FDOT contract T3951 bid tabulation
SR 20 OVER ECONFINA CREEK, BRIDGE NO 460037 AND 460034. Let by Florida DOT on March 25, 2026, Bay, District 3. 4 bids received; low bid $14,753,181 by RJ Gorman Contracting LLC.
- Owner
- Florida DOT
- Letting
- 25 MAR 2026
- Pay items
- 119
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | RJ Gorman Contracting LLC | $14,753,181 | Low |
| 2 | Murphree Bridge Corporation | $14,807,244 | 0.0% |
| 3 | Anderson Columbia Co., Inc. | $16,891,497 | +14% |
| 4 | Superior Construction Company Southeast, LLC | $18,747,903 | +27% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. RJ Gorman Contracting LLC | 2. Murphree Bridge Corporation | 3. Anderson Columbia Co., Inc. | 4. Superior Construction Company Southeast, LLC |
|---|---|---|---|---|---|---|---|
| 0005 | Removal of existing structures/bridges (0110-3) | SF | 1 | $150,854 | $330,000 | $185,000 | $760,665 |
| 0010 | Removal of existing structures/bridges (0110-3) | SF | 1 | $207,390 | $335,000 | $450,000 | $765,615 |
| 0015 | Concrete class II, bridge substructure (0400-2-5) | CY | 255.60 | $1,881.61 | $1,500.00 | $1,885.00 | $2,445.00 |
| 0020 | Concrete class II, approach slabs (0400-2-10) | CY | 242.60 | $451.08 | $1,100.00 | $800.00 | $745.00 |
| 0025 | Concrete class II, cast-in-place topping with shrinkage admixture (0400-2-47) | CY | 627.50 | $844.54 | $1,600.00 | $925.00 | $1,105.00 |
| 0030 | Bridge deck grooving (0400-7-1) | SY | 2,047 | $11.82 | $3.50 | $9.00 | $3.85 |
| 0035 | Bridge deck planing (0400-9-1) | SY | 2,047 | $11.82 | $10.75 | $14.00 | $7.35 |
| 0040 | Plain neoprene bearing pads (0400-148) | CF | 32 | $1,234.37 | $1,200.00 | $1,950.00 | $1,000.00 |
| 0045 | Reinforcing steel - bridge superstructure (0415-1-4) | LB | 130,442 | $1.54 | $1.80 | $2.00 | $1.30 |
| 0050 | Reinforcing steel- bridge substructure (0415-1-5) | LB | 30,786 | $1.54 | $1.80 | $2.50 | $1.30 |
| 0055 | Reinforcing steel- approach slabs (0415-1-9) | LB | 41,974 | $1.54 | $1.80 | $2.00 | $1.30 |
| 0060 | Prestressed beam: florida slab beam, beam depth 18" carbon steel, width 55-57" (0450-8-33) | LF | 4,002 | $446.37 | $365.00 | $620.00 | $345.00 |
| 0065 | Pile inspection, driven pile (0455-20-1) | EACH | 68 | $1,028.09 | $950.00 | $1,000.00 | $1,450.00 |
| 0070 | Steel piling, 24" dia. pipe (0455-35-22) | LF | 6,003 | $396.07 | $350.00 | $370.00 | $265.00 |
| 0075 | Load test (dynamic), data collection and analysis (0455-137) | EACH | 68 | $1,113.77 | $2,500.00 | $1,650.00 | $1,050.00 |
| 0080 | Load test (dynamic), test (0455-137-2) | EACH | 10 | $3,708.89 | $1,000.00 | $2,250.00 | $850.00 |
| 0085 | Test piles - steel, 24" dia pipe (0455-144-22) | LF | 1,179 | $472.72 | $375.00 | $412.00 | $550.00 |
| 0090 | Bridge deck expansion joint, construction, F&I poured joint with backer rod (0458-1-11) | LF | 188 | $62.73 | $60.00 | $85.00 | $45.50 |
| 0095 | Concrete traffic railing- 36" single-slope (0521-5-13) | LF | 1,065 | $117.34 | $120.00 | $150.00 | $115.00 |
| 0100 | Riprap, sand-cement bags (0530-1100) | CY | 88.20 | $770.61 | $1,250.00 | $780.00 | $930.00 |
| 0105 | Riprap- rubble, bank and shore (0530-3-3) | TN | 1,751 | $106.61 | $145.00 | $130.00 | $90.00 |
| 0108 | Articulating concrete block revetment system, thickness 6" (0530-4-6) | SY | 704 | $197.24 | $160.00 | $225.00 | $245.00 |
| 0115 | Bedding stone (0530-74) | TN | 988 | $113.81 | $100.00 | $150.00 | $120.00 |
| 0120 | Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16) | LF | 3,193 | $3.64 | $20.00 | $9.00 | $15.00 |
| 0125 | Junction box, furnish & install, embedded (0635-3-13) | EACH | 8 | $157.98 | $500.00 | $1,600.00 | $1,500.00 |
| 0130 | Mobilization (0101-1) | LS | 1 | $1,395,000 | $1,009,513 | $1,700,000 | $1,874,790 |
| 0135 | Maintenance of traffic (0102-1) | DA | 1 | $74,149 | $112,125 | $123,000 | $150,350 |
| 0140 | Special detour- temporary pavement (0102-2200) | SY | 1 | $304,962 | $172,000 | $230,000 | $699,195 |
| 0145 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $499,788 | $725,000 | $800,000 | $517,600 |
| 0150 | Special detour- temporary bridge bridge #460170 (0102-2400) | EACH | 1 | $235,606 | $485,800 | $350,000 | $402,200 |
| 0155 | Special detour- temporary bridge bridge #460171 (0102-2400) | EACH | 1 | $862,038 | $773,500 | $650,000 | $731,130 |
| 0160 | Commercial material for temporary driveway maintenance (0102-3) | CY | 16.20 | $172.78 | $85.00 | $90.00 | $200.00 |
| 0165 | Traffic control officer (0102-14) | HR | 120 | $77.10 | $75.00 | $95.00 | $83.50 |
| 0170 | Work zone sign (0102-60) | ED | 59,008 | $0.36 | $0.25 | $0.26 | $0.10 |
| 0175 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 4,356 | $51.40 | $40.00 | $41.97 | $44.00 |
| 0180 | Temporary barrier, F&I, free standing (0102-71-16) | LF | 530 | $32.13 | $25.00 | $26.23 | $27.50 |
| 0185 | Temporary barrier, relocate, anchored (0102-71-25) | LF | 2,445 | $32.13 | $15.00 | $15.74 | $16.50 |
| 0190 | Temporary guardrail (0102-73) | LF | 740 | $25.70 | $20.00 | $22.00 | $22.00 |
| 0195 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 105,968 | $0.13 | $0.10 | $0.10 | $0.10 |
| 0200 | Temporary crash cushion, redirective option (0102-89-1) | LO | 24 | $1,285.11 | $1,000.00 | $1,600.00 | $1,728.00 |
| 0205 | Portable changeable message sign, temporary (0102-99) | ED | 2,268 | $16.71 | $13.00 | $13.64 | $13.00 |
| 0210 | Type III barricade (0102-115) | ED | 10,688 | $0.32 | $0.25 | $0.26 | $0.25 |
| 0215 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.16 | $13,494 | $10,500 | $15,500 | $10,500 |
| 0220 | Removable tape, yellow, solid, (0102-913-31) | GM | 0.16 | $13,494 | $10,500 | $15,500 | $10,500 |
| 0225 | Artificial coverings /rolled erosion control products (0104-1) | SY | 184 | $14.33 | $15.00 | $15.74 | $12.25 |
| 0230 | Sediment barrier (0104-10-3) | LF | 2,801 | $2.24 | $4.00 | $4.00 | $10.00 |
| 0235 | Floating turbidity barrier (0104-11) | LF | 396 | $14.58 | $30.00 | $46.48 | $55.00 |
| 0240 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 440 | $12.08 | $5.00 | $40.19 | $30.00 |
| 0245 | Soil tracking prevention device (0104-15) | EACH | 3 | $2,971.71 | $3,850.00 | $6,649.53 | $6,900.00 |
| 0250 | Inlet protection system (0104-18) | EACH | 1 | $261.57 | $350.00 | $236.09 | $450.00 |
| 0255 | Litter removal (0107-1) | ACRE | 430.44 | $32.13 | $100.00 | $104.93 | $125.00 |
| 0260 | Mowing (0107-2) | ACRE | 314.39 | $38.55 | $100.00 | $104.93 | $100.00 |
| 0265 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $9,638.33 | $20,000 | $24,500 | $8,225.00 |
| 0270 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $9,638.33 | $21,500 | $22,000 | $17,690 |
| 0275 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $115,711 | $65,000 | $95,500 | $2,213,057 |
| 0280 | Removal of existing concrete (0110-4-10) | SY | 311 | $18.72 | $45.00 | $50.00 | $82.35 |
| 0285 | Mailbox, F&I single (0110-7-1) | EACH | 1 | $307.71 | $250.00 | $1,100.00 | $1,500.00 |
| 0290 | Regular excavation (0120-1) | CY | 837.90 | $6.13 | $10.00 | $10.49 | $13.00 |
| 0295 | Embankment (0120-6) | CY | 26,778.60 | $19.71 | $14.25 | $15.09 | $24.50 |
| 0300 | Settlement plate assembly (0141-70) | AS | 13 | $2,428.86 | $1,850.00 | $2,000.00 | $1,000.00 |
| 0305 | Geosynthetic reinforced embankment (0145-3) | SY | 11,885 | $4.79 | $10.00 | $11.00 | $6.50 |
| 0310 | Type B stabilization (0160-4) | SY | 10,554 | $5.04 | $5.00 | $5.25 | $11.00 |
| 0315 | Optional base, base group 01 (0285-701) | SY | 2,219 | $16.39 | $15.00 | $15.74 | $18.00 |
| 0320 | Optional base, base group 02 (0285-702) | SY | 824 | $19.98 | $18.50 | $19.41 | $22.00 |
| 0325 | Optional base, base group 04 (0285-704) | SY | 1,830 | $23.02 | $22.00 | $23.08 | $20.50 |
| 0330 | Optional base, base group 09 (0285-709) | SY | 4,320 | $31.09 | $32.00 | $33.58 | $30.00 |
| 0335 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 4,239 | $4.21 | $3.00 | $3.15 | $3.00 |
| 0340 | Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52) | TN | 697.80 | $269.61 | $145.00 | $152.15 | $145.00 |
| 0345 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 941.50 | $263.90 | $149.00 | $156.34 | $149.00 |
| 0350 | Miscellaneous asphalt (0339-1) | TN | 86.20 | $257.02 | $250.00 | $262.32 | $310.00 |
| 0355 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 1 | $7,636.57 | $6,325.00 | $6,636.80 | $9,145.00 |
| 0360 | Inlets, DT bot, type D, <10' (0425-1541) | EACH | 1 | $6,414.90 | $5,300.00 | $5,561.27 | $8,285.00 |
| 0365 | Inlets, gutter, type S, <10' (0425-1701) | EACH | 9 | $7,733.02 | $6,700.00 | $7,082.75 | $8,070.00 |
| 0370 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 977 | $78.85 | $95.00 | $101.78 | $115.00 |
| 0375 | Mitered end section, optional round, 18" CD (0430-982125) | EACH | 7 | $3,445.49 | $2,815.00 | $3,252.81 | $4,800.00 |
| 0380 | Treated timber, structural (0470-1) | MB | 0.20 | $19,577 | $15,000 | $15,739 | $20,000 |
| 0385 | Concrete curb & gutter, type F (0520-1-10) | LF | 328 | $51.86 | $35.00 | $40.92 | $55.00 |
| 0390 | Traffic separator concrete- type I, 4' wide (0520-5-11) | LF | 220 | $119.82 | $95.37 | $142.70 | $150.00 |
| 0395 | Shoulder gutter- concrete (0520-6) | LF | 1,423 | $39.14 | $45.08 | $53.51 | $63.00 |
| 0400 | Concrete barrier, with slab, 36" single slope (0521-8-7) | LF | 270 | $418.49 | $443.21 | $478.48 | $540.00 |
| 0405 | Concrete ditch pavt, non reinforced, 3" (0524-1-1) | SY | 45 | $128.38 | $131.87 | $99.68 | $125.00 |
| 0410 | Concrete ditch pavement, 4", reinforced (0524-1-29) | SY | 79 | $156.92 | $210.64 | $283.08 | $305.00 |
| 0415 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 125.80 | $131.84 | $190.00 | $199.36 | $153.00 |
| 0420 | Guardrail -roadway, general (0536-1-1) | LF | 1,639 | $34.70 | $27.00 | $28.33 | $27.00 |
| 0425 | Guardrail transition to rigid barrier, F&I- index 536- 001, approach TL-3 (0536-8112) | EACH | 8 | $3,855.33 | $3,000.00 | $3,147.89 | $3,000.00 |
| 0430 | Guardrail removal (0536-73) | LF | 1,437 | $2.57 | $2.00 | $5.00 | $2.00 |
| 0435 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 4 | $3,855.33 | $3,000.00 | $3,147.89 | $3,000.00 |
| 0440 | Guardrail end treatment- type CRT (0536-85-26) | EACH | 2 | $4,497.89 | $3,500.00 | $3,672.53 | $3,500.00 |
| 0445 | Retaining wall system, permanent, excluding barrier (0548-12) | SF | 3,382 | $69.93 | $75.00 | $136.76 | $105.00 |
| 0450 | Retaining wall system,temporary, excluding barrier (0548-13) | SF | 6,227 | $24.98 | $27.50 | $31.45 | $25.00 |
| 0455 | Fencing, wood fence, 0.0-5.0' (0550-10410) | LF | 120 | $25.70 | $32.39 | $52.46 | $33.00 |
| 0460 | Performance turf (0570-1-1) | SY | 5,129 | $1.93 | $3.50 | $3.50 | $7.00 |
| 0465 | Performance turf, sod (0570-1-2) | SY | 13,296 | $4.50 | $1.50 | $3.85 | $8.00 |
| 0470 | Plastic erosion mat, turf reinforced mat, type 3 (0571-1-13) | SY | 5,954 | $3.85 | $17.50 | $18.36 | $16.00 |
| 0475 | Raised pavement marker, type B (0706-1-3) | EACH | 2,752 | $6.43 | $5.00 | $5.25 | $10.00 |
| 0480 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 2.36 | $2,377.46 | $1,850.00 | $1,888.73 | $1,850.00 |
| 0485 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 2.35 | $2,377.46 | $1,850.00 | $1,888.73 | $1,850.00 |
| 0490 | Biosorption activated media, bam- filter strip (0917-532-11) | CY | 1,061.80 | $575.41 | $700.00 | $835.00 | $620.20 |
| 0495 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $150,000 | $150,000 | $150,000 | $150,000 |
| 0500 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 1.45 | $10,923 | $8,500.00 | $9,000.00 | $8,500.00 |
| 0505 | Single column ground sign assembly, relocate (0700-1500) | EACH | 20 | $128.51 | $100.00 | $110.00 | $100.00 |
| 0510 | Single column ground sign assembly, remove (0700-1600) | EACH | 7 | $64.25 | $25.00 | $100.00 | $50.00 |
| 0515 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 1 | $10,024 | $7,500.00 | $8,000.00 | $7,800.00 |
| 0520 | Multi-column ground sign assembly, relocate (0700-2500) | EACH | 3 | $1,220.85 | $2,500.00 | $2,600.00 | $950.00 |
| 0525 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 1 | $835.33 | $250.00 | $500.00 | $650.00 |
| 0530 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 1 | $321.27 | $50.00 | $100.00 | $250.00 |
| 0535 | Enhanced highway sign solar powered, relocate - ground mount (0700-142802) | EACH | 1 | $2,313.20 | $1,000.00 | $1,500.00 | $1,800.00 |
| 0540 | Raised pavement marker, type B (0706-1-3) | EACH | 155 | $7.71 | $6.00 | $5.25 | $10.00 |
| 0545 | Painted pavement markings, surface (0710-90) | LS | 1 | $7,325.14 | $5,700.00 | $5,000.00 | $5,700.00 |
| 0550 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 144 | $10.28 | $8.00 | $11.00 | $8.00 |
| 0555 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 35 | $12.85 | $10.00 | $25.00 | $10.00 |
| 0560 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 1 | $257.02 | $200.00 | $500.00 | $200.00 |
| 0565 | Thermoplastic, standard, arrow (0711-11170) | EACH | 3 | $192.77 | $150.00 | $125.00 | $150.00 |
| 0570 | Thermoplastic, standard, blue, solid,6" (0711-11421) | LF | 44 | $6.43 | $5.00 | $15.00 | $5.00 |
| 0575 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 1.14 | $8,031.95 | $6,250.00 | $7,000.00 | $6,250.00 |
| 0580 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.68 | $8,031.95 | $6,250.00 | $7,000.00 | $6,250.00 |
| 0585 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.22 | $3,662.56 | $2,850.00 | $3,672.53 | $2,850.00 |
| 0590 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.16 | $38,553 | $30,000 | $50,000 | $30,000 |
| 0595 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.16 | $38,553 | $30,000 | $50,000 | $30,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of March 25, 2026. Compiled by Mirage Metrics.