FDOT contract T4697 bid tabulation
SR 5 (US 1) FROM 59TH ST TO SR 850 (NORTHLAKE BLVD). Let by Florida DOT on February 26, 2025, Palm Beach, District 4. 4 bids received; low bid $13,446,097 by Ohla USA Inc.
- Owner
- Florida DOT
- Letting
- 26 FEB 2025
- Pay items
- 185
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ohla USA Inc | $13,446,097 | Low |
| 2 | General Asphalt Company, LLC | $14,411,329 | +7.0% |
| 3 | Roadway Construction, LLC | $14,452,514 | +7.0% |
| 4 | Halley Engineering Contractors, Inc. | $20,862,855 | +55% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ohla USA Inc | 2. General Asphalt Company, LLC | 3. Roadway Construction, LLC | 4. Halley Engineering Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 0005 | Removal of existing structures/bridges (0110-3) | SF | 1 | $1,000,000 | $171,749 | $145,550 | $336,000 |
| 0010 | Cleaning & coating concrete surface, class 5 (0400-143) | SF | 41,659 | $1.60 | $3.54 | $3.00 | $3.60 |
| 0015 | Epoxy material for crack injection- structures rehab (0411-1) | GA | 2 | $158.00 | $1,770.00 | $1,500.00 | $1,800.00 |
| 0020 | Cracks inject & seal- structures rehab (0411-2) | LF | 351 | $195.00 | $339.84 | $288.00 | $345.00 |
| 0025 | Methacrylate monomer (0413-151) | GA | 1,964 | $68.00 | $89.68 | $76.00 | $92.00 |
| 0030 | Cleaning & sealing concrete surfaces - penetrant sealer or methacrylates (0413-154) | SF | 196,394 | $1.50 | $2.21 | $1.87 | $2.25 |
| 0035 | Bridge deck expansion joint, rehabilitation, strip seal (0458-1-22) | LF | 405 | $185.00 | $954.62 | $809.00 | $971.00 |
| 0040 | Concrete traffic railing- 36" single-slope (0521-5-13) | LF | 3,880 | $97.00 | $239.54 | $203.00 | $244.00 |
| 0045 | Mobilization (0101-1) | LS | 1 | $1,340,000 | $500,000 | $1,445,200 | $1,917,000 |
| 0050 | Maintenance of traffic (0102-1) | DA | 1 | $849,000 | $1,800,000 | $2,000,000 | $2,800,000 |
| 0055 | Special detour- temporary pavement (0102-2200) | SY | 1 | $1.00 | $75,506 | $205,975 | $273,000 |
| 0060 | Traffic control officer (0102-14) | HR | 452 | $71.00 | $94.40 | $70.00 | $110.00 |
| 0065 | Work zone sign (0102-60) | ED | 15,036 | $0.19 | $0.25 | $0.19 | $0.19 |
| 0070 | Barrier mounted work zone sign- index 700-013 (0102-62-13) | ED | 2,286 | $0.85 | $1.00 | $0.85 | $1.90 |
| 0075 | Temporary barrier, F&I, free standing (0102-71-16) | LF | 934 | $27.70 | $46.02 | $45.91 | $23.00 |
| 0080 | Temporary barrier, relocate, free standing (0102-71-26) | LF | 934 | $10.20 | $18.88 | $18.83 | $8.50 |
| 0085 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 230,769 | $0.09 | $0.12 | $0.09 | $0.25 |
| 0090 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 4,040 | $0.07 | $0.12 | $0.07 | $0.06 |
| 0095 | Arrow board / advance warning arrow panel (0102-76) | ED | 1,386 | $5.00 | $5.90 | $5.00 | $5.00 |
| 0100 | Temporary crash cushion, redirective option (0102-89-1) | LO | 2 | $960.00 | $1,132.80 | $960.00 | $1,100.00 |
| 0105 | Portable changeable message sign, temporary (0102-99) | ED | 1,386 | $8.90 | $11.68 | $8.90 | $9.00 |
| 0110 | Temporary signalization and maintenance, intersection (0102-104) | ED | 6,237 | $28.00 | $5.90 | $14.00 | $14.00 |
| 0115 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 6,237 | $23.10 | $1.18 | $15.00 | $15.00 |
| 0120 | Type III barricade (0102-115) | ED | 1,386 | $0.25 | $0.42 | $0.25 | $0.23 |
| 0125 | Removable tape, white, solid 6" (0102-913-21) | GM | 2.06 | $10,500 | $12,217 | $10,338 | $10,353 |
| 0130 | Removable tape, yellow, solid, (0102-913-31) | GM | 1.85 | $10,500 | $12,217 | $10,336 | $10,353 |
| 0135 | Inlet protection system (0104-18) | EACH | 160 | $253.00 | $141.60 | $169.92 | $125.00 |
| 0140 | Litter removal (0107-1) | ACRE | 186.26 | $50.00 | $0.01 | $0.01 | $50.00 |
| 0145 | Mowing (0107-2) | ACRE | 90.44 | $101.00 | $0.01 | $0.01 | $250.00 |
| 0150 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $37,563 | $1.18 | $4,000.00 | $15,000 |
| 0155 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $10,150 | $1.18 | $10,000 | $15,000 |
| 0160 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $835,000 | $131,192 | $820,710 | $2,700,000 |
| 0165 | Removal of existing concrete (0110-4-10) | SY | 6,884 | $40.00 | $40.12 | $41.42 | $50.00 |
| 0170 | Tree protection barrier (0110-21) | LF | 991 | $10.00 | $5.31 | $9.56 | $5.00 |
| 0175 | Borrow excavation, truck measure (0120-2-2) | CY | 1,167 | $20.00 | $191.16 | $29.92 | $25.00 |
| 0180 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $20,037 | $78,942 | $14,592 | $799,000 |
| 0185 | Type B stabilization (0160-4) | SY | 4,329 | $0.01 | $9.44 | $28.08 | $0.01 |
| 0190 | Optional base, base group 09 (0285-709) | SY | 3,846 | $80.00 | $53.96 | $33.82 | $146.00 |
| 0195 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 100,524 | $3.00 | $3.05 | $3.23 | $7.00 |
| 0200 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 345.60 | $245.00 | $257.39 | $190.62 | $539.00 |
| 0205 | Asphalt concrete friction course,traffic C, FC-9.5, PG 76-22 (0337-7-82) | TN | 8,481.30 | $185.00 | $214.78 | $227.52 | $295.00 |
| 0210 | Inlets, curb, type P-3, <10' (0425-1331) | EACH | 1 | $10,900 | $19,470 | $12,364 | $9,500.00 |
| 0215 | Inlets, curb, type P-3, partial (0425-1335) | EACH | 3 | $10,900 | $6,626.88 | $6,850.95 | $7,000.00 |
| 0220 | Inlets, curb, type P-5, <10' (0425-1351) | EACH | 2 | $10,900 | $12,853 | $8,961.51 | $8,500.00 |
| 0225 | Inlets, barrier wall, rigid, curb & gutter, <=10' (0425-1881) | EACH | 12 | $14,000 | $31,662 | $6,588.15 | $17,000 |
| 0230 | Manhole, adjust (0425-5) | EACH | 73 | $900.00 | $1,003.00 | $600.00 | $900.00 |
| 0235 | Manhole, adjust, utilities (0425-5-1) | EACH | 4 | $1,000.00 | $885.00 | $600.00 | $900.00 |
| 0240 | Valve boxes, adjust (0425-6) | EACH | 116 | $777.00 | $855.50 | $489.06 | $700.00 |
| 0245 | Meter boxes, adjust (0425-6-1) | EACH | 2 | $777.00 | $944.00 | $1,022.74 | $1,000.00 |
| 0250 | Pipe culvert optional material, round, 18", gutter drain (0430-173118) | LF | 30 | $360.00 | $306.80 | $454.45 | $2,400.00 |
| 0255 | Pipe liner, cured in place, 30" (0431-1130) | LF | 424 | $225.00 | $244.61 | $207.30 | $208.00 |
| 0260 | Pipe liner, cured in place, 48" (0431-1148) | LF | 202 | $510.00 | $554.84 | $470.20 | $471.00 |
| 0265 | Bullet rail, single rail (0515-4-1) | LF | 193 | $90.00 | $102.66 | $52.50 | $87.00 |
| 0270 | Concrete curb & gutter, type F (0520-1-10) | LF | 2,758 | $49.00 | $63.72 | $36.20 | $38.00 |
| 0275 | Concrete curb, type D (0520-2-4) | LF | 8,928 | $38.00 | $37.17 | $29.72 | $34.00 |
| 0280 | Concrete traffic separator, special- variable width (0520-70) | SY | 1,164 | $90.00 | $161.66 | $133.09 | $106.00 |
| 0285 | Shoulder concrete barrier, curb and gutter barrier (0521-72-43) | LF | 661 | $215.00 | $381.14 | $323.00 | $340.00 |
| 0290 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 1,462 | $70.00 | $99.12 | $64.09 | $67.00 |
| 0295 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 2,429 | $90.00 | $119.18 | $92.24 | $75.00 |
| 0300 | Patterned pavement (0523-3) | SY | 929 | $260.00 | $191.16 | $162.00 | $172.00 |
| 0305 | Detectable warnings (0527-2) | SF | 1,125 | $46.00 | $42.48 | $35.73 | $55.00 |
| 0310 | Crash cushion, TL-2, narrow (0544-2-1) | EACH | 2 | $29,250 | $32,450 | $21,500 | $33,000 |
| 0315 | Performance turf, sod (0570-1-2) | SY | 4,542 | $7.75 | $4.25 | $7.77 | $11.50 |
| 0320 | Irrigation system- modify existing system (0590-70-5) | LS | 1 | $55,750 | $65,785 | $79,739 | $85,000 |
| 0325 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 8 | $2,200.00 | $2,324.60 | $2,350.00 | $2,350.00 |
| 0330 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 8 | $2,575.00 | $1,121.00 | $2,350.00 | $2,350.00 |
| 0335 | Raised pavement marker, type B (0706-1-3) | EACH | 1,838 | $4.00 | $4.43 | $3.75 | $3.75 |
| 0340 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 9.16 | $1,500.00 | $2,065.00 | $1,748.66 | $1,750.00 |
| 0345 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.14 | $1,550.00 | $2,755.30 | $2,421.48 | $2,335.00 |
| 0350 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 508 | $3.00 | $1.83 | $1.55 | $1.55 |
| 0355 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 2,867 | $3.25 | $1.95 | $1.65 | $1.65 |
| 0360 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 4.53 | $800.00 | $590.00 | $500.55 | $500.00 |
| 0365 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 3.75 | $800.00 | $796.50 | $675.54 | $675.00 |
| 0370 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 76 | $85.00 | $47.20 | $40.00 | $40.00 |
| 0375 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 106 | $35.00 | $47.20 | $40.00 | $40.00 |
| 0380 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 5.02 | $1,500.00 | $2,065.00 | $1,751.40 | $1,750.00 |
| 0385 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 115 | $3.00 | $1.83 | $1.55 | $1.55 |
| 0390 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 0.15 | $800.00 | $590.00 | $496.69 | $500.00 |
| 0395 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.19 | $775.00 | $796.50 | $586.34 | $675.00 |
| 0400 | Painted pavement markings, standard, yellow, island nose (0710-11290) | SF | 98 | $10.00 | $4.72 | $4.00 | $4.00 |
| 0405 | Directional indicators (0919-528100) | SF | 48 | $105.00 | $59.00 | $221.00 | $120.00 |
| 0410 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0415 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $131,563 | $131,563 | $131,563 | $131,563 |
| 0420 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $665.00 | $665.00 | $665.00 | $665.00 |
| 0425 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $5,225.00 | $5,225.00 | $5,225.00 | $5,225.00 |
| 0430 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $19,807 | $19,807 | $19,807 | $19,807 |
| 0435 | Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 12" (1050-51212) | LF | 120 | $265.00 | $74.34 | $282.94 | $63.00 |
| 0440 | Utility fittings, ductile iron, furnish & install elbow, (1055-51112) | EACH | 12 | $3,300.00 | $885.00 | $2,535.21 | $750.00 |
| 0445 | Utility fittings, ductile iron, furnish & install union, 12" (1055-51412) | EACH | 24 | $4,000.00 | $855.50 | $1,743.95 | $725.00 |
| 0450 | Utility structure, below ground, adjust/modify (1060-15) | EACH | 1 | $2,065.00 | $6,136.00 | $3,253.28 | $5,200.00 |
| 0455 | Utility fixture, valve/meter box, relocate (1080-21400) | EACH | 8 | $7,775.00 | $3,658.00 | $511.37 | $3,100.00 |
| 0460 | Fire hydrant, relocate (1644-800) | EACH | 1 | $13,500 | $6,490.00 | $12,924 | $5,500.00 |
| 0465 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 62 | $520.00 | $613.60 | $400.00 | $520.00 |
| 0470 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 17 | $1,900.00 | $2,242.00 | $1,300.00 | $1,900.00 |
| 0475 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 15 | $2,400.00 | $2,832.00 | $1,600.00 | $2,400.00 |
| 0480 | Single column ground sign assembly, F&I barrier 12.0-20.0 SF (0700-1312) | EACH | 1 | $4,000.00 | $4,720.00 | $285.00 | $4,000.00 |
| 0485 | Single column ground sign assembly, F&I barrier 20.1-30.0 SF (0700-1313) | EACH | 1 | $5,000.00 | $5,900.00 | $1,300.00 | $5,000.00 |
| 0490 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $750.00 | $885.00 | $850.00 | $750.00 |
| 0495 | Single column ground sign assembly, remove (0700-1600) | EACH | 48 | $30.00 | $35.40 | $10.00 | $30.00 |
| 0500 | Multi-column ground sign assembly, F&I ground mount, 20.0 SF (0700-2112) | EACH | 3 | $6,000.00 | $7,080.00 | $3,000.00 | $6,000.00 |
| 0505 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 3 | $2,000.00 | $2,360.00 | $650.00 | $2,000.00 |
| 0510 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 2 | $275.00 | $324.50 | $250.00 | $275.00 |
| 0515 | Retroreflective sign strip- furnish and install, 2' (0700-13-12) | EACH | 44 | $100.00 | $118.00 | $55.00 | $100.00 |
| 0520 | Tubular marker, 36" yellow (0704-1-4) | EACH | 53 | $225.00 | $265.50 | $350.00 | $225.00 |
| 0525 | Object marker, type 1 (0705-10-1) | EACH | 1 | $350.00 | $413.00 | $275.00 | $350.00 |
| 0530 | Delineator, flexible tubular (0705-11-1) | EACH | 50 | $100.00 | $118.00 | $150.00 | $100.00 |
| 0535 | Raised pavement marker, type B (0706-1-3) | EACH | 1,838 | $4.00 | $4.48 | $3.80 | $3.80 |
| 0540 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 98 | $10.00 | $5.90 | $5.00 | $5.00 |
| 0545 | Painted pavement markings, surface (0710-90) | LS | 1 | $50,000 | $48,011 | $40,687 | $40,687 |
| 0550 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 7,459 | $3.00 | $3.65 | $3.09 | $3.09 |
| 0555 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 461 | $5.00 | $5.48 | $4.64 | $4.64 |
| 0560 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 2,986 | $6.00 | $7.29 | $6.18 | $6.18 |
| 0565 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 2.14 | $3,000.00 | $2,655.00 | $2,246.85 | $2,250.00 |
| 0570 | Thermoplastic, standard, arrow (0711-11170) | EACH | 120 | $90.00 | $64.90 | $55.00 | $55.00 |
| 0575 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 120 | $5.00 | $5.33 | $4.52 | $4.52 |
| 0580 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.45 | $3,000.00 | $2,655.00 | $2,275.28 | $2,250.00 |
| 0585 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 81 | $190.00 | $238.36 | $202.00 | $202.00 |
| 0590 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 81 | $95.00 | $101.48 | $86.00 | $86.00 |
| 0595 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 5.85 | $5,200.00 | $5,730.08 | $4,853.51 | $4,856.00 |
| 0600 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.11 | $6,000.00 | $7,640.50 | $6,594.91 | $6,475.00 |
| 0605 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 4.49 | $3,000.00 | $1,432.52 | $1,214.54 | $1,214.00 |
| 0610 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 5.28 | $5,200.00 | $5,371.36 | $4,549.42 | $4,552.00 |
| 0615 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.15 | $3,000.00 | $1,342.84 | $1,130.46 | $1,138.00 |
| 0620 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.74 | $27,300 | $37,620 | $31,664 | $31,881 |
| 0625 | Permanent tape, white, 6-10 skip/dotted, 6" for concrete surfaces (0713-103141) | GM | 0.74 | $7,445.00 | $9,405.78 | $7,916.78 | $7,971.00 |
| 0630 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.74 | $27,315 | $37,620 | $31,664 | $31,881 |
| 0635 | Permanent tape, black, 6-10 dotted extension, 6" for concrete surfaces (0713-103341) | GM | 0.73 | $8,400.00 | $9,150.90 | $7,787.00 | $7,555.00 |
| 0640 | Preformed/permanent tape, remove (0713-107) | SF | 5,823 | $2.00 | $2.01 | $1.70 | $1.70 |
| 0645 | Green-colored pavement markings, bike lane (0714-10) | SF | 1,143 | $8.00 | $10.50 | $8.90 | $8.90 |
| 0650 | Channelizing curb, centerline (0921-703100) | LF | 7 | $200.00 | $64.90 | $1,000.00 | $175.00 |
| 0655 | Conduit, furnish & install, open trench (0630-2-11) | LF | 94 | $19.50 | $23.60 | $18.60 | $18.60 |
| 0660 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,393 | $27.00 | $31.86 | $21.40 | $21.40 |
| 0665 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 59 | $1,075.00 | $2,731.70 | $1,095.00 | $1,095.00 |
| 0670 | Electrical power service, F&I, overhead meter purchased by contractor from power company (0639-1112) | AS | 2 | $4,575.00 | $8,272.98 | $10,721 | $8,322.00 |
| 0675 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $4,250.00 | $7,493.00 | $10,721 | $8,322.00 |
| 0680 | Lighting conductors, F&I, insulated, no. 10 or < (0715-1-11) | LF | 2,400 | $1.50 | $1.48 | $2.50 | $2.50 |
| 0685 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 11,008 | $2.50 | $3.54 | $3.30 | $3.30 |
| 0690 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 4,458 | $1.40 | $1.18 | $0.20 | $0.20 |
| 0695 | Luminaire & bracket arm, luminaire and arm on existing pole (0715-5-21) | EACH | 2 | $2,065.00 | $6,189.10 | $5,240.40 | $5,241.00 |
| 0700 | Luminaire & bracket arm, luminaire and arm; pole remains (0715-5-51) | EACH | 1 | $478.00 | $472.00 | $426.70 | $427.00 |
| 0705 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 35 | $1,425.00 | $1,463.20 | $990.20 | $991.00 |
| 0710 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, pendant/teardrop (0715-11216) | EACH | 86 | $4,400.00 | $5,451.60 | $4,335.00 | $4,335.00 |
| 0715 | Light pole complete, F&I, standard pole special foundation, 30' mounting height, 8' arm length (0715-62111) | EACH | 1 | $9,800.00 | $12,591 | $11,065 | $11,065 |
| 0720 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 137 | $630.00 | $979.40 | $734.50 | $735.00 |
| 0725 | Light pole complete- special design, F&I, single arm shoulder mount, concrete, 20' (0715-511320) | EACH | 3 | $19,050 | $21,240 | $14,847 | $14,847 |
| 0730 | Light pole complete- special design, F&I, single arm shoulder mount, concrete, 30' (0715-511330) | EACH | 9 | $20,500 | $28,473 | $22,010 | $22,010 |
| 0735 | Conduit, furnish & install, open trench (0630-2-11) | LF | 909 | $19.50 | $20.06 | $23.80 | $23.80 |
| 0740 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 2,526 | $33.00 | $61.36 | $25.20 | $25.20 |
| 0745 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 18 | $57.00 | $65.49 | $48.10 | $48.10 |
| 0750 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 9 | $10,100 | $5,439.80 | $14,502 | $14,502 |
| 0755 | Signal cable, remove- intersection (0632-7-6) | PI | 9 | $2,000.00 | $1,834.90 | $1,000.00 | $1,000.00 |
| 0760 | Fiber optic cable, relocate, underground (0633-1420) | LF | 10 | $220.00 | $106.20 | $4.00 | $4.00 |
| 0765 | Fiber optic cable locator (0633-6) | DA | 693 | $270.00 | $236.00 | $0.01 | $233.00 |
| 0770 | Span wire assembly, F&I, two point, box or drop box (0634-4153) | PI | 1 | $13,600 | $11,936 | $7,660.40 | $7,661.00 |
| 0775 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 94 | $1,075.00 | $1,581.20 | $1,461.60 | $1,000.00 |
| 0780 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 2 | $2,000.00 | $4,454.50 | $3,636.19 | $2,400.00 |
| 0785 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 76 | $1,560.00 | $2,360.00 | $1,638.75 | $1,200.00 |
| 0790 | Pull & splice box, F&I, 30" X 48" cover size (0635-2-15) | EACH | 6 | $2,125.00 | $4,973.70 | $4,731.02 | $3,950.00 |
| 0795 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 8 | $2,500.00 | $4,973.70 | $5,600.00 | $5,600.00 |
| 0800 | Electrical service wire, & install (0639-2-1) | LF | 625 | $10.20 | $9.44 | $15.00 | $15.00 |
| 0805 | Electrical service wire, relocate (0639-2-4) | LF | 10 | $10.20 | $10.92 | $2.00 | $2.00 |
| 0810 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 8 | $550.00 | $2,997.20 | $2,140.00 | $2,140.00 |
| 0815 | Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60) | EACH | 6 | $250.00 | $2,832.00 | $400.00 | $401.00 |
| 0820 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 8 | $1,675.00 | $2,613.70 | $2,050.00 | $2,050.00 |
| 0825 | Prestressed concrete pole, type P-VIII (0641-2-18) | EACH | 1 | $22,150 | $21,677 | $10,837 | $10,837 |
| 0830 | Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60) | EACH | 1 | $14,100 | $372.29 | $500.00 | $500.00 |
| 0835 | Prestressed concrete pole, shallow pole removal- pole 30' and greater (0641-2-70) | EACH | 1 | $12,100 | $10,738 | $2,133.50 | $2,134.00 |
| 0840 | Strain pole, wood, remove (0643-600) | EACH | 2 | $1,500.00 | $1,569.40 | $533.40 | $534.00 |
| 0845 | Aluminum signals pole, (0646-1-11) | EACH | 37 | $2,400.00 | $2,961.80 | $1,850.00 | $1,850.00 |
| 0850 | Aluminum signals pole, remove (0646-1-60) | EACH | 19 | $440.00 | $371.70 | $400.10 | $401.00 |
| 0855 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 4 | $2,110.00 | $2,112.20 | $1,300.00 | $1,300.00 |
| 0860 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 4 | $150.00 | $253.70 | $150.00 | $150.00 |
| 0865 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 75 | $755.00 | $743.40 | $550.00 | $550.00 |
| 0870 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 35 | $1,000.00 | $985.30 | $760.00 | $760.00 |
| 0875 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 11 | $1,675.00 | $8,419.30 | $1,525.00 | $1,525.00 |
| 0880 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 21 | $240.00 | $188.80 | $75.00 | $75.00 |
| 0885 | Loop detector inductive, F&I, type 10 (0660-1110) | EACH | 60 | $955.00 | $519.20 | $400.00 | $400.00 |
| 0890 | Loop assembly, F&I, type F (0660-2106) | AS | 77 | $2,200.00 | $1,480.90 | $2,200.10 | $2,201.00 |
| 0895 | Vehicle detection system- remove cabinet equipment (0660-4-61) | EACH | 4 | $350.00 | $708.00 | $350.00 | $350.00 |
| 0900 | Vehicle detection system- remove above ground (0660-4-62) | EACH | 16 | $450.00 | $1,227.20 | $350.00 | $350.00 |
| 0905 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 55 | $380.00 | $377.60 | $380.00 | $380.00 |
| 0910 | Pedestrian detector, furnish & install, accessible (0665-1-12) | EACH | 2 | $1,360.00 | $4,147.70 | $1,900.00 | $1,900.00 |
| 0915 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 21 | $95.00 | $125.08 | $75.00 | $75.00 |
| 0920 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 9 | $1,700.00 | $2,360.00 | $6,520.00 | $6,520.00 |
| 0925 | Relocate trees and palms, palms, <10.0" DBH, <14.0' of clear trunk (0581-1271) | EACH | 1 | $1,500.00 | $8,260.00 | $7,000.00 | $7,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of February 26, 2025. Compiled by Mirage Metrics.