FDOT contract T5837 bid tabulation

SR 5 FROM MYERS DR TO CRANE CREEK BRIDGE, NO 700006. Let by Florida DOT on March 26, 2025, Brevard, District 5. 3 bids received; low bid $10,009,766 by Timothy Rose Contracting, Inc..

Owner
Florida DOT
Letting
26 MAR 2025
Pay items
159
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Timothy Rose Contracting, Inc.$10,009,766Low
2Ohla USA Inc$10,611,470+6.0%
3Preferred Materials Inc.$12,890,566+29%
FDOT contract T5837: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Timothy Rose Contracting, Inc.2. Ohla USA Inc3. Preferred Materials Inc.
0005Mobilization (0101-1)LS1$515,554$830,000$1,415,000
0010Maintenance of traffic (0102-1)DA1$348,191$795,000$855,000
0015Traffic control officer (0102-14)HR288$86.25$75.00$112.50
0020Work zone sign (0102-60)ED9,140$0.25$0.22$0.22
0025Temporary barrier, F&I, low profile, concrete (0102-71-13)LF9,808$80.50$0.01$55.00
0030Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED29,100$0.01$0.10$0.09
0035Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD2,960$0.12$0.10$0.15
0040Arrow board / advance warning arrow panel (0102-76)ED320$8.05$7.00$4.50
0045Portable changeable message sign, temporary (0102-99)ED514$10.35$9.00$9.75
0050Temporary signalization and maintenance, intersection (0102-104)ED1,000$27.60$39.00$31.50
0055Temporary traffic detection and maintenance, intersection (0102-107-1)ED1,000$32.43$18.00$1.00
0060Inlet protection system (0104-18)EACH68$161.00$250.00$140.00
0065Litter removal (0107-1)ACRE88.74$115.00$75.00$100.00
0070Mowing (0107-2)ACRE81.52$287.50$200.00$250.00
0075Clearing & grubbing (0110-1-1)ACRE1$23,213$500,000$28,000
0080Clearing & grubbing (0110-1-1)ACRE1$10,581$490,000$43,000
0085Removal of existing concrete (0110-4-10)SY712$35.52$24.00$121.21
0090Embankment (0120-6)CY189$78.07$74.00$154.60
0095Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2)SY70,622$4.82$4.50$7.05
0100Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY5,485$7.56$5.00$7.95
0105Milling existing asphalt pavement, 2" avg depth (0327-70-5)SY33,925$3.94$5.50$3.70
0110Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY520$8.46$16.00$10.55
0115Milling existing asphalt pavement, 4" avg depth (0327-70-7)SY701$7.95$15.00$10.35
0120Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN7,607.20$203.35$172.00$290.90
0125Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN9,647.60$200.00$190.00$294.50
0130Plain cement concrete 6" (0350-3-1)SY574$154.66$205.00$160.52
0135Inlets, curb type P-1, partial (0425-1315)EACH1$4,044.23$11,000$11,235
0140Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF81$455.39$160.00$227.60
0145Concrete curb & gutter, type E (0520-1-7)LF4,060$42.58$40.00$38.66
0150Concrete curb & gutter, type F (0520-1-10)LF1,275$42.39$47.00$48.06
0155Concrete curb, type B (0520-2-2)LF4,703$34.46$38.00$45.15
0160Concrete traffic separator, special- variable width (0520-70)SY183$150.78$170.00$147.68
0165Concrete sidewalk and driveways, 4" thick (0522-1)SY80$89.19$88.00$100.28
0170Concrete sidewalk and driveways, 6" thick (0522-2)SY552$103.70$130.00$147.30
0175Patterned pavement (0523-3)SY945$103.50$164.00$183.93
0180Pavers, architectural, (0526-1-2)SY1,748$247.96$162.00$267.00
0185Detectable warnings (0527-2)SF560$39.96$33.40$29.40
0190Performance turf, sod (0570-1-2)SY1,130$6.02$16.00$10.01
0195Performance turf, sod and shoulder treatment index (0570-1-3)SY100$10.32$50.00$25.01
0200Irrigation sleeve, 2" diameter (0591-1200)LF2,897$14.94$60.00$30.00
0205Irrigation sleeve, 4" diameter (0591-1400)LF2,897$17.41$50.00$32.00
0210Conduit, furnish & install, open trench (0630-2-11)LF45$36.91$32.50$41.00
0215Conduit, furnish & install, directional bore (0630-2-12)LF270$43.70$38.50$55.25
0220Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH4$1,984.44$1,200.00$1,205.00
0225Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH13$3,640.82$1,500.00$1,770.00
0230Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH13$2,850.88$1,835.00$1,700.00
0235Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162)EACH2$7,137.77$6,075.00$7,400.00
0240Traffic monitoring site cabinet, remove existing cabinet (0695-7600)EACH1$271.17$835.00$960.00
0245Raised pavement marker, type B (0706-1-3)EACH2,242$4.60$4.50$5.00
0250Painted pavement markings, standard, white, solid, 6" (0710-11101)GM7.76$1,578.96$2,000.00$1,655.00
0255Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF4,130$0.92$2.00$1.35
0260Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF512$1.26$3.00$3.00
0265Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF2,580$1.50$4.00$2.75
0270Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM6.99$409.86$750.00$465.00
0275Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM1.40$506.00$850.00$755.00
0280Painted pavement markings, standard, white, message or symbol (0710-11160)EACH29$57.50$65.00$85.00
0285Painted pavement markings, standard, white, arrows (0710-11170)EACH143$46.00$35.00$55.00
0290Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM3.77$1,578.96$2,000.00$1,655.00
0295Initial contingency amount, DO not bid (0999-25)LS1$108,500$108,500$108,500
0300Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH30$546.25$525.00$540.00
0305Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH17$1,955.02$1,625.00$2,100.00
0310Single column ground sign assembly, remove (0700-1600)EACH15$34.50$50.00$100.00
0315Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH10$247.25$325.00$210.00
0320Sign panel, relocate, UP to 12 SF (0700-3501)EACH32$247.25$160.00$240.00
0325Sign panel, remove, UP to 12 SF (0700-3601)EACH6$34.50$105.00$150.00
0330Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH40$10.35$152.00$175.00
0335Enhanced highway sign solar powered, F&I ground mount, W/eds, UP to 12 SF of static sign panels (0700-142131)EACH1$0.00$18,000$14,560
0340Tubular marker, 36" white post (0704-1-3)EACH8$86.25$220.00$250.00
0345Tubular marker, 36" yellow (0704-1-4)EACH24$86.25$220.00$250.00
0350Raised pavement marker, type B (0706-1-3)EACH2,579$4.60$4.50$5.00
0355Painted pavement markings, standard, white, island nose (0710-11190)SF48$6.90$5.00$10.00
0360Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF243$6.90$5.00$10.00
0365Painted pavement markings, surface (0710-90)LS1$33,350$58,000$44,500
0370Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF4,130$2.30$3.50$3.25
0375Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF575$4.60$4.50$5.50
0380Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF635$6.90$8.00$9.00
0385Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM1.40$2,530.02$2,500.00$2,700.00
0390Thermoplastic, standard, message or symbol (0711-11160)EACH8$143.75$150.00$150.00
0395Thermoplastic, standard, arrow (0711-11170)EACH122$103.50$100.00$70.00
0400Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF24$4.60$4.50$5.50
0405Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.18$2,530.02$2,445.00$2,685.00
0410Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF1,945$19.55$15.00$13.50
0415Thermoplastic, preformed, white, message (0711-14160)EACH21$230.00$200.00$255.00
0420Thermoplastic, preformed, white, arrow (0711-14170)EACH21$230.00$100.00$190.00
0425Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM7.76$7,130.06$4,895.00$3,900.00
0430Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.19$6,900.06$8,900.00$22,000
0435Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM6.99$2,415.02$1,500.00$1,700.00
0440Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133)GM0.10$3,105.03$3,000.00$15,000
0445Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM3.77$7,130.06$4,900.00$3,900.00
0450Thermoplastic, standard-other surfaces, yellow, solid, 8" (0711-16202)GM0.02$6,900.06$5,000.00$23,000
0455Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM0.03$2,530.02$1,400.00$17,000
0460Conduit, furnish & install, open trench (0630-2-11)LF277$24.15$18.00$27.00
0465Conduit, furnish & install, directional bore (0630-2-12)LF4,467$24.15$25.00$22.50
0470Conduit, furnish & install, aboveground (0630-2-14)LF70$51.75$57.00$52.25
0475Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH47$2,016.06$1,200.00$2,140.00
0480Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH2$4,143.58$3,500.00$3,770.00
0485Electrical power service, F&I, underground, meter by contractor (0639-1122)AS2$977.51$4,900.00$5,260.00
0490Electrical service disconnect, F&I, pole mount (0639-3-11)EACH2$1,322.51$1,060.00$2,460.00
0495Prestressed concrete pole, type P-II service pole (0641-2-12)EACH2$2,817.53$2,000.00$2,140.00
0500Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF16,925$3.22$3.00$3.25
0505Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13)LF692$3.56$7.00$3.50
0510Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF443$0.92$1.00$1.50
0515Load center, F&I, secondary voltage (0715-7-11)EACH2$20,125$16,500$17,420
0520Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH10$2,472.52$1,500.00$1,500.00
0525Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 8' arm length (0715-61311)EACH2$13,225$11,900$9,300.00
0530Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 12' arm length (0715-61342)EACH1$13,225$9,500.00$9,370.00
0535Light pole complete, remove pole and foundation (0715-69000)EACH2$977.51$2,450.00$1,500.00
0540Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH51$747.51$650.00$807.00
0545Light pole complete- special design, F&I, single arm shoulder mount, concrete, 30' (0715-511330)EACH38$13,376$11,900$13,125
0550Itsfm subsurface documentation- project length (0611-1-1)MI2.14$4,124.63$2,900.00$1,655.88
0555Itsfm location documentation- intersection (0611-2-1)EACH4$3,298.12$2,175.00$1,650.00
0560Conduit, furnish & install, open trench (0630-2-11)LF2,497$25.88$25.00$17.50
0565Conduit, furnish & install, directional bore (0630-2-12)LF5,687$25.88$36.00$29.00
0570Conduit, furnish & install, aboveground (0630-2-14)LF140$63.25$41.00$52.25
0575Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI2$15,525$8,530.00$14,955
0580Signal cable, remove- intersection (0632-7-6)PI2$977.51$1,330.00$1,500.00
0585Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF117$5.17$4.00$3.25
0590Fiber optic cable, F&I, underground,49-96 fibers (0633-1123)LF3,862$4.31$4.00$4.00
0595Fiber optic connection, install, splice (0633-2-31)EACH36$57.50$51.00$65.25
0600Fiber optic connection hardware, F&I, splice (0633-3-11)EACH1$1,374.26$1,350.00$1,270.00
0605Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH3$57.50$56.00$59.00
0610Fiber optic connection hardware, F&I, preterminated patch panel (0633-3-15)EACH1$2,242.52$1,675.00$1,239.00
0615Fiber optic cable locator (0633-6)DA250$287.50$330.00$240.00
0620Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH76$2,131.06$1,225.00$1,200.00
0625Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH14$4,143.58$3,500.00$3,235.00
0630Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13)EACH1$11,734$8,550.00$6,700.00
0635Electrical service wire, relocate (0639-2-4)LF40$11.50$5.00$14.00
0640Aluminum signals pole, (0646-1-11)EACH15$2,622.02$2,530.00$2,450.00
0645Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH2$2,622.02$2,530.00$2,295.00
0650Aluminum signals pole, remove (0646-1-60)EACH9$287.50$710.00$300.00
0655Vehicular traffic signal, furnish & install 3 section, 1 way (0650-1-34)AS4$1,610.01$2,100.00$1,450.00
0660Vehicular traffic signal, relocate- includes removal reinstallation (0650-1-70)AS10$1,610.01$1,250.00$800.00
0665Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- black with reflect border (0650-2102)EACH26$1,265.01$650.00$360.00
0670Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH15$747.51$670.00$555.00
0675Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS12$805.01$1,725.00$700.00
0680Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS3$1,587.01$1,975.00$690.00
0685Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS3$172.50$420.00$100.00
0690Loop detector inductive, F&I, type 9 (0660-1109)EACH47$425.50$182.00$455.00
0695Loop detector inductive, F&I, type 10 (0660-1110)EACH14$506.00$345.00$455.00
0700Loop detector inductive, remove- cabinet to remain (0660-1600)EACH18$28.75$28.00$95.00
0705Loop assembly, F&I, type B (0660-2102)AS67$2,817.53$1,725.00$1,225.00
0710Loop assembly, F&I, type F (0660-2106)AS47$2,817.53$2,550.00$1,330.00
0715Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH4$7,820.07$35,700$27,210
0720Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH4$9,487.59$11,500$7,460.00
0725Signal priority & preemption system, relocate (0663-1400)EACH1$2,127.52$2,690.00$3,365.00
0730Pedestrian detector, furnish & install, standard (0665-1-11)EACH34$483.00$425.00$270.00
0735Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH17$28.75$140.00$100.00
0740Traffic controller, modify (0671-2-40)EACH2$8,797.58$2,800.00$3,335.00
0745Traffic controller, relocate- without cabinet (0671-2-50)EACH1$3,047.53$25,000$1,940.00
0750Traffic signal controller cabinet, furnish & install without controller, NEMA 44" W X 52" H X 24" D (0676-1116)EACH1$31,050$35,350$39,980
0755Traffic signal controller cabinet, adjust/modify (0676-1500)EACH3$17,940$1,400.00$3,335.00
0760Traffic signal controller cabinet, remove (0676-1600)EACH1$1,725.02$1,400.00$940.00
0765Controller accessories, replace existing- furnish and install, load switch (0678-1104)EACH1$1,265.01$195.00$300.00
0770Managed field ethernet switch, furnish & install (0684-1-1)EACH1$7,820.07$7,225.00$4,500.00
0775Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13)EACH4$9,775.09$12,000$12,480
0780Remote power management rpmu, furnish and install (0685-2-1)EACH4$632.51$1,425.00$1,915.00
0785Sign panel, remove, UP to 12 SF (0700-3601)EACH3$28.75$265.00$125.00
0790Sign panel, remove, 12-20 SF (0700-3602)EACH4$51.75$800.00$150.00
0795Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH7$4,887.54$5,000.00$6,950.00
FDOT contract T5837: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of March 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy