25 | $0.20 | $0.34 | $0.27 | $0.17 | $0.15 |
| 10 | Vegetative watering (168-7001) | TGL | 2,815 | $72.90 | $22.96 | $25.00 | $27.19 | $29.86 | $5.00 | $12.00 |
| 11 | Proof rolling (216-7001) | HR | 100 | $102.00 | $77.00 | $75.00 | $75.19 | $76.26 | $145.00 | $150.00 |
| 12 | FL BS (compacted in place)(type D GR 5) (247-7016) | TON | 65,280 | $15.00 | $28.43 | $32.00 | $37.31 | $32.08 | $36.60 | $48.00 |
| 13 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 1,226 | $340.00 | $316.44 | $350.00 | $348.46 | $323.87 | $315.00 | $350.00 |
| 14 | Lime TRT (subgrade) (8") (260-7020) | SY | 58,851 | $2.00 | $1.65 | $3.50 | $2.23 | $3.83 | $3.77 | $4.00 |
| 15 | Cement (275-7001) | TON | 1,418 | $228.00 | $194.40 | $200.00 | $209.98 | $215.16 | $196.00 | $290.00 |
| 16 | Cement TRT (new base)(10") (275-7012) | SY | 114,208 | $4.39 | $1.65 | $2.00 | $1.87 | $3.35 | $1.80 | $3.75 |
| 17 | Prime coat (RC-250) (310-7006) | GAL | 20,466 | $4.25 | $4.76 | $4.75 | $5.71 | $5.75 | $5.40 | $4.00 |
| 18 | Aggregate (type-B, GR-5)(sac-B) (316-7175) | CY | 751 | $69.00 | $75.92 | $175.00 | $174.06 | $318.53 | $225.00 | $245.00 |
| 19 | D-GR HMA type-B PG64-22 (341-7001) | TON | 10 | $100.00 | $214.52 | $500.00 | $597.01 | $64.15 | $380.00 | $700.00 |
| 20 | D-GR HMA type-C sac-B PG70-22 (341-7024) | TON | 11,770 | $93.00 | $93.74 | $110.00 | $112.37 | $123.87 | $99.70 | $94.00 |
| 21 | D-GR HMA type D PG70-22 (level-UP) (341-7051) | TON | 9,118 | $100.00 | $98.06 | $140.00 | $106.49 | $149.31 | $107.00 | $105.00 |
| 22 | Tack coat (341-7082) | GAL | 248 | $90.00 | $3.08 | $4.00 | $10.89 | $7.74 | $3.75 | $3.00 |
| 23 | Flexible pavement structure repair(8") (351-7007) | SY | 2,275 | $57.00 | $53.01 | $60.00 | $85.85 | $91.80 | $60.00 | $70.00 |
| 24 | Cut & restoring pavement (400-7006) | SY | 232 | $109.00 | $125.00 | $100.00 | $176.79 | $77.08 | $158.00 | $140.00 |
| 25 | Cem stabil BKFL (400-7010) | CY | 802 | $157.00 | $160.00 | $150.00 | $150.42 | $193.55 | $195.00 | $85.00 |
| 26 | Trench excavation protection (402-7001) | LF | 329 | $17.50 | $101.00 | $20.00 | $13.41 | $16.59 | $17.00 | $10.00 |
| 27 | Temporary special shoring (403-7001) | SF | 1,126 | $51.50 | $65.00 | $22.00 | $44.21 | $38.71 | $31.50 | $25.00 |
| 28 | Riprap (stone protection)(12 in) (432-7041) | CY | 131 | $215.00 | $260.00 | $320.00 | $270.08 | $171.43 | $249.00 | $170.00 |
| 29 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 72 | $750.00 | $355.00 | $350.00 | $428.61 | $568.95 | $398.00 | $380.00 |
| 30 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 172 | $515.00 | $360.00 | $425.00 | $388.28 | $438.24 | $400.00 | $450.00 |
| 31 | Concrete box culvert (6 FT X 3 FT) (462-7011) | LF | 236 | $750.00 | $650.00 | $775.00 | $587.61 | $760.20 | $553.00 | $700.00 |
| 32 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,004 | $65.00 | $68.00 | $110.00 | $73.49 | $106.00 | $125.00 | $85.00 |
| 33 | RC pipe (CL III)(24 in) (464-7005) | LF | 140 | $89.00 | $80.00 | $130.00 | $105.63 | $119.46 | $130.00 | $175.00 |
| 34 | RC pipe (CL III)(42 in) (464-7010) | LF | 175 | $220.00 | $250.00 | $285.00 | $277.38 | $277.68 | $392.00 | $275.00 |
| 35 | Headwall (CH - PW - 0) (diameter= 42 in) (466-7106) | EACH | 3 | $16,000 | $18,000 | $12,500 | $19,052 | $16,037 | $17,200 | $15,000 |
| 36 | Wingwall (FW - S) (HW=3 FT) (466-7159) | EACH | 1 | $11,500 | $4,500.00 | $7,150.00 | $20,835 | $5,408.34 | $14,750 | $18,000 |
| 37 | Wingwall (FW - S) (HW=4 FT) (466-7160) | EACH | 1 | $9,350.00 | $5,500.00 | $7,500.00 | $21,266 | $5,945.86 | $15,225 | $20,000 |
| 38 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 1 | $20,000 | $16,500 | $15,000 | $23,291 | $19,324 | $25,500 | $28,000 |
| 39 | Wingwall (PW - 2) (HW=4 FT) (466-7188) | EACH | 2 | $14,500 | $8,200.00 | $13,500 | $22,747 | $17,559 | $25,800 | $25,000 |
| 40 | Wingwall (PW - 2) (HW=5 FT) (466-7189) | EACH | 1 | $21,500 | $21,000 | $15,000 | $23,210 | $19,510 | $26,450 | $30,000 |
| 41 | Set (type I) (42 in) (3: 1) (C) (467-7020) | EACH | 1 | $19,500 | $16,600 | $8,000.00 | $11,599 | $6,514.34 | $8,900.00 | $10,000 |
| 42 | Set (type I)(S= 6 FT)(HW= 4 FT)(3:1)(C) (467-7128) | EACH | 2 | $23,000 | $15,000 | $21,000 | $18,415 | $9,843.40 | $30,500 | $25,000 |
| 43 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 38 | $1,060.00 | $1,800.00 | $2,500.00 | $1,183.43 | $1,631.35 | $2,100.00 | $1,500.00 |
| 44 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 4 | $1,505.00 | $2,300.00 | $2,250.00 | $1,477.38 | $2,322.60 | $2,290.00 | $2,000.00 |
| 45 | Removing structure (set) (496-7004) | EACH | 20 | $175.00 | $590.00 | $1,500.00 | $462.70 | $446.72 | $620.00 | $400.00 |
| 46 | Removing structure (wingwall) (496-7005) | EACH | 10 | $1,150.00 | $1,500.00 | $2,000.00 | $1,905.08 | $540.38 | $1,360.00 | $700.00 |
| 47 | Removing structure (pipe) (496-7007) | LF | 348 | $10.00 | $21.00 | $35.00 | $14.37 | $43.24 | $25.00 | $13.00 |
| 48 | Remove STR (driveway culvert) (496-7038) | EACH | 9 | $1,500.00 | $3,000.00 | $1,000.00 | $1,842.29 | $1,178.97 | $1,150.00 | $700.00 |
| 49 | Mobilization (500-7001) | LS | 1 | $1,008,400 | $756,303 | $1,100,000 | $1,180,510 | $576,447 | $763,000 | $750,000 |
| 50 | Barricades, signs and traffic handling (502-7001) | MO | 28 | $20,000 | $2,776.51 | $9,500.00 | $1,964.57 | $6,083.00 | $12,885 | $8,000.00 |
| 51 | TMA (stationary) (505-7001) | DAY | 1,094 | $190.00 | $111.61 | $200.00 | $84.77 | $212.30 | $0.01 | $100.00 |
| 52 | TMA (mobile operation) (505-7002) | HR | 40 | $92.00 | $111.61 | $225.00 | $317.32 | $196.32 | $89.00 | $500.00 |
| 53 | Rock filter dams (install) (type 1) (506-7001) | LF | 1,560 | $45.00 | $30.66 | $40.00 | $21.06 | $33.18 | $40.60 | $25.00 |
| 54 | Rock filter dams (install) (type 2) (506-7002) | LF | 780 | $46.45 | $40.88 | $50.00 | $29.52 | $44.24 | $47.30 | $30.00 |
| 55 | Rock filter dams (remove) (506-7011) | LF | 2,340 | $10.30 | $9.20 | $12.00 | $5.29 | $9.95 | $12.14 | $5.00 |
| 56 | Temporary sediment control fence (install) (506-7039) | LF | 24,360 | $3.03 | $3.01 | $3.25 | $3.60 | $3.26 | $3.20 | $2.00 |
| 57 | Temporary sediment control fence (remove) (506-7041) | LF | 24,360 | $0.95 | $0.82 | $1.00 | $1.13 | $0.88 | $0.88 | $1.00 |
| 58 | Constructing detours (508-7001) | SY | 14,540 | $82.00 | $40.32 | $65.00 | $49.96 | $44.18 | $65.90 | $70.00 |
| 59 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 240 | $29.00 | $39.00 | $30.00 | $29.61 | $63.53 | $39.00 | $110.00 |
| 60 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 80 | $29.00 | $38.00 | $45.00 | $29.53 | $123.71 | $33.00 | $110.00 |
| 61 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 960 | $10.00 | $22.00 | $25.00 | $12.10 | $8.20 | $31.40 | $10.00 |
| 62 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 320 | $11.00 | $41.00 | $38.00 | $14.56 | $8.20 | $31.40 | $10.00 |
| 63 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 240 | $9.00 | $22.00 | $30.00 | $16.88 | $13.15 | $32.00 | $15.00 |
| 64 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 80 | $13.51 | $42.00 | $45.00 | $17.50 | $20.68 | $32.00 | $15.00 |
| 65 | Intersections (ACP) (530-7002) | SY | 2,939 | $65.00 | $46.88 | $70.00 | $93.53 | $87.80 | $53.80 | $71.00 |
| 66 | Driveways (concrete) (530-7006) | SY | 120 | $105.00 | $130.00 | $125.00 | $157.36 | $135.21 | $158.00 | $160.00 |
| 67 | Driveways (ACP) (type 1) (530-7011) | SY | 3,751 | $50.00 | $39.24 | $40.00 | $79.73 | $36.50 | $79.00 | $70.00 |
| 68 | Turnouts (ACP) (530-7018) | SY | 153 | $70.00 | $39.24 | $35.00 | $93.43 | $86.27 | $79.00 | $135.00 |
| 69 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 47,347 | $0.13 | $0.17 | $0.15 | $0.51 | $0.20 | $0.36 | $0.10 |
| 70 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 21,817 | $0.15 | $0.31 | $0.15 | $0.53 | $0.24 | $0.41 | $0.15 |
| 71 | Mailbox install-S (WC-post) type 3 (560-7004) | EACH | 13 | $215.00 | $145.00 | $145.00 | $245.54 | $160.37 | $145.00 | $400.00 |
| 72 | Mailbox install-D (WC-post) type 3 (560-7005) | EACH | 1 | $257.00 | $175.00 | $175.00 | $324.29 | $193.55 | $175.00 | $400.00 |
| 73 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 93 | $689.00 | $575.00 | $575.00 | $456.24 | $635.95 | $575.00 | $450.00 |
| 74 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 19 | $853.00 | $675.00 | $675.00 | $587.28 | $746.55 | $675.00 | $575.00 |
| 75 | Remove SM RD SN sup&AM (644-7073) | EACH | 36 | $121.00 | $100.00 | $100.00 | $141.57 | $110.60 | $100.00 | $45.00 |
| 76 | Install object marker assembly (OM-2X)(WC)GND (658-7055) | EACH | 28 | $79.00 | $65.00 | $65.00 | $88.70 | $71.89 | $65.00 | $55.00 |
| 77 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 51,368 | $0.20 | $0.24 | $0.35 | $0.26 | $0.23 | $0.21 | $0.20 |
| 78 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 4,702 | $0.22 | $0.28 | $0.40 | $0.28 | $0.28 | $0.25 | $0.20 |
| 79 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 53,308 | $0.23 | $0.24 | $0.35 | $0.24 | $0.23 | $0.21 | $0.20 |
| 80 | Work zone pavement marking non-removing (Y)24"(solid) (662-7042) | LF | 254 | $2.13 | $3.36 | $6.50 | $6.08 | $3.32 | $3.00 | $4.00 |
| 81 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 1,436 | $3.86 | $3.92 | $4.50 | $3.74 | $3.87 | $3.50 | $4.50 |
| 82 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 55,464 | $0.66 | $0.66 | $1.00 | $0.65 | $0.65 | $0.59 | $0.50 |
| 83 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 1,886 | $6.32 | $4.48 | $6.50 | $4.69 | $4.42 | $4.00 | $6.00 |
| 84 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 51,534 | $0.63 | $0.66 | $1.00 | $0.66 | $0.65 | $0.59 | $0.50 |
| 85 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 11,966 | $0.84 | $1.53 | $0.55 | $1.33 | $0.74 | $1.50 | $0.50 |
| 86 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 106 | $7.50 | $7.84 | $7.50 | $14.36 | $7.74 | $7.00 | $13.00 |
| 87 | Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041) | EACH | 6 | $226.41 | $168.09 | $150.00 | $188.46 | $165.90 | $150.00 | $175.00 |
| 88 | Reflectorized pavement marking type I (Y)24"(solid)(090MIL) (666-7122) | LF | 254 | $3.00 | $7.28 | $7.50 | $9.75 | $7.19 | $6.50 | $12.00 |
| 89 | Pavement sler 6" (666-7347) | LF | 103,379 | $0.15 | $0.21 | $0.25 | $0.22 | $0.21 | $0.19 | $0.20 |
| 90 | Pavement sler 24" (666-7352) | LF | 360 | $1.02 | $2.24 | $2.50 | $2.87 | $2.21 | $2.00 | $3.00 |
| 91 | Pavement sler (arrow) (666-7353) | EACH | 6 | $100.00 | $33.62 | $30.00 | $46.98 | $33.18 | $30.00 | $65.00 |
| 92 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 50,316 | $0.65 | $0.61 | $0.55 | $0.60 | $0.60 | $0.54 | $0.50 |
| 93 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 7,021 | $0.79 | $0.67 | $0.60 | $0.64 | $0.66 | $0.60 | $0.50 |
| 94 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 46,042 | $0.66 | $0.61 | $0.55 | $0.61 | $0.60 | $0.54 | $0.50 |
| 95 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 742 | $4.00 | $4.15 | $4.50 | $4.39 | $4.09 | $3.70 | $5.00 |
| 96 | Bonding course (3007-7001) | GAL | 12,427 | $6.00 | $3.14 | $4.00 | $11.33 | $4.98 | $3.90 | $4.00 |
| 97 | Natural gas pipeline (7080-7001) | LF | 8,325 | $35.00 | $9.00 | $10.00 | $20.25 | $9.95 | $9.00 | $12.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 2, 2025. Compiled by Mirage Metrics.