FDOT contract T2A86 bid tabulation

SR 100 FROM CLAY COUNTY LINE TO STJOHNS RIVER WATER MANAGEMENT. Let by Florida DOT on October 28, 2026, Putnam, District 2. 8 bids received; low bid $8,449,954 by Pigott Asphalt and Sitework LLC.

Owner
Florida DOT
Letting
28 OCT 2026
Pay items
85
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Pigott Asphalt and Sitework LLC$8,449,954Low
2Anderson Columbia Co., Inc.$8,733,923+3.0%
3Preferred Materials Inc.$9,707,652+15%
4Halifax Paving, Inc.$9,844,951+17%
5C.W. Roberts Contracting, Inc.$10,440,721+24%
6Hubbard Construction Company$11,318,998+34%
7C.W. Matthews Contracting Co., Inc.$12,724,367+51%
8Duval Asphalt Products, Inc.$12,813,803+52%
FDOT contract T2A86: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Pigott Asphalt and Sitework LLC2. Anderson Columbia Co., Inc.3. Preferred Materials Inc.4. Halifax Paving, Inc.5. C.W. Roberts Contracting, Inc.6. Hubbard Construction Company
0005Bridge deck expansion joint, rehabilitation, poured joint backer rod (0458-1-21)LF644$62.25$76.70$59.00$55.00$59.25$83.74
0010Polymer nosing for bridge expansion joint (0458-2)CF25.70$938.95$876.60$890.00$1,000.00$1,077.00$837.37
0015Mobilization (0101-1)LS1$423,000$581,293$528,541$337,725$416,000$580,293
0020Maintenance of traffic (0102-1)DA1$300,000$256,253$327,823$200,000$300,000$710,938
0025Special detour- temporary pavement (0102-2200)SY1$2,500.00$19,466$26,546$15,000$19,000$15,681
0030Special detour- temporary earthwork/base (0102-2300)CY1$1,500.00$14,479$6,064.82$5,000.00$22,100$6,803.65
0035Traffic control officer (0102-14)HR10$300.00$164.36$100.00$150.00$250.00$94.79
0040Work zone sign (0102-60)ED12,954$0.20$0.24$0.21$0.22$0.22$0.23
0045Temporary barrier, F&I, anchored (0102-71-15)LF2,500$1.00$39.45$36.00$36.00$39.10$38.26
0050Temporary barrier, relocate, anchored (0102-71-25)LF750$1.00$17.54$16.00$16.00$17.35$17.00
0055Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED59,795$0.01$0.12$0.10$0.11$0.11$0.12
0060Temporary raised/retroreflective pavement marker, type B (0102-78-2)EACH846$5.25$5.48$5.00$5.00$5.70$5.76
0065Temporary crash cushion, redirective option (0102-89-1)LO4$150.00$2,410.66$1,200.00$3,500.00$1,232.00$2,739.10
0070Portable changeable message sign, temporary (0102-99)ED628$10.00$16.44$10.40$15.00$10.60$15.94
0075Type III barricade (0102-115)ED326$1.00$0.44$0.28$0.40$0.28$0.43
0080Temporary raised rumble per day, includes all sets and relocations (0102-909)DA179$21.00$0.01$20.80$80.00$21.35$27.98
0085Sediment barrier (0104-10-3)LF2,889$1.11$2.28$1.05$1.50$2.15$1.27
0090Litter removal (0107-1)ACRE990.43$1.00$54.79$67.50$28.00$28.75$29.31
0095Mowing (0107-2)ACRE731.74$1.00$21.91$28.00$69.00$70.85$72.22
0100Clearing & grubbing (0110-1-1)ACRE1$20,000$36,394$23,185$35,000$23,000$103,939
0105Regular excavation (0120-1)CY214.40$36.00$18.65$32.09$50.00$36.00$41.32
0110Subsoil excavation (0120-4)CY190.80$50.00$24.81$36.06$50.00$112.00$47.93
0115Embankment (0120-6)CY987.30$22.00$20.26$37.73$22.00$34.00$37.68
0120Type B stabilization (0160-4)SY1,244$16.00$6.11$21.82$20.00$19.80$19.78
0125Grout pipe installation (0173-76)LF280$26.38$27.39$35.00$35.00$123.00$26.17
0130Subsurface pressure grouting, sand cement (0173-77-1)CY65$342.88$356.13$335.00$335.00$430.00$387.36
0135Optional base, base group 01 (0285-701)SY1,774$21.00$17.63$32.94$18.00$18.05$17.35
0140Optional base, base group 07 (0285-707)SY834$45.00$59.80$49.60$30.00$56.30$67.49
0145Milling existing asphalt pavement, 4 1/2" avg depth (0327-70-3)SY7,416$5.00$3.65$4.42$5.00$4.60$5.81
0150Milling existing asphalt pavement, 2" avg depth (0327-70-5)SY376,168$1.40$1.72$1.50$2.65$1.75$2.41
0155Milling existing asphalt pavement, 5 1/2" avg depth (0327-70-18)SY841$10.00$12.53$14.35$5.00$14.05$6.96
0160Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN1,337.60$140.00$127.66$165.41$175.00$156.00$161.00
0165Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN42,404.10$130.00$124.92$145.62$145.00$161.00$147.72
0170Miscellaneous asphalt (0339-1)TN28.80$350.00$449.01$581.80$250.00$400.00$316.24
0175Replace grate (0425-82)EACH1$3,500.00$3,457.33$1,000.00$2,000.00$2,307.00$3,140.15
0180Pipe culvert, optional material, round, 18"SD (0430-174118)LF8$250.00$522.85$1,150.00$260.00$305.00$327.79
0185Mitered end section, optional round, 18" SD (0430-984125)EACH34$1,800.00$1,641.24$1,125.00$2,300.00$3,291.00$3,580.87
0190Mitered end section, optional round, 24" SD (0430-984129)EACH10$2,500.00$2,193.33$1,200.00$2,600.00$3,073.00$4,352.13
0195Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625)EACH6$2,300.00$2,081.89$1,125.00$2,400.00$2,791.00$3,801.23
0200Mitered end sect, optional - elliptical / arch, 24" SD (0430-984629)EACH1$3,000.00$2,658.10$1,200.00$2,750.00$4,631.00$5,453.94
0205Traffic separator concrete- type IV, 4' wide (0520-5-41)LF84$130.00$164.36$88.00$110.00$91.70$137.73
0210Guardrail -roadway, general (0536-1-1)LF2,184$27.43$33.97$31.00$26.00$26.75$32.94
0215Special guardrail post- deep post for slope break timber or steel (0536-7-1)EACH257$79.13$1.10$1.00$75.00$77.00$1.06
0220Guardrail removal (0536-73)LF2,184$2.37$2.19$2.00$2.25$2.30$2.13
0225Guardrail end treatment- parallel approach terminal (0536-85-24)EACH1$2,848.50$3,615.99$3,300.00$2,700.00$2,773.00$3,506.76
0230Performance turf, sod (0570-1-2)SY66,800$2.94$2.84$3.00$3.50$4.40$6.41
0235Shoulder drop off soil (0570-13-1)CY9,362.70$1.00$5.10$20.97$20.00$1.00$46.98
0240Painted pavement markings, standard, white, solid, 6" (0710-11101)GM1.86$2,500.00$1,424.48$1,293.71$1,300.00$1,487.00$2,083.30
0245Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF31$5.00$2.19$2.00$2.00$2.28$3.14
0250Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.02$10,000$712.23$590.91$650.00$679.00$761.36
0255Painted pavement markings, standard, white, arrows (0710-11170)EACH8$50.00$49.31$45.00$45.00$51.70$57.57
0260Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM1.59$2,500.00$1,424.48$1,296.74$1,300.00$1,490.00$2,088.17
0265Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF252$2.50$1.92$1.75$1.75$2.00$3.14
0270Painted pavement markings, standard, yellow, skip, 6" (0710-11231)GM0.06$10,000$712.23$590.91$650.00$679.00$409.09
0275Initial contingency amount, DO not bid (0999-25)LS1$113,412$113,412$113,412$113,412$113,412$113,412
0280Ground-in rumble strips, 8" sinusoidal (0546-72-3)GM51.10$1,680.00$1,972.36$2,169.93$2,115.00$2,390.00$1,935.08
0285Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH40$527.50$547.87$490.26$490.26$560.00$513.16
0290Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH17$2,162.75$2,246.29$1,466.43$1,466.43$1,675.00$1,534.93
0295Single column ground sign assembly, relocate (0700-1500)EACH6$184.63$191.75$348.71$348.71$398.00$365.00
0300Single column ground sign assembly, remove (0700-1600)EACH29$52.75$54.79$105.00$105.00$119.00$109.91
0305Multi-column ground sign assembly, F&I ground mount, than 12 SF (0700-2111)EACH1$4,220.00$4,383.01$3,616.97$3,616.97$4,131.50$3,785.94
0310Multi-column ground sign assembly, remove (0700-2600)EACH4$527.50$547.87$840.00$840.00$959.50$879.24
0315Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH14$211.00$219.15$280.99$280.99$321.00$294.12
0320Sign panel, furnish & install ground mount, 12-20 SF (0700-3102)EACH1$290.13$301.34$469.81$469.81$537.00$491.76
0325Sign panel, remove, UP to 12 SF (0700-3601)EACH14$36.93$38.35$52.50$52.50$60.00$54.95
0330Sign panel, remove, 12-20 SF (0700-3602)EACH1$58.03$60.27$105.00$105.00$120.00$109.91
0335Enhanced highway sign solar powered, F&I ground mount, W/beacon, 12-20 SF of static sign panels (0700-142112)EACH2$10,550$10,958$7,532.12$7,532.12$8,604.00$7,883.99
0340Enhanced highway sign solar powered, relocate - ground mount (0700-142802)EACH1$1,846.25$1,917.57$3,661.19$3,661.19$4,182.00$3,832.22
0345Enhanced highway sign solar powered, remove - mount (0700-142902)EACH2$263.75$273.95$420.00$420.00$480.00$439.62
0350Object marker, type 1 (0705-10-1)EACH42$237.38$246.54$118.95$118.95$136.00$124.51
0355Object marker, type 2 (0705-10-2)EACH32$89.68$93.14$116.24$116.24$132.75$121.67
0360Object marker, type 3 (0705-10-3)EACH8$237.38$246.54$184.84$184.84$211.00$193.48
0365Delineator, flexible tubular (0705-11-1)EACH24$110.78$115.05$273.53$273.53$312.00$286.31
0370Raised pavement marker, type B (0706-1-3)EACH4,745$5.27$5.48$5.00$5.00$5.70$5.76
0375Painted pavement markings, surface (0710-90)LS1$124,263$129,063$117,785$117,785$135,374$170,405
0380Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF1,215$6.07$6.30$5.75$5.75$6.60$6.28
0385Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF318$8.44$8.77$8.00$8.00$9.15$10.47
0390Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.12$2,321.00$2,410.66$2,104.35$2,200.00$2,419.00$2,603.13
0395Thermoplastic, standard, message or symbol (0711-11160)EACH8$200.45$208.19$190.00$190.00$218.40$209.34
0400Thermoplastic, standard, arrow (0711-11170)EACH33$79.13$82.18$75.00$75.00$86.15$94.20
0405Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF640$6.86$7.12$6.50$6.50$7.45$6.54
0410Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM37.87$4,220.00$4,383.01$3,999.68$4,000.00$4,595.00$3,977.20
0415Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM19.56$4,220.00$4,383.01$4,000.00$4,000.00$4,596.00$3,977.52
0420Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM11.64$1,266.00$1,314.90$1,199.48$1,200.00$1,379.00$1,255.52
0425Loop assembly, F&I, type F (0660-2106)AS1$3,500.00$2,676.06$2,472.84$2,472.84$2,540.00$2,588.36
FDOT contract T2A86: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of October 28, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy