FDOT contract T4726 bid tabulation
UTOPIA DR FROM RIVIERA BLVD TO SR 824 (PEMBROKE RD). Let by Florida DOT on July 30, 2025, Broward, District 4. 6 bids received; low bid $1,400,000 by Pedrail Systems LLC.
- Owner
- Florida DOT
- Letting
- 30 JUL 2025
- Pay items
- 39
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pedrail Systems LLC | $1,400,000 | Low |
| 2 | General Asphalt Company, LLC | $1,481,919 | +6.0% |
| 3 | Roadway Construction, LLC | $1,636,235 | +17% |
| 4 | The Stout Group LLC | $1,685,689 | +20% |
| 5 | Florida Engineering & Development Corp | $1,789,121 | +28% |
| 6 | Weekley Asphalt Paving, Inc. | $1,870,312 | +34% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pedrail Systems LLC | 2. General Asphalt Company, LLC | 3. Roadway Construction, LLC | 4. The Stout Group LLC | 5. Florida Engineering & Development Corp | 6. Weekley Asphalt Paving, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $420,000 | $100,000 | $163,624 | $150,000 | $178,000 | $126,445 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $80,000 | $171,000 | $35,000 | $150,000 | $135,000 | $209,590 |
| 0015 | Work zone sign (0102-60) | ED | 1,653 | $1.00 | $0.35 | $0.32 | $0.32 | $0.33 | $0.32 |
| 0020 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 1,218 | $1.00 | $0.22 | $0.20 | $0.20 | $0.21 | $0.20 |
| 0025 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 2,045 | $0.05 | $0.11 | $0.10 | $0.10 | $0.10 | $0.10 |
| 0030 | Portable changeable message sign, temporary (0102-99) | ED | 404 | $16.00 | $15.40 | $14.00 | $14.00 | $14.42 | $14.00 |
| 0035 | Sediment barrier (0104-10-3) | LF | 6,211 | $2.00 | $0.01 | $2.63 | $8.00 | $1.86 | $1.90 |
| 0040 | Inlet protection system (0104-18) | EACH | 18 | $150.00 | $203.50 | $226.41 | $150.00 | $99.89 | $160.00 |
| 0045 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $41,899 | $55,220 | $410,981 | $65,000 | $110,000 | $210,668 |
| 0050 | Removal of existing concrete (0110-4-10) | SY | 13 | $50.00 | $110.00 | $98.97 | $50.00 | $50.92 | $150.00 |
| 0055 | Tree protection barrier (0110-21) | LF | 3,642 | $1.00 | $5.50 | $4.39 | $10.00 | $11.40 | $11.15 |
| 0060 | Tree root and branch pruning (0110-22) | EACH | 209 | $50.00 | $990.00 | $991.00 | $350.00 | $1,287.50 | $1,223.00 |
| 0065 | Tree removal (0110-23) | EACH | 23 | $1,100.00 | $2,200.00 | $3,500.00 | $1,850.00 | $515.00 | $3,115.00 |
| 0070 | Regular excavation (0120-1) | CY | 3,719.10 | $10.00 | $37.73 | $18.55 | $40.00 | $74.00 | $29.00 |
| 0075 | Embankment (0120-6) | CY | 153.10 | $20.00 | $28.71 | $18.59 | $95.00 | $103.45 | $44.00 |
| 0080 | Type B stabilization (0160-4) | SY | 7,267 | $2.00 | $9.46 | $14.29 | $25.00 | $17.37 | $19.00 |
| 0085 | Optional base, base group 01 (0285-701) | SY | 4,435 | $26.00 | $17.82 | $11.20 | $40.00 | $25.49 | $34.10 |
| 0090 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 365.90 | $295.00 | $181.47 | $156.18 | $300.00 | $195.41 | $200.00 |
| 0095 | Miscellaneous asphalt (0339-1) | TN | 103.70 | $250.00 | $263.09 | $165.50 | $350.00 | $353.89 | $300.00 |
| 0100 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 87 | $50.00 | $198.00 | $85.43 | $150.00 | $96.59 | $181.55 |
| 0105 | Detectable warnings (0527-2) | SF | 60 | $35.00 | $44.00 | $29.58 | $40.00 | $40.83 | $49.00 |
| 0110 | Guardrail -roadway, general/low speed TL-2 (0536-1-0) | LF | 1,331 | $28.00 | $21.49 | $16.43 | $18.33 | $20.13 | $19.54 |
| 0115 | Guardrail removal (0536-73) | LF | 344 | $5.00 | $0.61 | $3.13 | $2.05 | $0.57 | $0.55 |
| 0120 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 2 | $1,800.00 | $1,630.45 | $1,721.09 | $1,297.25 | $1,526.70 | $1,490.00 |
| 0125 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 32 | $3,400.00 | $2,857.23 | $2,920.63 | $2,891.18 | $2,675.40 | $2,600.00 |
| 0130 | Performance turf, sod (0570-1-2) | SY | 8,626 | $6.50 | $9.00 | $8.39 | $8.00 | $6.17 | $5.75 |
| 0135 | Bench, F&I, steel (0751-38-14) | EACH | 24 | $1,500.00 | $3,080.00 | $1,437.81 | $2,250.00 | $1,177.75 | $1,500.00 |
| 0140 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0145 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 44 | $750.00 | $561.28 | $450.00 | $600.00 | $561.35 | $567.00 |
| 0150 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $250.00 | $495.00 | $340.00 | $600.00 | $437.75 | $500.00 |
| 0155 | Single column ground sign assembly, remove (0700-1600) | EACH | 31 | $50.00 | $33.00 | $35.00 | $50.00 | $10.30 | $34.00 |
| 0160 | Object marker, type 1 (0705-10-1) | EACH | 57 | $300.00 | $385.00 | $250.00 | $400.00 | $360.50 | $390.00 |
| 0165 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 59 | $50.00 | $42.00 | $20.00 | $69.32 | $28.32 | $43.00 |
| 0170 | Conduit, furnish & install, open trench (0630-2-11) | LF | 873 | $35.00 | $45.32 | $25.00 | $41.20 | $42.44 | $36.00 |
| 0175 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 5 | $2,000.00 | $1,591.59 | $1,000.00 | $1,446.90 | $1,490.31 | $1,600.00 |
| 0180 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 4,570 | $10.00 | $3.96 | $2.00 | $3.60 | $3.71 | $4.00 |
| 0185 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 4,305 | $5.00 | $0.11 | $0.63 | $0.10 | $0.10 | $2.00 |
| 0190 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 2 | $1,500.00 | $851.84 | $658.00 | $774.40 | $797.63 | $1,500.00 |
| 0195 | Light pole complete-special design, F&I, pole top mount, aluminum, 10' (0715-516110) | EACH | 2 | $12,000 | $8,086.98 | $16,225 | $7,351.80 | $7,572.36 | $18,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of July 30, 2025. Compiled by Mirage Metrics.