36" conc. pipe, VDOT 302SD20-0059

Low bidders on VDOT contracts carried a median of $1,000.00 per LF for this item, over the 24 months to 28 OCT 2026, across 3 low bids. Half of all 10 bids fell between $396.95 and $961.24.

Owner
Virginia DOT
Item
302SD20-0059
Unit
LF
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 1362 on lettings from 29 JAN 2002 to 15 DEC 2021 (274 bids); 302SD20-0059 on lettings from 22 OCT 2025 to 27 MAY 2026 (10 bids). They are combined here into one trend.

$1,000.00Low bidder's median, per LF
$605.00Median of all bids, per LF
3Contracts in the window

By year of letting

36" conc. pipe, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200266$79.0018$80.00
20031413$77.1937$80.00
200499$100.0022$101.00
200577$100.0014$119.00
200655$145.7915$125.00
200755$105.0015$125.00
200855$126.7015$130.00
200944$96.6012$99.41
201044$127.3212$121.65
201154$115.5014$119.08
201244$157.4412$167.50
201333$90.009$103.19
201599$162.0226$201.36
201633$188.957$188.95
201766$278.0218$266.50
201811$148.003$260.74
201933$122.757$209.00
202044$279.009$255.00
202133$235.718$245.15
202511$1,000.005$800.00
202622$705.005$410.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Salem18$127.5052$135.00
Northern Virginia17$120.0051$153.68
Staunton20$100.0051$104.00
Bristol11$96.0029$103.31
Hampton Roads10$153.5027$176.20
Fredericksburg8$150.1824$173.50
Lynchburg7$115.0023$105.00
Richmond6$117.2516$117.25
Culpeper4$123.8510$123.85
36" conc. pipe, VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (LF)Low bidsLow-bid median
1 to 3025$171.00
35 to 6625$100.00
66 to 14025$120.00
157 to 1,62226$100.00
36" conc. pipe, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
General Excavation, Inc.157 (47%)
Curtis Contracting, Inc.94 (44%)
Sowers Construction Co., Inc.84 (50%)
Martin and Gass, Incorporated54 (80%)
W. C. English, Incorporated73 (43%)
Arthur Construction Co., Inc.53 (60%)
36" conc. pipe, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
27 MAY 2026C0000113412C01BFredericksburg207$1,000.00$620.444Allan Myers Va, Inc.VDOT
04 FEB 2026C000115407C01BRichmond445$410.00$410.001J. R. Caskey, Inc.VDOT
22 OCT 2025C0000127769N01Northern Virginia1$1,000.00$800.005Arthur Construction Co., Inc.VDOT
15 DEC 2021C0000017817C01Bristol23$306.57$263.282W-L Construction & Paving, Inc.VDOT
17 NOV 2021C0000106670C01Fredericksburg370$172.00$238.303J. L. Kent & Sons, Inc.VDOT
20 JAN 2021C0000109481C01Hampton Roads8$235.71$252.003Henry S. Branscome, L.L.C.VDOT
22 JUL 2020C0000109440C01Bristol140$175.00$201.992Jones Road & Bridge, Inc.VDOT
22 APR 2020C0000107061C01Salem94$255.00$255.003Kanawha Stone Company, Inc.VDOT
25 MAR 2020C0000018003C01Staunton100$303.00$276.502General Excavation, Inc.VDOT
22 JAN 2020C000111370C01BSalem16$1,150.00$1,075.002Allegheny Construction Company, Inc.VDOT
18 DEC 2019C0000097688C01Richmond30$122.75$200.003Howard Brothers Contractor, Inc.VDOT
18 DEC 2019C0000108906C01Salem60$209.00$245.502Branch Civil, Inc.VDOT
20 MAR 2019C000114693N01Culpeper24$121.00$210.502Commonwealth Excavating, Inc.VDOT
28 MAR 2018C0000008753C01Salem334$148.00$260.743Kanawha Stone Company, Inc.VDOT
25 OCT 2017C0000105893M01Fredericksburg4$279.45$279.453J. L. Kent & Sons, Inc.VDOT
Latest VDOT contracts carrying 36" conc. pipe

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way