Gravel borrow including haul, WSDOT
Low bidders on WSDOT contracts carried a median of $15.25 per TON for this item, from 29 MAR 2000 to 23 FEB 2023, across 100 low bids. Half of all 645 bids fell between $11.50 and $25.38.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- TON
- Data through
- 07 OCT 2026
WSDOT prints this item as “GRAVEL BORROW INCL. HAUL”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 2 | 2 | $10.50 | 9 | $12.00 |
| 2002 | 3 | 3 | $10.00 | 13 | $10.00 |
| 2003 | 2 | 2 | $85.50 | 10 | $31.35 |
| 2004 | 6 | 6 | $8.75 | 40 | $12.10 |
| 2005 | 4 | 4 | $5.25 | 26 | $10.70 |
| 2006 | 3 | 3 | $7.50 | 12 | $10.50 |
| 2007 | 7 | 7 | $10.00 | 41 | $15.00 |
| 2008 | 9 | 9 | $25.00 | 63 | $14.25 |
| 2009 | 7 | 6 | $11.32 | 48 | $11.07 |
| 2010 | 6 | 4 | $13.30 | 40 | $12.00 |
| 2011 | 4 | 3 | $12.00 | 26 | $13.00 |
| 2012 | 8 | 8 | $34.00 | 54 | $20.88 |
| 2013 | 6 | 5 | $20.00 | 40 | $18.75 |
| 2014 | 4 | 4 | $14.57 | 38 | $16.37 |
| 2015 | 3 | 3 | $30.00 | 22 | $22.45 |
| 2016 | 9 | 9 | $22.00 | 56 | $23.50 |
| 2017 | 3 | 3 | $30.00 | 19 | $20.00 |
| 2018 | 3 | 3 | $22.50 | 16 | $17.00 |
| 2019 | 3 | 3 | $21.00 | 15 | $31.01 |
| 2020 | 2 | 2 | $20.88 | 12 | $20.50 |
| 2021 | 5 | 5 | $30.25 | 20 | $31.95 |
| 2022 | 3 | 3 | $35.00 | 10 | $35.00 |
| 2023 | 3 | 3 | $28.00 | 15 | $40.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 61 | $14.00 | 411 | $15.80 |
| SWR region | 16 | $14.56 | 113 | $14.97 |
| OR region | 21 | $24.50 | 112 | $24.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 10 to 485.90 | 25 | $34.00 |
| 490 to 1,900 | 25 | $20.00 |
| 1,930 to 6,464 | 25 | $15.00 |
| 6,810 to 349,690 | 25 | $10.30 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Wilder Construction Company | 25 | 10 (40%) |
| Tri-State Construction, Inc. | 26 | 8 (31%) |
| Granite Construction Company | 16 | 4 (25%) |
| Midmountain Contractors, Inc. | 12 | 4 (33%) |
| Strider Construction Co., Inc. | 11 | 4 (36%) |
| Mowat Construction Company | 10 | 4 (40%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 23 FEB 2023 | 009932 | NWR region | 190 | $28.00 | $50.00 | $50.00 | 4 | Faber Construction Corp. | WSDOT |
| 19 JAN 2023 | 009911 | OR region | 1,000 | $25.00 | $36.59 | $40.00 | 7 | Skycorp, LTD | WSDOT |
| 11 JAN 2023 | 009909 | SWR region | 485.90 | $50.00 | $54.00 | $40.00 | 4 | Thompson Bros. Excavating, Inc | WSDOT |
| 06 APR 2022 | 009795 | SWR region | 2,380 | $28.00 | $30.00 | $25.00 | 7 | SB Structures, LLC | WSDOT |
| 09 MAR 2022 | 009774 | OR region | 1,050 | $35.00 | $38.00 | $35.00 | 2 | Kraemer North America, LLC. | WSDOT |
| 12 JAN 2022 | 009758 | NWR region | 148 | $75.00 | $75.00 | $40.00 | 1 | Award Construction, Inc. | WSDOT |
| 15 DEC 2021 | 009742 | NWR region | 6,090 | $45.00 | $36.00 | $30.00 | 4 | Granite Construction Company | WSDOT |
| 21 APR 2021 | 009662 | NWR region | 3,450 | $33.65 | $36.83 | $25.00 | 4 | Scarsella Bros., Inc. | WSDOT |
| 21 APR 2021 | 009681 | OR region | 4,440 | $30.25 | $27.57 | $22.00 | 4 | Scarsella Bros., Inc. | WSDOT |
| 14 APR 2021 | 009673 | OR region | 52 | $24.50 | $34.00 | $30.00 | 4 | Skycorp, LTD | WSDOT |
| 24 MAR 2021 | 009636 | OR region | 82 | $20.00 | $73.50 | $48.00 | 4 | Graham Contracting, LTD. | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 5,350 | $11.75 | $17.75 | $24.00 | 8 | Interwest Construction, Inc. | WSDOT |
| 05 FEB 2020 | 009517 | OR region | 120 | $30.00 | $51.00 | $21.00 | 4 | Skycorp, LTD | WSDOT |
| 10 APR 2019 | 009419 | SWR region | 920 | $20.00 | $28.00 | $30.00 | 8 | Farline Bridge, Incorporated | WSDOT |
| 06 MAR 2019 | 009392 | OR region | 1,900 | $70.00 | $102.82 | $25.00 | 3 | Dirt and Aggregate Interchange | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WSDOT letting of 07 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.