TxDOT contract A00206364 bid tabulation
Construct Pedestrian Infrastructure, Various (FM 2483 City Limits to Morgan's Pt Rd to Morgan's Pt Rd from FM 2483 to Sobrante). Let by Texas DOT on November 5, 2025, Bell, Waco District. 11 bids received; low bid $2,475,158 by Wellcraft Builders, -17% against the engineer's estimate of $2,991,266.
- Owner
- Texas DOT
- Letting
- 05 NOV 2025
- Pay items
- 86
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Wellcraft Builders | $2,475,158 | Low | -17% |
| 2 | 3LW Civil LLC | $2,659,504 | +7.0% | -11% |
| 3 | Ti-Zack Concrete, LLC | $2,695,529 | +9.0% | -10% |
| 4 | Scout 5 Construction LLC | $2,716,335 | +10% | -9.0% |
| 5 | Garret Shields Infrastructure | $2,834,397 | +15% | -5.0% |
| 6 | STX Civil | $2,839,408 | +15% | -5.0% |
| 7 | TTG Utilities, LP | $3,034,034 | +23% | +1.0% |
| 8 | Rise Up Construction LLC | $3,169,887 | +28% | +6.0% |
| 9 | Highway 19 Construction LLC | $3,224,368 | +30% | +8.0% |
| 10 | Grey Sky Construction LLC | $3,252,325 | +31% | +9.0% |
| 11 | E-Z Bel Construction, LLC | $4,058,325 | +64% | +36% |
Engineer's estimate: $2,991,266.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Wellcraft Builders | 2. 3LW Civil LLC | 3. Ti-Zack Concrete, LLC | 4. Scout 5 Construction LLC | 5. Garret Shields Infrastructure | 6. STX Civil |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 100.50 | $900.00 | $877.56 | $250.00 | $105.00 | $10,000 | $500.00 | $225.00 |
| 2 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 9 | $1,500.00 | $819.06 | $2,500.00 | $577.50 | $500.00 | $500.00 | $1,000.00 |
| 3 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 2 | $2,500.00 | $1,170.08 | $3,500.00 | $2,625.00 | $1,000.00 | $1,500.00 | $1,600.00 |
| 4 | Removing concrete (driveways) (104-7011) | SY | 420 | $25.00 | $19.04 | $30.00 | $30.13 | $25.00 | $40.00 | $30.00 |
| 5 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 22 | $35.00 | $21.19 | $50.00 | $38.35 | $25.00 | $40.00 | $30.00 |
| 6 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 110 | $15.00 | $8.83 | $25.00 | $7.67 | $10.00 | $40.00 | $10.00 |
| 7 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052) | SY | 1,782 | $20.00 | $10.11 | $15.00 | $23.67 | $5.00 | $30.00 | $15.00 |
| 8 | Excavation (channel) (110-7002) | CY | 531 | $40.00 | $23.40 | $35.00 | $79.44 | $15.00 | $40.00 | $55.00 |
| 9 | Embankment (final)(OC)(type B) (132-7003) | CY | 507 | $60.00 | $40.95 | $40.00 | $83.20 | $100.00 | $30.00 | $25.00 |
| 10 | Furn & place topsoil (4") (160-7002) | SY | 17,031 | $4.00 | $3.21 | $4.25 | $2.48 | $3.14 | $5.00 | $5.00 |
| 11 | Block sodding (162-7002) | SY | 17,031 | $8.00 | $7.51 | $4.39 | $5.25 | $4.95 | $9.00 | $7.00 |
| 12 | Vegetative watering (168-7001) | TGL | 140.10 | $50.00 | $17.55 | $75.12 | $1.05 | $15.00 | $100.00 | $100.00 |
| 13 | Flexible pavement structure repair(8") (351-7007) | SY | 207 | $220.00 | $286.85 | $265.20 | $131.25 | $70.00 | $100.00 | $250.00 |
| 14 | Drilled shaft (30 in) (416-7005) | LF | 160 | $200.00 | $345.17 | $385.00 | $210.00 | $600.00 | $400.00 | $250.00 |
| 15 | Class C concrete (collar) (420-7061) | EACH | 6 | $1,500.00 | $585.04 | $1,250.00 | $1,890.00 | $259.17 | $1,000.00 | $1,300.00 |
| 16 | Class C concrete (miscellaneous) (420-7067) | CY | 16 | $1,250.00 | $819.06 | $1,250.00 | $767.92 | $295.19 | $2,000.00 | $1,000.00 |
| 17 | Riprap (concrete)(6 in) (432-7003) | CY | 139 | $1,000.00 | $585.04 | $702.66 | $767.92 | $267.55 | $1,000.00 | $650.00 |
| 18 | Rail (handrail)(type F) (450-7063) | LF | 70 | $200.00 | $146.26 | $219.26 | $173.25 | $134.76 | $200.00 | $300.00 |
| 19 | RC pipe (CL III)(12 in) (464-7001) | LF | 407 | $75.00 | $86.45 | $73.66 | $57.75 | $27.64 | $80.00 | $80.00 |
| 20 | RC pipe (CL III)(18 in) (464-7003) | LF | 242 | $120.00 | $88.66 | $77.75 | $66.15 | $32.49 | $100.00 | $110.00 |
| 21 | RC pipe (CL III)(24 in) (464-7005) | LF | 117 | $130.00 | $106.61 | $113.67 | $93.45 | $49.83 | $130.00 | $140.00 |
| 22 | RC pipe (arch)(CL III)(des 4) (464-7043) | LF | 64 | $310.00 | $573.34 | $278.04 | $357.00 | $367.40 | $400.00 | $380.00 |
| 23 | Inlet (complete)(PSL)(RC)(3FTX3FT) (465-7070) | EACH | 2 | $6,000.00 | $5,674.89 | $6,891.40 | $6,300.00 | $3,355.00 | $8,000.00 | $8,000.00 |
| 24 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 1 | $8,000.00 | $5,908.90 | $6,989.68 | $6,825.00 | $3,575.00 | $8,000.00 | $8,750.00 |
| 25 | Inlet (complete)(PSL)(FG)(5FTX6FT-4FTX4FT) (465-7138) | EACH | 1 | $8,500.00 | $9,711.66 | $14,274 | $8,400.00 | $7,150.00 | $10,000 | $15,000 |
| 26 | Headwall (CH - PW - 0) (diameter= 12 in) (466-7097) | EACH | 1 | $6,500.00 | $4,095.28 | $10,500 | $2,205.00 | $565.59 | $2,000.00 | $12,000 |
| 27 | Headwall (CH - PW - A - 0) (des= 4) (466-7130) | EACH | 1 | $14,000 | $7,020.48 | $13,528 | $7,560.00 | $797.05 | $5,000.00 | $25,000 |
| 28 | Set (type II) (12 in) (RCP) (6: 1) (P) (467-7292) | EACH | 12 | $1,000.00 | $672.80 | $2,142.08 | $1,249.50 | $393.25 | $800.00 | $1,500.00 |
| 29 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 6 | $1,200.00 | $819.06 | $1,853.93 | $1,365.00 | $544.50 | $1,500.00 | $1,800.00 |
| 30 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 1 | $2,000.00 | $1,345.59 | $2,850.00 | $1,995.00 | $907.50 | $3,000.00 | $2,000.00 |
| 31 | Grate & frame (471-7003) | EACH | 39 | $2,000.00 | $1,603.01 | $2,591.52 | $2,404.77 | $1,777.63 | $1,500.00 | $2,250.00 |
| 32 | Adjusting manholes (479-7001) | EACH | 1 | $1,000.00 | $2,340.16 | $1,950.00 | $843.60 | $500.00 | $1,000.00 | $2,500.00 |
| 33 | Adjusting manholes (water valve box) (479-7007) | EACH | 19 | $500.00 | $585.04 | $975.00 | $444.00 | $500.00 | $600.00 | $300.00 |
| 34 | Removing structure (inlet) (496-7002) | EACH | 1 | $1,000.00 | $1,170.08 | $1,750.00 | $1,260.00 | $500.00 | $1,000.00 | $2,500.00 |
| 35 | Removing structure (set) (496-7004) | EACH | 23 | $700.00 | $409.53 | $500.00 | $183.75 | $500.00 | $100.00 | $500.00 |
| 36 | Removing structure (pipe) (496-7007) | LF | 518 | $50.00 | $17.55 | $25.00 | $15.75 | $25.00 | $10.00 | $25.00 |
| 37 | Mobilization (500-7001) | LS | 1 | $225,000 | $153,409 | $122,892 | $196,644 | $150,000 | $200,000 | $198,000 |
| 38 | Barricades, signs and traffic handling (502-7001) | MO | 14 | $4,000.00 | $5,850.40 | $12,339 | $2,625.00 | $0.01 | $5,000.00 | $2,800.00 |
| 39 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $33,581 | $8,500.00 | $1.05 | $45,000 | $1,000.00 | $10,000 |
| 40 | TMA (stationary) (505-7001) | DAY | 193 | $200.00 | $351.02 | $0.10 | $1.05 | $140.25 | $300.00 | $150.00 |
| 41 | TMA (mobile operation) (505-7002) | HR | 40 | $100.00 | $117.01 | $0.10 | $1.05 | $17.60 | $100.00 | $60.00 |
| 42 | Rock filter dams (install) (type 3) (506-7003) | LF | 65 | $40.00 | $40.95 | $0.10 | $0.11 | $133.64 | $40.00 | $250.00 |
| 43 | Rock filter dams (remove) (506-7011) | LF | 65 | $15.00 | $11.70 | $0.10 | $0.11 | $0.01 | $10.00 | $10.00 |
| 44 | Temporary sediment control fence (install) (506-7039) | LF | 671 | $2.00 | $4.10 | $0.10 | $0.11 | $2.10 | $5.00 | $6.00 |
| 45 | Temporary sediment control fence (remove) (506-7041) | LF | 671 | $6.00 | $1.17 | $0.10 | $0.11 | $0.01 | $1.00 | $1.00 |
| 46 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 53 | $9.00 | $5.27 | $0.10 | $0.11 | $2.28 | $6.00 | $10.00 |
| 47 | Biodegradable erosion control logs (remove) (506-7046) | LF | 53 | $3.00 | $1.76 | $0.10 | $0.11 | $0.01 | $1.00 | $1.00 |
| 48 | Concrete curb (type II) (529-7002) | LF | 356 | $40.00 | $18.87 | $40.00 | $59.27 | $15.00 | $40.00 | $50.00 |
| 49 | Concrete curb & gutter (type II) (529-7009) | LF | 16 | $50.00 | $33.32 | $75.00 | $59.27 | $45.00 | $50.00 | $65.00 |
| 50 | Driveways (concrete) (hes) (530-7007) | SY | 1,629 | $130.00 | $117.39 | $105.00 | $121.10 | $49.72 | $120.00 | $155.00 |
| 51 | Driveways (ACP) (530-7010) | SY | 189 | $100.00 | $190.44 | $178.80 | $131.25 | $34.93 | $120.00 | $160.00 |
| 52 | Concrete sidewalks (4") (531-7001) | SY | 8,075 | $95.00 | $69.36 | $74.63 | $100.88 | $33.66 | $90.00 | $85.00 |
| 53 | Curb ramps (type 1) (531-7005) | EACH | 5 | $2,500.00 | $2,632.68 | $1,857.51 | $2,869.01 | $375.73 | $3,000.00 | $1,800.00 |
| 54 | Curb ramps (type 7) (531-7010) | EACH | 13 | $2,500.00 | $2,749.69 | $1,542.41 | $2,869.01 | $567.60 | $3,000.00 | $2,000.00 |
| 55 | Curb ramps (type 21) (531-7013) | EACH | 3 | $2,500.00 | $2,925.20 | $2,466.31 | $2,869.01 | $775.50 | $3,000.00 | $2,500.00 |
| 56 | Concrete sidewalks (special) (531-7025) | SY | 1,312 | $225.00 | $100.06 | $194.11 | $191.98 | $134.28 | $150.00 | $200.00 |
| 57 | Relocate existing mailbox (560-7012) | EACH | 11 | $380.00 | $292.52 | $350.00 | $472.50 | $1,000.00 | $500.00 | $300.00 |
| 58 | In RD IL (type SA) 20T-4 (150W EQ) LED (610-7034) | EACH | 20 | $3,500.00 | $4,563.31 | $4,700.00 | $4,869.38 | $6,000.00 | $5,000.00 | $5,000.00 |
| 59 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 5,689 | $16.00 | $11.70 | $24.00 | $21.00 | $9.90 | $16.00 | $21.50 |
| 60 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 110 | $25.00 | $38.61 | $60.00 | $48.09 | $34.76 | $30.00 | $50.00 |
| 61 | Electrical conductor (no.6) bare (620-7009) | LF | 6,104 | $3.00 | $2.57 | $2.20 | $2.15 | $2.40 | $2.10 | $3.00 |
| 62 | Electrical conductor (no.6) insulated (620-7010) | LF | 12,208 | $3.00 | $2.81 | $3.00 | $2.78 | $2.55 | $2.50 | $3.00 |
| 63 | Ground box type D (162922)W/apron (624-7008) | EACH | 21 | $1,800.00 | $1,491.85 | $1,250.00 | $1,449.00 | $1,402.50 | $2,600.00 | $1,500.00 |
| 64 | Elc SRV type A 120/240 060(NS)SS(E)SP(U) (628-7010) | EACH | 2 | $7,000.00 | $11,701 | $8,500.00 | $6,247.50 | $15,000 | $9,000.00 | $6,200.00 |
| 65 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 4 | $850.00 | $643.54 | $1,197.69 | $472.50 | $401.25 | $800.00 | $1,200.00 |
| 66 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 8 | $700.00 | $672.80 | $650.00 | $472.50 | $238.19 | $500.00 | $250.00 |
| 67 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 1 | $100.00 | $157.96 | $80.00 | $472.50 | $30.25 | $100.00 | $45.00 |
| 68 | Remove delin & object marker assms (658-7078) | EACH | 1 | $25.00 | $146.26 | $25.00 | $472.50 | $100.00 | $100.00 | $1.00 |
| 69 | Pavement sler 4" (666-7346) | LF | 155 | $1.00 | $0.35 | $0.60 | $1.05 | $0.33 | $1.00 | $0.65 |
| 70 | Pavement sler 8" (666-7348) | LF | 50 | $2.00 | $0.70 | $0.95 | $2.10 | $0.66 | $1.00 | $0.90 |
| 71 | Pavement sler 24" (666-7352) | LF | 375 | $5.00 | $2.11 | $1.20 | $6.30 | $1.98 | $1.50 | $1.25 |
| 72 | Pavement sler (arrow) (666-7353) | EACH | 2 | $50.00 | $58.50 | $30.00 | $105.00 | $55.00 | $32.00 | $50.00 |
| 73 | Pavement sler (word) (666-7354) | EACH | 2 | $50.00 | $58.50 | $30.00 | $105.00 | $55.00 | $32.00 | $50.00 |
| 74 | Prefabricated PM type C (W)(4")(solid) (668-7076) | LF | 155 | $5.00 | $2.93 | $6.00 | $6.30 | $2.75 | $7.00 | $6.10 |
| 75 | Prefabricated PM type C (W)(8")(solid) (668-7084) | LF | 50 | $7.00 | $5.85 | $8.40 | $8.40 | $5.50 | $9.00 | $7.80 |
| 76 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 375 | $18.00 | $17.55 | $15.60 | $17.33 | $16.50 | $20.00 | $5.00 |
| 77 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 2 | $300.00 | $321.77 | $276.00 | $420.00 | $302.50 | $300.00 | $100.00 |
| 78 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 2 | $300.00 | $351.02 | $336.00 | $525.00 | $330.00 | $350.00 | $100.00 |
| 79 | Eliminating existing PM & markers (24") (677-7008) | LF | 38 | $10.00 | $5.85 | $3.60 | $78.75 | $5.50 | $5.00 | $2.00 |
| 80 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 2 | $20.00 | $87.76 | $84.00 | $105.00 | $82.50 | $100.00 | $50.00 |
| 81 | Eliminating existing PM & markers (word) (677-7015) | EACH | 2 | $20.00 | $87.76 | $84.00 | $105.00 | $82.50 | $100.00 | $50.00 |
| 82 | Pavement surface preparation for marking (4") (678-7001) | LF | 155 | $1.00 | $0.18 | $0.30 | $0.21 | $0.17 | $0.50 | $0.85 |
| 83 | Pavement surface preparation for marking (8") (678-7004) | LF | 50 | $1.00 | $0.35 | $0.41 | $0.32 | $0.33 | $0.50 | $0.85 |
| 84 | Pavement surface preparation for marking (24") (678-7008) | LF | 375 | $3.00 | $1.05 | $1.20 | $2.10 | $0.99 | $1.25 | $1.50 |
| 85 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 2 | $35.00 | $23.40 | $26.40 | $26.25 | $25.00 | $28.00 | $50.00 |
| 86 | Pavement surface preparation for marking (word) (678-7016) | EACH | 2 | $35.00 | $23.40 | $26.40 | $26.25 | $25.00 | $28.00 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.