ARDOT contract 061745 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO REPLACE ONE STRUCTURE ON HIGHWAY 13 IN LONOKE COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, FLOWABLE SELECT MATERIAL, EARTHWORK, ROCK FILL, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH SLABS AND GUTTERS, MAINTENANCE OF TRAFFIC, MINOR DRAINAGE, GUARDRAIL, EROSION CONTROL, GEOTEXTILE FABRIC, RUMBLE STRIPS, PAVEMENT MARKING, CONSTRUCT ONE CAST IN PLACE DECK BRIDGE (110.00'), AND MISC. ITEMS. Let by Arkansas DOT on June 25, 2025, Lonoke. 3 bids received; low bid $3,971,834 by Thomco, Inc..
- Owner
- Arkansas DOT
- Letting
- 25 JUN 2025
- Pay items
- 84
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Thomco, Inc. | $3,971,834 | Low |
| 2 | Robertson Contractors, Inc. | $4,096,983 | +3.0% |
| 3 | Mobley Contractors, Inc. | $4,385,081 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Thomco, Inc. | 2. Robertson Contractors, Inc. | 3. Mobley Contractors, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 17 | $3,531.50 | $2,000.00 | $3,708.08 |
| 0002 | Grubbing (201111) | STA | 17 | $2,118.90 | $2,000.00 | $2,224.85 |
| 0003 | Removal and disposal of pipe culverts (202096) | EACH | 4 | $3,884.65 | $800.00 | $4,078.88 |
| 0004 | Removal and disposal of headwalls (202099) | EACH | 2 | $2,118.90 | $1,500.00 | $2,224.85 |
| 0005 | Removal and disposal of signs (202191) | EACH | 21 | $300.00 | $150.00 | $315.00 |
| 0006 | Removal and disposal of mailboxes (202200) | EACH | 2 | $70.63 | $150.00 | $74.16 |
| 0007 | Removal of existing bridge structure (site no. 1) (205011) | LS | 1 | $50,000 | $70,000 | $41,867 |
| 0008 | Flowable select material (206021) | CY | 12 | $500.00 | $350.00 | $375.03 |
| 0009 | Unclassified excavation (210213) | CY | 4,320 | $23.12 | $34.75 | $24.28 |
| 0010 | Compacted embankment (210611) | CY | 14,886 | $35.94 | $35.00 | $37.74 |
| 0011 | Rock fill (210633) | TON | 7,695 | $46.96 | $33.00 | $49.31 |
| 0012 | Soil stabilization (210702) | TON | 100 | $323.98 | $200.00 | $340.18 |
| 0013 | Aggregate base course (class 7) (303117) | TON | 3,869 | $44.89 | $54.00 | $47.13 |
| 0014 | Tack coat (401011) | GAL | 1,656 | $1.00 | $1.00 | $1.05 |
| 0015 | Mineral aggregate in achm binder course (1") (406161) | TON | 598 | $76.00 | $76.00 | $79.80 |
| 0016 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 29 | $650.00 | $650.00 | $682.50 |
| 0017 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 1,389 | $85.00 | $85.00 | $89.25 |
| 0018 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 85 | $650.00 | $650.00 | $682.50 |
| 0019 | Cold milling asphalt pavement (412002) | SY | 2,700 | $3.50 | $3.50 | $3.68 |
| 0020 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 10 | $250.00 | $250.00 | $231.00 |
| 0021 | Achm patching of existing roadway (415011) | TON | 100 | $220.00 | $220.00 | $231.00 |
| 0022 | Approach slabs (504031) | CY | 128 | $925.00 | $950.00 | $1,021.81 |
| 0023 | Approach gutters (504264) | CY | 17.20 | $2,000.00 | $1,485.00 | $1,703.73 |
| 0024 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $172,000 | $195,000 | $201,737 |
| 0025 | Furnishing field office (602011) | EACH | 1 | $40,000 | $35,000 | $54,186 |
| 0026 | Maintenance of traffic (603009) | LS | 1 | $50,000 | $180,000 | $323,778 |
| 0027 | Signs (604003) | SF | 291 | $7.00 | $7.00 | $7.35 |
| 0028 | Barricades (604013) | LF | 64 | $16.00 | $16.00 | $16.80 |
| 0029 | Traffic drums (604023) | EACH | 63 | $20.00 | $20.00 | $21.00 |
| 0030 | Furnishing and installing precast concrete barrier (604031) | LF | 405 | $52.00 | $52.00 | $55.91 |
| 0031 | Construction pavement markings (604041) | LF | 18,273 | $0.25 | $0.25 | $0.26 |
| 0032 | Removable construction pavement markings (604051) | LF | 1,850 | $1.50 | $1.50 | $1.58 |
| 0033 | Removal of permanent pavement markings (604061) | LF | 590 | $1.75 | $1.75 | $1.84 |
| 0034 | Vertical panels (604083) | EACH | 32 | $25.00 | $25.00 | $26.25 |
| 0035 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 54 | $76.85 | $120.00 | $317.56 |
| 0036 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 56 | $94.87 | $160.00 | $288.30 |
| 0037 | 24" flared end sections for reinforced concrete pipe culverts (605858) | EACH | 2 | $2,564.27 | $2,200.00 | $6,129.16 |
| 0038 | 24" side drain (606704) | LF | 144 | $76.85 | $115.00 | $277.59 |
| 0039 | 4" pipe underdrains (611008) | LF | 100 | $39.33 | $1.00 | $10.50 |
| 0040 | Underdrain outlet protectors (611013) | EACH | 4 | $629.99 | $1.00 | $472.50 |
| 0041 | Guardrail (type A) (617005) | LF | 350 | $34.00 | $34.00 | $35.70 |
| 0042 | Guardrail terminal (type 2) (617312) | EACH | 4 | $3,200.00 | $3,200.00 | $3,360.00 |
| 0043 | Thrie beam guardrail terminal (617332) | EACH | 4 | $2,500.00 | $2,500.00 | $2,625.00 |
| 0044 | Lime (620001) | TON | 8 | $85.00 | $85.00 | $89.25 |
| 0045 | Seeding (620011) | ACRE | 3.98 | $1,300.00 | $1,300.00 | $1,365.00 |
| 0046 | Mulch cover (620022) | ACRE | 10 | $900.00 | $900.00 | $945.00 |
| 0047 | Water (620030) | MGAL | 528.90 | $10.00 | $10.00 | $10.50 |
| 0048 | Temporary seeding (621001) | ACRE | 6.02 | $700.00 | $700.00 | $735.00 |
| 0049 | Silt fence (621021) | LF | 3,326 | $3.25 | $3.25 | $3.41 |
| 0050 | Sand bag ditch checks (621031) | BAG | 185 | $9.00 | $9.00 | $9.45 |
| 0051 | Sediment removal and disposal (621111) | CY | 124 | $32.26 | $1.00 | $1.05 |
| 0052 | Rock ditch checks (621151) | CY | 133 | $126.00 | $115.00 | $115.50 |
| 0053 | Filter sock (12") (621168) | LF | 1,139 | $8.82 | $8.82 | $9.26 |
| 0054 | Second seeding application (623001) | ACRE | 3.98 | $250.00 | $250.00 | $262.50 |
| 0055 | Solid sodding (624001) | SY | 16 | $18.75 | $18.75 | $19.69 |
| 0056 | Geotextile fabric (type 8) (625018) | SY | 2,900 | $8.50 | $5.50 | $7.35 |
| 0057 | Erosion control matting (class 3) (626003) | SY | 1,229.34 | $5.95 | $5.95 | $6.25 |
| 0058 | Roadway construction control (635001) | LS | 1 | $25,000 | $45,000 | $35,185 |
| 0059 | Bridge construction control (636001) | LS | 1 | $50,000 | $40,000 | $18,621 |
| 0060 | Mailboxes (637001) | EACH | 2 | $50.00 | $50.00 | $52.50 |
| 0061 | Mailbox supports (single) (637017) | EACH | 2 | $140.00 | $140.00 | $147.00 |
| 0062 | Rumble strips in asphalt shoulders (642001) | LF | 3,728 | $0.50 | $0.50 | $0.53 |
| 0063 | Portable traffic signal system - actuated (701603) | WEEK | 6 | $1,750.00 | $1,750.00 | $1,837.50 |
| 0064 | Thermoplastic pavement marking white (6") (719002) | LF | 4,400 | $1.50 | $1.50 | $1.58 |
| 0065 | Thermoplastic pavement marking yellow (6") (719102) | LF | 4,400 | $1.50 | $1.50 | $1.58 |
| 0066 | Raised pavement markers (type II) (721002) | EACH | 132 | $15.00 | $15.00 | $15.75 |
| 0067 | Temporary impact attenuation barrier (731071) | EACH | 3 | $10,000 | $5,500.00 | $7,875.00 |
| 0068 | Temporary impact attenuation barrier (repair) (731072) | EACH | 2 | $650.00 | $650.00 | $682.50 |
| 0069 | Class S concrete-bridge (802112) | CY | 116.40 | $2,300.00 | $2,150.00 | $1,582.87 |
| 0070 | Class S(AE) concrete-bridge (802122) | CY | 127.70 | $2,500.00 | $2,650.00 | $2,876.45 |
| 0071 | Prestressed concrete girders (type II) (802662) | LF | 527.30 | $575.00 | $480.00 | $609.36 |
| 0072 | Class 2 protective surface treatment (803004) | SY | 401 | $12.00 | $16.50 | $8.40 |
| 0073 | Reinforcing steel-roadway (grade 60) (804003) | LB | 16,536 | $2.00 | $2.20 | $2.12 |
| 0074 | Reinforcing steel-bridge (grade 60) (804013) | LB | 11,200 | $2.00 | $2.35 | $4.22 |
| 0075 | Epoxy coated reinforcing steel (grade 60) (804023) | LB | 37,171 | $2.20 | $2.40 | $1.96 |
| 0076 | Steel shell piling (18" diameter) (805124) | LF | 950 | $240.00 | $260.00 | $185.99 |
| 0077 | Steel shell piling (24" diameter) (805127) | LF | 475 | $331.00 | $385.00 | $257.09 |
| 0078 | Pile encasement (805513) | LF | 53 | $350.00 | $450.00 | $556.24 |
| 0079 | Structural steel in beam spans (A709, GR. 50W) (807020) | LB | 5,378 | $15.00 | $20.50 | $26.10 |
| 0080 | Elastomeric bearings (808002) | CUIN | 3,510 | $5.00 | $12.30 | $7.95 |
| 0081 | Silicone joint sealant (809015) | LF | 79 | $120.00 | $105.00 | $106.37 |
| 0082 | Bridge name plate (type D) (812004) | EACH | 1 | $3,000.00 | $3,000.00 | $4,059.19 |
| 0083 | Filter blanket (816003) | SY | 184 | $28.65 | $7.00 | $11.12 |
| 0084 | Foundation protection riprap (816131) | TON | 129 | $114.45 | $135.00 | $108.86 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of June 25, 2025. Compiled by Mirage Metrics.