ALDOT contract 20250926027 bid tabulation
ACCESS MANAGEMENT AND TRAFFIC SIGNAL UPGRADES ON DAUPHIN STREET FROM A POINT WEST OF THE I-65 INTERCHANGE TO THE INTERSECTION OF SAGE AVENUE IN MOBILE. Let by Alabama DOT on September 26, 2025, Mobile, 0901. 3 bids received; low bid $9,292,727 by Wiregrass Construction Company, Inc..
- Owner
- Alabama DOT
- Letting
- 26 SEP 2025
- Pay items
- 190
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Wiregrass Construction Company, Inc. | $9,292,727 | Low |
| 2 | McElhenney Construction Co., LLC | $10,771,357 | +16% |
| 3 | Apac-Alabama, Inc. | $11,128,252 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Wiregrass Construction Company, Inc. | 2. McElhenney Construction Co., LLC | 3. Apac-Alabama, Inc. |
|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (maximum allowable bid $ 8,000.00 per acre) (approximately 2 acres) (201A002) | LS | 1 | $16,000 | $16,000 | $16,000 |
| 0020 | Removing concrete sidewalk (206C000) | SY | 181 | $15.39 | $21.97 | $26.20 |
| 0030 | Removing concrete pavement (206C001) | SY | 1,084 | $15.38 | $41.18 | $8.75 |
| 0040 | Removing concrete slope paving (206C002) | SY | 894 | $19.23 | $47.06 | $5.30 |
| 0050 | Removing temporary asphalt pavement (206C026) | SY | 1,400 | $7.69 | $16.47 | $8.08 |
| 0060 | Removing pipe (206D000) | LF | 316 | $19.23 | $47.06 | $17.76 |
| 0070 | Removing guardrail (206D001) | LF | 160 | $3.68 | $4.13 | $4.37 |
| 0080 | Removing curb (206D002) | LF | 3,944 | $9.61 | $21.05 | $17.80 |
| 0090 | Removing curb and gutter (206D003) | LF | 4,343 | $9.61 | $23.39 | $17.80 |
| 0100 | Removing gutter (206D005) | LF | 341 | $9.61 | $24.71 | $17.80 |
| 0110 | Removing utility lines (206D030) | LF | 581 | $15.75 | $29.65 | $15.78 |
| 0120 | Removing inlets (206E001) | EACH | 21 | $1,281.95 | $1,253.99 | $755.12 |
| 0130 | Removing junction boxes (206E002) | EACH | 2 | $1,281.76 | $1,482.40 | $782.78 |
| 0140 | Removing trees (206E006) | EACH | 35 | $961.46 | $412.63 | $679.93 |
| 0150 | Removing guardrail end anchor (all type) (206E008) | EACH | 2 | $315.00 | $353.69 | $374.43 |
| 0160 | Removing inlets (partial) (206E042) | EACH | 2 | $525.00 | $1,482.40 | $2,740.40 |
| 0170 | Unclassified excavation (210A000) | CY | 3,750 | $44.30 | $55.33 | $54.26 |
| 0180 | Borrow excavation (loose truckbed measurement)(A-2-4(0) or A-4(0) ) (210D022) | CY | 1,309 | $37.80 | $46.34 | $57.82 |
| 0190 | Borrow excavation (A-3 or better) loose truckbed measure (210D024) | CY | 788 | $37.80 | $57.76 | $57.82 |
| 0200 | Structure excavation (214A000) | CY | 125 | $44.31 | $17.21 | $12.24 |
| 0210 | Foundation backfill, commercial (214B001) | CY | 190 | $122.00 | $150.44 | $65.73 |
| 0220 | Roadbed processing (230A000) | RBST | 45 | $1,224.53 | $926.44 | $541.35 |
| 0230 | Crushed aggregate base course, type B, plant mixed, 6" compacted thickness (301A012) | SY | 8,299 | $36.68 | $42.77 | $34.45 |
| 0240 | Bituminous treatment A (401A000) | SY | 7,838 | $1.61 | $1.27 | $1.48 |
| 0250 | Tack coat (405A000) | GAL | 4,263 | $4.72 | $8.88 | $4.75 |
| 0260 | Planing existing pavement (approximately 1.10" thru 2.0" thick) (408A052) | SY | 66,030 | $3.10 | $3.00 | $2.74 |
| 0270 | Superpave bituminous concrete wearing surface layer, 1/2" maximum aggregate size mix, esal range C/D (424A360) | TON | 5,951 | $150.02 | $153.56 | $155.52 |
| 0280 | Superpave bituminous concrete wearing surface layer, widening, 1/2" maximum aggregate size mix, esal range C/D (424A369) | TON | 125 | $382.35 | $176.41 | $213.89 |
| 0290 | Superpave bituminous concrete upper binder layer, 1" maximum aggregate size mix, esal range C/D (424B651) | TON | 771 | $182.13 | $167.52 | $210.34 |
| 0300 | Superpave bituminous concrete upper binder layer, patching, 1" maximum aggregate size mix, esal range C/D (424B655) | TON | 75 | $652.94 | $167.52 | $319.76 |
| 0310 | Superpave bituminous concrete upper binder layer, leveling, 1/2" maximum aggregate size mix, esal range C/D (424B657) | TON | 100 | $179.63 | $202.43 | $213.60 |
| 0320 | Superpave bituminous concrete lower binder layer, 1" maximum aggregate size mix, esal range C/D (424B681) | TON | 567 | $224.73 | $167.52 | $218.53 |
| 0330 | Aggregate surfacing (aldot #467 or #57) (430B000) | TON | 125 | $86.65 | $102.42 | $120.19 |
| 0340 | Aggregate surfacing (1" down, crusher run) (430B043) | TON | 125 | $85.39 | $101.15 | $119.00 |
| 0350 | 15" roadway pipe (class 3 R.C.) (extension) (530A100) | LF | 12 | $374.33 | $278.25 | $473.08 |
| 0360 | 18" roadway pipe (class 3 R.C.) (extension) (530A101) | LF | 44 | $577.31 | $211.19 | $478.58 |
| 0370 | 18" span, 11" rise roadway pipe (class 3 R.C.) (extension) (530B011) | LF | 4 | $614.24 | $465.74 | $770.47 |
| 0380 | 36" span, 23" rise roadway pipe (class 3 R.C.) (extension) (530B014) | LF | 4 | $743.78 | $595.20 | $828.94 |
| 0390 | 18" storm sewer pipe (class 3 R.C.) (533A098) | LF | 379 | $103.67 | $151.43 | $102.58 |
| 0400 | Cleaning existing pipe (less than or equal to 48" horizontal opening) (534E001) | LF | 636 | $26.25 | $29.47 | $29.72 |
| 0410 | Mobilization (600A000) | LS | 1 | $688,275 | $1,003,866 | $1,114,059 |
| 0420 | Right of way markers (602A000) | EACH | 9 | $539.47 | $486.11 | $597.63 |
| 0430 | Filter blanket, geotextile (610D003) | SY | 1,000 | $8.51 | $5.53 | $5.50 |
| 0440 | Slope paving (614A000) | CY | 321 | $418.95 | $648.43 | $678.58 |
| 0450 | Concrete sidewalk, 4" thick (618A000) | SY | 114 | $71.40 | $117.90 | $136.77 |
| 0460 | Concrete driveway, 6" thick (includes wire mesh) (618B003) | SY | 1,140 | $84.00 | $117.90 | $141.10 |
| 0470 | Detectable warning surface (618C001) | SF | 460 | $19.35 | $76.63 | $39.23 |
| 0480 | Curb ramp (618D000) | SY | 318 | $404.25 | $294.74 | $293.43 |
| 0490 | Minor structure concrete (620A000) | CY | 17 | $1,575.00 | $1,414.75 | $1,700.06 |
| 0500 | Junction boxes, type 1 or 1P (621A011) | EACH | 2 | $3,987.73 | $4,979.31 | $7,099.81 |
| 0510 | Junction boxes, type partial (621A057) | EACH | 2 | $2,940.00 | $3,536.87 | $3,268.78 |
| 0520 | Inlets, type B (621C001) | EACH | 2 | $4,718.56 | $6,541.77 | $6,505.49 |
| 0530 | Inlets, type S1 or S3 (1 wing) (621C015) | EACH | 7 | $6,393.11 | $7,513.28 | $7,758.83 |
| 0540 | Inlets, type S1 or S3 (2 wing) (621C017) | EACH | 9 | $6,963.59 | $9,838.56 | $8,924.38 |
| 0550 | Inlets, type "special" (621C030) | EACH | 1 | $4,725.00 | $7,924.48 | $10,322 |
| 0560 | Inlets, type S4 (2 wing) (modified) (621C099) | EACH | 1 | $5,775.00 | $12,969 | $19,389 |
| 0570 | Inlets, type PD-6 (621C110) | EACH | 5 | $15,232 | $15,648 | $7,269.09 |
| 0580 | Inlet units, type S1 or S3 (621D015) | EACH | 9 | $1,094.36 | $1,103.99 | $594.32 |
| 0590 | Inlet units, type PD-6 (621D110) | EACH | 2 | $2,012.61 | $2,030.33 | $594.33 |
| 0600 | Concrete gutter (modified) (623A004) | LF | 75 | $31.50 | $235.79 | $124.01 |
| 0610 | Concrete curb, type N (623B000) | LF | 7,397 | $26.25 | $31.83 | $30.27 |
| 0620 | Combination curb & gutter, type C (modified) (623C003) | LF | 7,112 | $30.45 | $33.01 | $36.59 |
| 0630 | Steel beam guardrail, class A, type 2 (630A001) | LF | 254 | $27.30 | $30.65 | $32.45 |
| 0640 | Guardrail end anchor, type 20 series (630C050) | EACH | 1 | $3,780.00 | $4,244.24 | $4,493.09 |
| 0650 | 6 inch ductile iron water main laid (641A612) | LF | 10 | $210.00 | $349.50 | $249.62 |
| 0660 | 8 inch P.V.C. water main laid (641A748) | LF | 612 | $110.25 | $109.29 | $131.05 |
| 0670 | Ductile iron fittings (641C500) | LB | 738 | $10.50 | $21.79 | $12.48 |
| 0680 | Fire hydrant (641D500) | EACH | 7 | $9,292.50 | $8,045.63 | $11,046 |
| 0690 | 6 inch gate valve with box (641J516) | EACH | 1 | $2,362.50 | $2,786.76 | $2,808.19 |
| 0700 | 8 inch gate valve with box (641J518) | EACH | 1 | $3,307.50 | $3,963.14 | $3,931.45 |
| 0710 | Concrete for water mains (thrust blocks) (641L500) | CY | 5 | $498.75 | $704.32 | $592.84 |
| 0720 | 6 inch retainer gland (641M512) | EACH | 3 | $210.00 | $264.38 | $249.62 |
| 0730 | 8 inch retainer gland (641M514) | EACH | 31 | $262.50 | $315.16 | $312.02 |
| 0740 | 8 inch X 8 inch tapping valve and sleeve (641O520) | EACH | 2 | $11,025 | $12,058 | $13,105 |
| 0750 | 8 inch line stop (641T512) | EACH | 4 | $16,800 | $21,384 | $19,969 |
| 0760 | Manhole frame and cover reset (645K500) | EACH | 3 | $3,150.00 | $1,598.33 | $3,744.24 |
| 0770 | Topsoil (650A000) | CY | 522 | $65.67 | $47.31 | $49.90 |
| 0780 | Mowing (652C000) | ACRE | 8 | $288.75 | $324.21 | $374.42 |
| 0790 | Solid sodding (centipede) (654A003) | SY | 16,238 | $5.25 | $5.89 | $7.49 |
| 0800 | Temporary seeding (665A000) | ACRE | 8 | $420.00 | $471.58 | $1,497.70 |
| 0810 | Temporary mulching (665B001) | TON | 8 | $498.75 | $560.00 | $499.23 |
| 0820 | Temporary pipe (665C010) | LF | 152 | $72.55 | $55.71 | $67.08 |
| 0830 | Polyethylene (665E000) | SY | 5,500 | $2.10 | $2.36 | $3.31 |
| 0840 | Hay bales (665F000) | EACH | 100 | $11.81 | $13.26 | $14.98 |
| 0850 | Sand bags (665G000) | EACH | 100 | $8.40 | $9.43 | $39.33 |
| 0860 | Silt fence (665J002) | LF | 5,160 | $4.20 | $4.72 | $14.98 |
| 0870 | Temporary coarse aggregate,aldot number 1 (665N000) | TON | 50 | $87.72 | $102.43 | $134.87 |
| 0880 | Silt fence removal (665O001) | LF | 5,160 | $1.58 | $1.77 | $5.93 |
| 0890 | Inlet protection, stage 3 or 4 (665P005) | EACH | 63 | $472.50 | $530.53 | $374.42 |
| 0900 | Wattle (665Q002) | LF | 1,260 | $9.98 | $11.20 | $13.73 |
| 0910 | Pest control treatment (666A001) | ACRE | 3 | $262.50 | $294.74 | $499.23 |
| 0920 | Construction safety fence (674A000) | LF | 2,500 | $5.00 | $4.02 | $3.91 |
| 0930 | Geometric controls (680A001) | LS | 1 | $52,805 | $106,082 | $39,248 |
| 0940 | Construction fuel (maximum bid limited to $ 432,235.00) (698A000) | LS | 1 | $0.00 | $0.00 | $0.00 |
| 0950 | Solid white, class 2, type A traffic stripe (5" wide) (701A227) | MI | 4 | $3,990.00 | $4,480.03 | $4,742.70 |
| 0960 | Solid yellow, class 2, type A traffic stripe (5" wide) (701A230) | MI | 4 | $3,990.00 | $4,480.03 | $4,742.70 |
| 0970 | Broken white, class 2, type A traffic stripe (5" wide) (701A239) | MI | 3 | $1,050.00 | $1,178.96 | $1,248.08 |
| 0980 | Solid white, class 2 type A traffic stripe (10" wide) (701A270) | MI | 2 | $8,400.00 | $9,431.64 | $9,984.64 |
| 0990 | Dotted, class 2, type A traffic stripe(lane drop 10" wide) (701B063) | LF | 4,727 | $0.63 | $0.71 | $0.75 |
| 1000 | Dotted, class 2, type A traffic stripe (5" wide) (701B207) | LF | 463 | $0.42 | $0.47 | $0.50 |
| 1010 | Broken temporary traffic stripe (701C000) | MI | 5 | $577.50 | $648.43 | $686.45 |
| 1020 | Solid temporary traffic stripe (701C001) | MI | 12 | $1,312.50 | $1,473.69 | $1,560.10 |
| 1030 | Solid traffic stripe removed (701D005) | MI | 12 | $1,365.00 | $1,532.64 | $1,622.50 |
| 1040 | Broken traffic stripe removed (701D013) | MI | 5 | $1,050.00 | $1,178.96 | $1,248.08 |
| 1050 | Dotted temporary traffic stripe (paint) (701F001) | LF | 9,454 | $0.09 | $0.11 | $0.11 |
| 1060 | Broken white, class W, type A traffic stripe (5" wide) (701G142) | LF | 564 | $2.10 | $2.36 | $2.50 |
| 1070 | Solid white, class W, type A traffic stripe (5"wide) (701G146) | LF | 564 | $8.40 | $9.43 | $9.98 |
| 1080 | Solid yellow, class W, type A traffic stripe (5" wide) (701G154) | LF | 564 | $8.40 | $9.43 | $9.98 |
| 1090 | Traffic control markings, class 2, type A (703A002) | SF | 6,601 | $4.99 | $5.60 | $5.93 |
| 1100 | Traffic control markings, class W, type A (703A011) | SF | 33 | $21.00 | $23.58 | $24.96 |
| 1110 | Traffic control legends, class 2, type A (703B002) | SF | 1,099 | $6.83 | $7.66 | $8.11 |
| 1120 | Traffic control legends, class W, type A (703B011) | SF | 45 | $63.00 | $70.74 | $74.88 |
| 1130 | Temporary traffic control markings (paint) (703D002) | SF | 2,297 | $1.31 | $1.47 | $1.56 |
| 1140 | Pavement markers, class A-H, type 2-C (705A030) | EACH | 771 | $5.25 | $5.89 | $6.24 |
| 1150 | Pavement markers, class A-H, type 2-D (705A037) | EACH | 114 | $5.25 | $5.89 | $6.24 |
| 1160 | Class 9, aluminum flat sign panels (type XI background) (710A153) | SF | 732 | $23.10 | $30.06 | $31.83 |
| 1170 | Roadway sign post (#3 "U" channel galvanized steel) (710B001) | LF | 546 | $19.95 | $21.81 | $23.09 |
| 1180 | Removal of existing roadway signs (710C000) | LS | 1 | $5,512.50 | $1,296.85 | $1,372.89 |
| 1190 | Fiber optic trunk cable, 96F (729A005) | LF | 18,020 | $3.69 | $4.19 | $4.45 |
| 1200 | Fiber optic drop cable, 12F (729A101) | LF | 1,025 | $3.43 | $3.90 | $4.14 |
| 1210 | Fiber distribution unit, secondary (729B010) | EACH | 9 | $993.85 | $1,130.03 | $1,199.32 |
| 1220 | Fan-out kit (729B020) | EACH | 9 | $24.77 | $28.16 | $29.89 |
| 1230 | FO patch cable, duplex, LC-LC, 1 meter (729B230) | EACH | 27 | $59.23 | $67.35 | $71.48 |
| 1240 | Network device, type C (fmes)(furnished by others) (729C022) | EACH | 9 | $531.11 | $603.89 | $640.92 |
| 1250 | Camera, positioner (furnished by others) (729D104) | EACH | 4 | $2,233.95 | $2,540.06 | $2,695.81 |
| 1260 | Conduit, underground, non-metallic, 2 inch (729I101) | LF | 6,080 | $13.16 | $14.96 | $15.88 |
| 1270 | Locate tone wire (729I800) | LF | 6,080 | $1.56 | $1.78 | $1.89 |
| 1280 | Warning tape (729I810) | LF | 6,080 | $0.62 | $0.70 | $0.75 |
| 1290 | Miscellaneous infrastructure, fusion splicing (729N000) | EACH | 66 | $46.65 | $53.04 | $56.30 |
| 1300 | Miscellaneous infrastructure, splice closure, underground, 12 fiber (729N111) | EACH | 10 | $1,125.12 | $1,279.29 | $1,357.73 |
| 1310 | Miscellaneous infrastructure, splice closure, underground, 96 fiber (729N117) | EACH | 1 | $1,356.74 | $1,542.65 | $1,637.25 |
| 1320 | Miscellaneous infrastructure, commbox, type F1 (729N301) | EACH | 49 | $983.58 | $1,118.35 | $1,186.93 |
| 1330 | Miscellaneous infrastructure, commbox, type F2 (729N302) | EACH | 9 | $1,811.50 | $2,059.73 | $2,186.03 |
| 1340 | Miscellaneous infrastructure, pull box (24 in X 24 in X 12 in) (729N400) | EACH | 2 | $3,245.85 | $3,690.62 | $3,916.92 |
| 1350 | Miscellaneous infrastructure, fiber marker post (729N500) | EACH | 59 | $73.13 | $83.15 | $88.25 |
| 1360 | Removal of existing traffic control unit ( dauphin street at springhill medical drive) (730A000) | LS | 1 | $15,750 | $17,908 | $18,958 |
| 1370 | Removal of existing traffic control unit ( dauphin street at DU rhu drive) (730A001) | LS | 1 | $15,750 | $17,908 | $18,958 |
| 1380 | Removal of existing traffic control unit ( dauphin street at I-65 southbound off ramp) (730A002) | LS | 1 | $15,750 | $17,908 | $18,958 |
| 1390 | Removal of existing traffic control unit ( dauphin street at I-65 northbound off ramp) (730A003) | LS | 1 | $15,750 | $17,908 | $18,958 |
| 1400 | Removal of existing traffic control unit ( dauphin street at springdale boulevard) (730A004) | LS | 1 | $15,750 | $17,908 | $18,958 |
| 1410 | Removal of existing traffic control unit ( dauphin street at northgate drive) (730A005) | LS | 1 | $15,750 | $17,908 | $18,958 |
| 1420 | Removal of existing traffic control unit ( dauphin street at dauphin square connector) (730A006) | LS | 1 | $15,750 | $17,908 | $18,958 |
| 1430 | Removal of existing traffic control unit ( dauphin street at sage avenue) (730A007) | LS | 1 | $15,750 | $17,908 | $18,958 |
| 1440 | Furnishing and installing traffic control unit ( dauphin street at springhill medical drive) (730C000) | LS | 1 | $65,854 | $74,878 | $79,268 |
| 1450 | Furnishing and installing traffic control unit ( dauphin street at dhu rhu drive) (730C001) | LS | 1 | $60,551 | $68,849 | $72,885 |
| 1460 | Furnishing and installing traffic control unit ( dauphin street at I-65 southbound off ramp) (730C002) | LS | 1 | $48,255 | $54,867 | $58,084 |
| 1470 | Furnishing and installing traffic control unit ( dauphin street at I-65 northbound off ramp) (730C003) | LS | 1 | $47,424 | $53,923 | $57,084 |
| 1480 | Furnishing and installing traffic control unit ( dauphin street at springdale boulevard) (730C004) | LS | 1 | $58,836 | $66,898 | $70,820 |
| 1490 | Furnishing and installing traffic control unit ( dauphin street at northgate drive) (730C005) | LS | 1 | $54,588 | $62,069 | $65,708 |
| 1500 | Furnishing and installing traffic control unit ( dauphin street at dauphin square connector) (730C006) | LS | 1 | $51,755 | $58,846 | $62,297 |
| 1510 | Furnishing and installing traffic control unit ( dauphin street at sage avenue) (730C007) | LS | 1 | $63,211 | $71,873 | $76,087 |
| 1520 | Metal traffic signal pole foundation (730E000) | EACH | 21 | $21,270 | $24,184 | $25,602 |
| 1530 | Metal traffic signal pole with 50' mast arm assembly (730F000) | EACH | 3 | $33,296 | $37,858 | $40,078 |
| 1540 | Metal traffic signal pole with 55' mast arm assembly (730F001) | EACH | 3 | $39,277 | $44,659 | $47,278 |
| 1550 | Metal traffic signal pole with 60' mast arm assembly (730F002) | EACH | 1 | $39,652 | $45,086 | $47,729 |
| 1560 | Metal traffic signal pole with 65' mast arm assembly (730F003) | EACH | 5 | $40,169 | $45,673 | $48,351 |
| 1570 | Metal traffic signal pole with 40' and 65' mast arms assembly (730F004) | EACH | 1 | $53,680 | $61,036 | $64,615 |
| 1580 | Metal traffic signal pole with 45' and 55' mast arms assembly (730F005) | EACH | 1 | $54,853 | $62,369 | $66,026 |
| 1590 | Metal traffic signal pole with 45' and 70' mast arms assembly (730F006) | EACH | 1 | $50,813 | $57,775 | $61,163 |
| 1600 | Metal traffic signal pole with 50' and 55' mast arms assembly (730F007) | EACH | 4 | $54,317 | $61,759 | $65,380 |
| 1610 | Metal traffic signal pole with 50' and 60' mast arms assembly (730F008) | EACH | 1 | $56,005 | $63,679 | $67,413 |
| 1620 | Metal traffic signal pole with 55' and 60' mast arms assembly (730F009) | EACH | 1 | $58,685 | $66,726 | $70,638 |
| 1630 | Traffic signal junction box type S2 (730K002) | EACH | 33 | $1,320.90 | $1,501.90 | $1,589.96 |
| 1640 | 1", non-metallic, conduit (730L003) | LF | 455 | $15.75 | $17.91 | $18.96 |
| 1650 | 2", non-metallic, conduit (730L005) | LF | 1,125 | $19.43 | $22.09 | $23.38 |
| 1660 | Luminaire extension assembly, 12' (730N000) | EACH | 29 | $3,745.35 | $4,258.57 | $4,508.26 |
| 1670 | Vehicular signal head, 12 inch, 3 (730P022) | EACH | 63 | $1,539.30 | $1,750.23 | $1,852.85 |
| 1680 | Vehicular signal head, 12 inch, 4 (730P023) | EACH | 20 | $1,739.85 | $1,978.26 | $2,094.25 |
| 1690 | Pedestrian signal head, type LED (730P100) | EACH | 36 | $1,123.50 | $1,277.45 | $1,352.35 |
| 1700 | Miscellaneous equipment, pedestrian push button (730Q001) | EACH | 36 | $1,200.15 | $1,364.60 | $1,444.61 |
| 1710 | Miscellaneous equipment, pedestal pole and foundation (730Q005) | EACH | 25 | $7,336.35 | $8,341.63 | $8,830.72 |
| 1720 | Electrical power service assembly with wood pole (730T010) | EACH | 8 | $3,940.65 | $4,480.63 | $4,743.34 |
| 1730 | Construction signs (740B000) | SF | 1,034 | $8.40 | $6.19 | $6.55 |
| 1740 | Channelizing drums (740D000) | EACH | 600 | $44.10 | $68.38 | $153.45 |
| 1750 | Cones (36 inches high) (740E000) | EACH | 200 | $16.80 | $29.47 | $29.42 |
| 1760 | Barricades, type III (740F002) | EACH | 11 | $236.25 | $294.74 | $312.02 |
| 1770 | Portable sequential arrow and chevron sign unit (741C010) | EACH | 4 | $1,080.91 | $3,418.97 | $3,619.43 |
| 1780 | Portable changeable message sign, type 1 (742A002) | EACH | 6 | $4,237.33 | $5,894.78 | $6,240.40 |
| 1790 | Uniformed police officer (745A000) | HR | 100 | $68.25 | $63.45 | $53.49 |
| 1800 | Roadway luminaire assembly with one, LED, 250 watt equivalent luminaire (750B601) | EACH | 58 | $8,125.25 | $9,238.63 | $9,805.13 |
| 1810 | Pole foundation,roadway (750C010) | EACH | 58 | $3,116.01 | $3,542.99 | $3,760.24 |
| 1820 | Electrical junction box,type 1 (750D200) | EACH | 62 | $568.47 | $646.37 | $686.00 |
| 1840 | Combined duct and cable,2 #6 AWG/ 1 #6 AWG GND (750G010) | LF | 9,652 | $19.70 | $22.40 | $23.77 |
| 1850 | Combined duct and cable, 2 #2 AWG/ 1 #6 AWG GND (750G030) | LF | 3,214 | $25.82 | $29.36 | $31.16 |
| 1860 | Lighting control center (750I015) | EACH | 2 | $26,147 | $29,729 | $31,552 |
| 1870 | Remove luminare pole foundation (751J004) | EACH | 41 | $941.01 | $1,069.95 | $1,135.56 |
| 1880 | Remove roadway luminaire assembly (751L025) | EACH | 41 | $280.77 | $319.24 | $338.82 |
| 1890 | 4" electrical conduit, 1 line, type 5 installation (756A022) | LF | 3,631 | $31.77 | $36.13 | $38.34 |
| 1900 | 6" electrical conduit, 1 line, type 5 installation (756A028) | LF | 3,980 | $45.44 | $51.67 | $54.84 |
| 1910 | Trainee hours at 80 cents per hour (999 000) | HR | 1,760 | $0.80 | $0.80 | $0.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of September 26, 2025. Compiled by Mirage Metrics.