FDOT contract T2A86 bid tabulation
SR 100 FROM CLAY COUNTY LINE TO STJOHNS RIVER WATER MANAGEMENT. Let by Florida DOT on October 28, 2026, Putnam, District 2. 8 bids received; low bid $8,449,954 by Pigott Asphalt and Sitework LLC.
- Owner
- Florida DOT
- Letting
- 28 OCT 2026
- Pay items
- 85
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pigott Asphalt and Sitework LLC | $8,449,954 | Low |
| 2 | Anderson Columbia Co., Inc. | $8,733,923 | +3.0% |
| 3 | Preferred Materials Inc. | $9,707,652 | +15% |
| 4 | Halifax Paving, Inc. | $9,844,951 | +17% |
| 5 | C.W. Roberts Contracting, Inc. | $10,440,721 | +24% |
| 6 | Hubbard Construction Company | $11,318,998 | +34% |
| 7 | C.W. Matthews Contracting Co., Inc. | $12,724,367 | +51% |
| 8 | Duval Asphalt Products, Inc. | $12,813,803 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pigott Asphalt and Sitework LLC | 2. Anderson Columbia Co., Inc. | 3. Preferred Materials Inc. | 4. Halifax Paving, Inc. | 5. C.W. Roberts Contracting, Inc. | 6. Hubbard Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Bridge deck expansion joint, rehabilitation, poured joint backer rod (0458-1-21) | LF | 644 | $62.25 | $76.70 | $59.00 | $55.00 | $59.25 | $83.74 |
| 0010 | Polymer nosing for bridge expansion joint (0458-2) | CF | 25.70 | $938.95 | $876.60 | $890.00 | $1,000.00 | $1,077.00 | $837.37 |
| 0015 | Mobilization (0101-1) | LS | 1 | $423,000 | $581,293 | $528,541 | $337,725 | $416,000 | $580,293 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $300,000 | $256,253 | $327,823 | $200,000 | $300,000 | $710,938 |
| 0025 | Special detour- temporary pavement (0102-2200) | SY | 1 | $2,500.00 | $19,466 | $26,546 | $15,000 | $19,000 | $15,681 |
| 0030 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $1,500.00 | $14,479 | $6,064.82 | $5,000.00 | $22,100 | $6,803.65 |
| 0035 | Traffic control officer (0102-14) | HR | 10 | $300.00 | $164.36 | $100.00 | $150.00 | $250.00 | $94.79 |
| 0040 | Work zone sign (0102-60) | ED | 12,954 | $0.20 | $0.24 | $0.21 | $0.22 | $0.22 | $0.23 |
| 0045 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 2,500 | $1.00 | $39.45 | $36.00 | $36.00 | $39.10 | $38.26 |
| 0050 | Temporary barrier, relocate, anchored (0102-71-25) | LF | 750 | $1.00 | $17.54 | $16.00 | $16.00 | $17.35 | $17.00 |
| 0055 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 59,795 | $0.01 | $0.12 | $0.10 | $0.11 | $0.11 | $0.12 |
| 0060 | Temporary raised/retroreflective pavement marker, type B (0102-78-2) | EACH | 846 | $5.25 | $5.48 | $5.00 | $5.00 | $5.70 | $5.76 |
| 0065 | Temporary crash cushion, redirective option (0102-89-1) | LO | 4 | $150.00 | $2,410.66 | $1,200.00 | $3,500.00 | $1,232.00 | $2,739.10 |
| 0070 | Portable changeable message sign, temporary (0102-99) | ED | 628 | $10.00 | $16.44 | $10.40 | $15.00 | $10.60 | $15.94 |
| 0075 | Type III barricade (0102-115) | ED | 326 | $1.00 | $0.44 | $0.28 | $0.40 | $0.28 | $0.43 |
| 0080 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 179 | $21.00 | $0.01 | $20.80 | $80.00 | $21.35 | $27.98 |
| 0085 | Sediment barrier (0104-10-3) | LF | 2,889 | $1.11 | $2.28 | $1.05 | $1.50 | $2.15 | $1.27 |
| 0090 | Litter removal (0107-1) | ACRE | 990.43 | $1.00 | $54.79 | $67.50 | $28.00 | $28.75 | $29.31 |
| 0095 | Mowing (0107-2) | ACRE | 731.74 | $1.00 | $21.91 | $28.00 | $69.00 | $70.85 | $72.22 |
| 0100 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $20,000 | $36,394 | $23,185 | $35,000 | $23,000 | $103,939 |
| 0105 | Regular excavation (0120-1) | CY | 214.40 | $36.00 | $18.65 | $32.09 | $50.00 | $36.00 | $41.32 |
| 0110 | Subsoil excavation (0120-4) | CY | 190.80 | $50.00 | $24.81 | $36.06 | $50.00 | $112.00 | $47.93 |
| 0115 | Embankment (0120-6) | CY | 987.30 | $22.00 | $20.26 | $37.73 | $22.00 | $34.00 | $37.68 |
| 0120 | Type B stabilization (0160-4) | SY | 1,244 | $16.00 | $6.11 | $21.82 | $20.00 | $19.80 | $19.78 |
| 0125 | Grout pipe installation (0173-76) | LF | 280 | $26.38 | $27.39 | $35.00 | $35.00 | $123.00 | $26.17 |
| 0130 | Subsurface pressure grouting, sand cement (0173-77-1) | CY | 65 | $342.88 | $356.13 | $335.00 | $335.00 | $430.00 | $387.36 |
| 0135 | Optional base, base group 01 (0285-701) | SY | 1,774 | $21.00 | $17.63 | $32.94 | $18.00 | $18.05 | $17.35 |
| 0140 | Optional base, base group 07 (0285-707) | SY | 834 | $45.00 | $59.80 | $49.60 | $30.00 | $56.30 | $67.49 |
| 0145 | Milling existing asphalt pavement, 4 1/2" avg depth (0327-70-3) | SY | 7,416 | $5.00 | $3.65 | $4.42 | $5.00 | $4.60 | $5.81 |
| 0150 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 376,168 | $1.40 | $1.72 | $1.50 | $2.65 | $1.75 | $2.41 |
| 0155 | Milling existing asphalt pavement, 5 1/2" avg depth (0327-70-18) | SY | 841 | $10.00 | $12.53 | $14.35 | $5.00 | $14.05 | $6.96 |
| 0160 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 1,337.60 | $140.00 | $127.66 | $165.41 | $175.00 | $156.00 | $161.00 |
| 0165 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 42,404.10 | $130.00 | $124.92 | $145.62 | $145.00 | $161.00 | $147.72 |
| 0170 | Miscellaneous asphalt (0339-1) | TN | 28.80 | $350.00 | $449.01 | $581.80 | $250.00 | $400.00 | $316.24 |
| 0175 | Replace grate (0425-82) | EACH | 1 | $3,500.00 | $3,457.33 | $1,000.00 | $2,000.00 | $2,307.00 | $3,140.15 |
| 0180 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 8 | $250.00 | $522.85 | $1,150.00 | $260.00 | $305.00 | $327.79 |
| 0185 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 34 | $1,800.00 | $1,641.24 | $1,125.00 | $2,300.00 | $3,291.00 | $3,580.87 |
| 0190 | Mitered end section, optional round, 24" SD (0430-984129) | EACH | 10 | $2,500.00 | $2,193.33 | $1,200.00 | $2,600.00 | $3,073.00 | $4,352.13 |
| 0195 | Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625) | EACH | 6 | $2,300.00 | $2,081.89 | $1,125.00 | $2,400.00 | $2,791.00 | $3,801.23 |
| 0200 | Mitered end sect, optional - elliptical / arch, 24" SD (0430-984629) | EACH | 1 | $3,000.00 | $2,658.10 | $1,200.00 | $2,750.00 | $4,631.00 | $5,453.94 |
| 0205 | Traffic separator concrete- type IV, 4' wide (0520-5-41) | LF | 84 | $130.00 | $164.36 | $88.00 | $110.00 | $91.70 | $137.73 |
| 0210 | Guardrail -roadway, general (0536-1-1) | LF | 2,184 | $27.43 | $33.97 | $31.00 | $26.00 | $26.75 | $32.94 |
| 0215 | Special guardrail post- deep post for slope break timber or steel (0536-7-1) | EACH | 257 | $79.13 | $1.10 | $1.00 | $75.00 | $77.00 | $1.06 |
| 0220 | Guardrail removal (0536-73) | LF | 2,184 | $2.37 | $2.19 | $2.00 | $2.25 | $2.30 | $2.13 |
| 0225 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 1 | $2,848.50 | $3,615.99 | $3,300.00 | $2,700.00 | $2,773.00 | $3,506.76 |
| 0230 | Performance turf, sod (0570-1-2) | SY | 66,800 | $2.94 | $2.84 | $3.00 | $3.50 | $4.40 | $6.41 |
| 0235 | Shoulder drop off soil (0570-13-1) | CY | 9,362.70 | $1.00 | $5.10 | $20.97 | $20.00 | $1.00 | $46.98 |
| 0240 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 1.86 | $2,500.00 | $1,424.48 | $1,293.71 | $1,300.00 | $1,487.00 | $2,083.30 |
| 0245 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 31 | $5.00 | $2.19 | $2.00 | $2.00 | $2.28 | $3.14 |
| 0250 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.02 | $10,000 | $712.23 | $590.91 | $650.00 | $679.00 | $761.36 |
| 0255 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 8 | $50.00 | $49.31 | $45.00 | $45.00 | $51.70 | $57.57 |
| 0260 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 1.59 | $2,500.00 | $1,424.48 | $1,296.74 | $1,300.00 | $1,490.00 | $2,088.17 |
| 0265 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 252 | $2.50 | $1.92 | $1.75 | $1.75 | $2.00 | $3.14 |
| 0270 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 0.06 | $10,000 | $712.23 | $590.91 | $650.00 | $679.00 | $409.09 |
| 0275 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $113,412 | $113,412 | $113,412 | $113,412 | $113,412 | $113,412 |
| 0280 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 51.10 | $1,680.00 | $1,972.36 | $2,169.93 | $2,115.00 | $2,390.00 | $1,935.08 |
| 0285 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 40 | $527.50 | $547.87 | $490.26 | $490.26 | $560.00 | $513.16 |
| 0290 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 17 | $2,162.75 | $2,246.29 | $1,466.43 | $1,466.43 | $1,675.00 | $1,534.93 |
| 0295 | Single column ground sign assembly, relocate (0700-1500) | EACH | 6 | $184.63 | $191.75 | $348.71 | $348.71 | $398.00 | $365.00 |
| 0300 | Single column ground sign assembly, remove (0700-1600) | EACH | 29 | $52.75 | $54.79 | $105.00 | $105.00 | $119.00 | $109.91 |
| 0305 | Multi-column ground sign assembly, F&I ground mount, than 12 SF (0700-2111) | EACH | 1 | $4,220.00 | $4,383.01 | $3,616.97 | $3,616.97 | $4,131.50 | $3,785.94 |
| 0310 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 4 | $527.50 | $547.87 | $840.00 | $840.00 | $959.50 | $879.24 |
| 0315 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 14 | $211.00 | $219.15 | $280.99 | $280.99 | $321.00 | $294.12 |
| 0320 | Sign panel, furnish & install ground mount, 12-20 SF (0700-3102) | EACH | 1 | $290.13 | $301.34 | $469.81 | $469.81 | $537.00 | $491.76 |
| 0325 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 14 | $36.93 | $38.35 | $52.50 | $52.50 | $60.00 | $54.95 |
| 0330 | Sign panel, remove, 12-20 SF (0700-3602) | EACH | 1 | $58.03 | $60.27 | $105.00 | $105.00 | $120.00 | $109.91 |
| 0335 | Enhanced highway sign solar powered, F&I ground mount, W/beacon, 12-20 SF of static sign panels (0700-142112) | EACH | 2 | $10,550 | $10,958 | $7,532.12 | $7,532.12 | $8,604.00 | $7,883.99 |
| 0340 | Enhanced highway sign solar powered, relocate - ground mount (0700-142802) | EACH | 1 | $1,846.25 | $1,917.57 | $3,661.19 | $3,661.19 | $4,182.00 | $3,832.22 |
| 0345 | Enhanced highway sign solar powered, remove - mount (0700-142902) | EACH | 2 | $263.75 | $273.95 | $420.00 | $420.00 | $480.00 | $439.62 |
| 0350 | Object marker, type 1 (0705-10-1) | EACH | 42 | $237.38 | $246.54 | $118.95 | $118.95 | $136.00 | $124.51 |
| 0355 | Object marker, type 2 (0705-10-2) | EACH | 32 | $89.68 | $93.14 | $116.24 | $116.24 | $132.75 | $121.67 |
| 0360 | Object marker, type 3 (0705-10-3) | EACH | 8 | $237.38 | $246.54 | $184.84 | $184.84 | $211.00 | $193.48 |
| 0365 | Delineator, flexible tubular (0705-11-1) | EACH | 24 | $110.78 | $115.05 | $273.53 | $273.53 | $312.00 | $286.31 |
| 0370 | Raised pavement marker, type B (0706-1-3) | EACH | 4,745 | $5.27 | $5.48 | $5.00 | $5.00 | $5.70 | $5.76 |
| 0375 | Painted pavement markings, surface (0710-90) | LS | 1 | $124,263 | $129,063 | $117,785 | $117,785 | $135,374 | $170,405 |
| 0380 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 1,215 | $6.07 | $6.30 | $5.75 | $5.75 | $6.60 | $6.28 |
| 0385 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 318 | $8.44 | $8.77 | $8.00 | $8.00 | $9.15 | $10.47 |
| 0390 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.12 | $2,321.00 | $2,410.66 | $2,104.35 | $2,200.00 | $2,419.00 | $2,603.13 |
| 0395 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 8 | $200.45 | $208.19 | $190.00 | $190.00 | $218.40 | $209.34 |
| 0400 | Thermoplastic, standard, arrow (0711-11170) | EACH | 33 | $79.13 | $82.18 | $75.00 | $75.00 | $86.15 | $94.20 |
| 0405 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 640 | $6.86 | $7.12 | $6.50 | $6.50 | $7.45 | $6.54 |
| 0410 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 37.87 | $4,220.00 | $4,383.01 | $3,999.68 | $4,000.00 | $4,595.00 | $3,977.20 |
| 0415 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 19.56 | $4,220.00 | $4,383.01 | $4,000.00 | $4,000.00 | $4,596.00 | $3,977.52 |
| 0420 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 11.64 | $1,266.00 | $1,314.90 | $1,199.48 | $1,200.00 | $1,379.00 | $1,255.52 |
| 0425 | Loop assembly, F&I, type F (0660-2106) | AS | 1 | $3,500.00 | $2,676.06 | $2,472.84 | $2,472.84 | $2,540.00 | $2,588.36 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of October 28, 2026. Compiled by Mirage Metrics.