TxDOT contract A00203223 bid tabulation
Removal And/Or Replacement And/Or Disposal, OLD ROBINSON DR (Old Robinson Rd @ Drain to Old Robinson Rd @ Drain). Let by Texas DOT on May 7, 2026, McLennan, Waco District. 6 bids received; low bid $578,158 by C & W Southern LLC, -14% against the engineer's estimate of $669,694.
- Owner
- Texas DOT
- Letting
- 07 MAY 2026
- Pay items
- 42
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | C & W Southern LLC | $578,158 | Low | -14% |
| 2 | Knife River Corporation - South | $579,658 | 0.0% | -13% |
| 3 | Bear Creek Contracting, LLC | $622,240 | +8.0% | -7.0% |
| 4 | Icos Management, LLC | $839,992 | +45% | +25% |
| 5 | Tucan Contracting, LLC | $862,810 | +49% | +29% |
| 6 | Hodges and Son Construction Company, Inc. | $906,866 | +57% | +35% |
Engineer's estimate: $669,694.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. C & W Southern LLC | 2. Knife River Corporation - South | 3. Bear Creek Contracting, LLC | 4. Icos Management, LLC | 5. Tucan Contracting, LLC | 6. Hodges and Son Construction Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 7 | $2,000.00 | $1,000.00 | $3,150.00 | $2,326.00 | $1,470.00 | $3,300.00 | $2,900.00 |
| 2 | Remove (6") TRT/untrt base & asphalt pavement (105-7026) | SY | 1,273 | $10.00 | $5.00 | $2.00 | $11.00 | $8.46 | $8.00 | |
| 3 | Excavation (roadway) (110-7001) | CY | 476 | $30.00 | $10.00 | $42.00 | $8.00 | $42.00 | $16.50 | $30.00 |
| 4 | Excavation (channel) (110-7002) | CY | 64 | $10.00 | $25.00 | $8.00 | $84.00 | $27.50 | $35.00 | |
| 5 | Embankment (final)(OC)(type B) (132-7003) | CY | 342 | $30.00 | $20.00 | $20.00 | $18.00 | $52.50 | $33.00 | $30.00 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 2,531 | $1.50 | $5.00 | $1.00 | $10.00 | $12.60 | $5.50 | $4.00 |
| 7 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 2,531 | $0.50 | $0.01 | $1.50 | $1.50 | $1.31 | $0.88 | $2.00 |
| 8 | Drill seed (permanent_rural_clay) (164-7010) | SY | 2,531 | $0.50 | $2.00 | $1.50 | $1.00 | $1.10 | $0.88 | $2.00 |
| 9 | Vegetative watering (168-7001) | TGL | 41 | $20.00 | $1.00 | $25.00 | $20.00 | $22.00 | $55.00 | $1.00 |
| 10 | FL BS (compacted in place)(type D GR 3)(final pos) (247-7189) | CY | 313 | $150.00 | $145.00 | $229.00 | $126.00 | $55.00 | $120.00 | |
| 11 | Emuls asphalt (BS or subgr TRT)(CSS-1H) (314-7004) | GAL | 2,167 | $8.50 | $1.00 | $4.00 | $10.50 | $11.00 | $15.00 | |
| 12 | Fog seal (CSS-1H) (315-7004) | GAL | 102 | $35.00 | $15.00 | $25.00 | $33.83 | $38.50 | $30.00 | |
| 13 | Asphalt (AC-20-5TR) (316-7007) | GAL | 356 | $22.00 | $11.00 | $20.00 | $24.00 | $23.43 | $30.00 | |
| 14 | Asphalt (CRS-2P) (316-7012) | GAL | 611 | $10.00 | $7.00 | $11.00 | $11.00 | $13.20 | $20.00 | |
| 15 | Aggregate (type-PD or PL, GR-4) (316-7258) | CY | 8 | $2,800.00 | $750.00 | $1,194.00 | $3,080.00 | $3,520.00 | $2,500.00 | |
| 16 | Aggregate (type-D or L,GR-3) (316-7278) | CY | 11 | $2,500.00 | $600.00 | $1,053.00 | $2,750.00 | $3,300.00 | $2,500.00 | |
| 17 | Cut & restore asphalt paving (400-7008) | SY | 98 | $200.00 | $150.00 | $100.00 | $173.00 | $231.00 | $328.03 | $140.00 |
| 18 | Cem stabil BKFL (400-7010) | CY | 163 | $250.00 | $250.00 | $250.00 | $180.00 | $294.00 | $330.00 | $300.00 |
| 19 | Trench excavation protection (402-7001) | LF | 44 | $40.00 | $14.00 | $8.00 | $12.00 | $16.50 | $5.00 | |
| 20 | Temporary special shoring (403-7001) | SF | 613 | $2.00 | $3.50 | $20.00 | $12.00 | $33.00 | $40.00 | |
| 21 | Riprap (stone protection)(12 in) (432-7041) | CY | 172 | $145.00 | $139.00 | $263.00 | $192.00 | $176.00 | $200.00 | |
| 22 | Rail (type T223) (450-7008) | LF | 100.40 | $250.00 | $200.00 | $233.00 | $504.00 | $198.00 | $160.00 | |
| 23 | Concrete box culvert (8 FT X 4 FT) (462-7021) | LF | 54 | $600.00 | $915.00 | $764.00 | $1,470.00 | $1,100.00 | $1,500.00 | |
| 24 | Concrete box culvert (10 FT X 5 FT) (462-7033) | LF | 64 | $800.00 | $1,050.00 | $1,286.00 | $2,100.00 | $1,485.00 | $1,800.00 | |
| 25 | Wingwall (PW - 1) (HW=7 FT) (466-7177) | EACH | 2 | $20,000 | $25,000 | $16,161 | $17,850 | $49,500 | $48,000 | |
| 26 | Set (type I)(S= 8 FT)(HW= 5 FT)(3:1)(C) (467-7183) | EACH | 4 | $15,000 | $10,700 | $9,000.00 | $2,100.00 | $12,100 | $18,000 | |
| 27 | Removing structure (wingwall) (496-7005) | EACH | 6 | $1,300.00 | $1,000.00 | $1,500.00 | $701.00 | $42.00 | $2,750.00 | $2,500.00 |
| 28 | Removing structure (box culvert) (496-7008) | LF | 138 | $100.00 | $40.00 | $159.00 | $40.00 | $42.00 | $220.00 | $200.00 |
| 29 | Mobilization (500-7001) | LS | 1 | $60,000 | $55,000 | $57,000 | $60,425 | $96,585 | $99,000 | $80,000 |
| 30 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $5,000.00 | $2,250.00 | $1,200.00 | $3,504.00 | $10,500 | $3,300.00 | $8,000.00 |
| 31 | Rock filter dams (install) (type 2) (506-7002) | LF | 152 | $10.00 | $38.00 | $15.00 | $10.50 | $49.50 | $1.00 | |
| 32 | Rock filter dams (remove) (506-7011) | LF | 152 | $1.00 | $15.00 | $4.00 | $5.25 | $19.80 | $1.00 | |
| 33 | Temporary sediment control fence (install) (506-7039) | LF | 1,490 | $4.00 | $2.50 | $6.90 | $5.00 | $2.10 | $5.50 | $1.00 |
| 34 | Temporary sediment control fence (remove) (506-7041) | LF | 1,490 | $1.00 | $1.00 | $1.50 | $3.00 | $1.10 | $1.10 | $1.00 |
| 35 | Metal W-beam guard fence (steel post) (540-7002) | LF | 75 | $30.00 | $31.00 | $37.00 | $47.25 | $33.00 | $32.00 | |
| 36 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 4 | $1,200.00 | $1,250.00 | $1,483.00 | $1,890.00 | $1,320.00 | $1,500.00 | |
| 37 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,200.00 | $1,250.00 | $1,483.00 | $1,785.00 | $1,320.00 | $1,500.00 | |
| 38 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,000.00 | $3,100.00 | $3,708.00 | $3,570.00 | $3,300.00 | $3,500.00 | |
| 39 | Wire fence (type C) (552-7003) | LF | 256 | $20.00 | $20.00 | $15.00 | $10.50 | $22.00 | $20.00 | |
| 40 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 2 | $20.00 | $22.00 | $163.00 | $52.50 | $22.00 | $45.00 | |
| 41 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 6 | $45.00 | $49.00 | $56.00 | $52.50 | $49.50 | $45.00 | |
| 42 | Install object marker assembly (OM-2Z)(WFLX)SRFLL(BI) (658-7260) | EACH | 4 | $65.00 | $70.00 | $156.00 | $255.00 | $71.50 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 7, 2026. Compiled by Mirage Metrics.