FDOT contract T5859 bid tabulation

SR 500 (US 441 / ORANGE BLOSSOM TR) AT CLARCONA-OCOEE RD. Let by Florida DOT on July 30, 2025, Orange, District 5. 5 bids received; low bid $2,732,458 by American Design Engineering Construction Inc..

Owner
Florida DOT
Letting
30 JUL 2025
Pay items
133
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1American Design Engineering Construction Inc.$2,732,458Low
2National Traffic Solution, Inc$2,899,803+6.0%
3Valencia Construction Group$3,341,040+22%
4Blacktip Services Incorporated$3,405,791+25%
5Janus Construction Corp.$3,459,169+27%
FDOT contract T5859: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. American Design Engineering Construction Inc.2. National Traffic Solution, Inc3. Valencia Construction Group4. Blacktip Services Incorporated5. Janus Construction Corp.
0005Mobilization (0101-1)LS1$250,000$265,000$555,000$313,000$338,636
0010Maintenance of traffic (0102-1)DA1$45,000$265,000$234,000$45,000$381,067
0015Pedestrian or bicycle special detour (0102-4-1)SY1$15,000$19,500$9,000.00$137,000$86,363
0020Traffic control officer (0102-14)HR16$95.00$65.00$101.00$80.00$88.13
0025Work zone sign (0102-60)ED3,295$1.00$0.43$0.24$0.30$1.00
0030Temporary barrier, F&I, low profile, concrete (0102-71-13)LF384$50.00$98.00$53.63$50.00$53.00
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED23,975$2.00$0.24$0.10$0.15$0.20
0040Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD27,678$2.00$0.24$0.05$0.10$0.50
0045Arrow board / advance warning arrow panel (0102-76)ED561$30.00$24.50$5.07$5.00$5.00
0050Portable changeable message sign, temporary (0102-99)ED271$30.00$24.50$10.73$12.00$10.58
0055Temporary signalization and maintenance, intersection (0102-104)ED190$100.00$30.00$160.90$32.00$16.50
0060Temporary traffic detection and maintenance, intersection (0102-107-1)ED190$100.00$30.00$228.84$25.00$16.50
0065Type III barricade (0102-115)ED90$1.00$0.50$0.30$0.30$1.18
0070Sediment barrier (0104-10-3)LF237$15.00$4.50$6.91$10.00$4.70
0075Inlet protection system (0104-18)EACH6$150.00$195.00$297.97$65.00$177.00
0080Litter removal (0107-1)ACRE4.81$200.00$95.00$655.53$65.00$871.00
0085Mowing (0107-2)ACRE2.33$200.00$95.00$893.91$65.00$1,809.00
0090Clearing & grubbing (0110-1-1)ACRE1$25,000$25,000$40,302$494,000$251,925
0095Removal of existing concrete (0110-4-10)SY690$15.00$50.00$16.60$60.00$41.13
0100Regular excavation (0120-1)CY277.50$45.00$50.00$23.60$60.00$88.13
0105Embankment (0120-6)CY54.60$45.00$50.00$36.70$60.00$117.50
0110Type B stabilization (0160-4)SY694$35.00$50.00$16.56$60.00$118.68
0115Optional base, base group 07 (0285-707)SY558$35.00$58.85$27.00$80.00$130.43
0120Optional base, base group 13 (0285-713)SY230$150.00$58.85$184.74$90.00$106.70
0125Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY5,562$12.00$5.88$15.32$16.00$6.05
0130Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY1,943$12.00$5.29$17.52$9.00$7.15
0135Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN516.70$250.00$299.99$362.85$275.00$237.60
0140Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN670.20$250.00$299.99$559.00$279.00$223.30
0145Concrete pavement for roundabout apron, 12" depth (0350-30-13)SY23$350.00$217.65$145.00$225.00$352.50
0150Inlets, curb, type P-1, <10' (0425-1311)EACH1$25,000$16,500$15,470$45,000$34,075
0155Inlets, curb type P-1, partial (0425-1315)EACH1$25,000$4,500.00$3,562.00$12,000$14,100
0160Inlets, curb type J-1, <10' (0425-1411)EACH1$25,000$15,500$15,470$45,000$37,600
0165Inlets, curb, type J-2, <10' (0425-1421)EACH1$25,000$15,500$17,384$45,000$39,950
0170Manholes, P-8, partial (0425-2-63)EACH1$25,000$5,500.00$5,156.00$12,000$8,812.50
0175Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF16$350.00$300.00$180.00$1,000.00$705.00
0180Pipe culvert,optional material,round, 24"S/CD (0430-175124)LF32$350.00$300.00$141.00$1,000.00$822.50
0185Concrete curb & gutter, type E (0520-1-7)LF268$40.00$59.95$42.53$65.00$99.88
0190Concrete curb & gutter, type F (0520-1-10)LF562$40.00$64.95$42.53$65.00$94.00
0195Concrete curb, type B (0520-2-2)LF106$40.00$94.95$36.61$65.00$99.88
0200Concrete curb, type RA (0520-2-8)LF99$40.00$64.95$61.51$65.00$146.88
0205Valley gutter- concrete (0520-3)LF87$40.00$64.95$45.93$65.00$158.63
0210Traffic separator concrete- type I, 4' wide (0520-5-11)LF7$250.00$200.00$315.49$165.00$205.63
0215Concrete traffic separator, special- variable width (0520-70)SY100$250.00$200.00$93.69$165.00$205.63
0220Concrete sidewalk and driveways, 4" thick (0522-1)SY186$75.00$94.50$54.42$165.00$82.25
0225Concrete sidewalk and driveways, 6" thick (0522-2)SY348$85.00$104.50$81.78$165.00$125.73
0230Detectable warnings (0527-2)SF172$30.00$42.50$50.30$30.00$29.38
0235Performance turf, sod (0570-1-2)SY422$8.00$12.50$7.00$10.00$17.63
0240Raised pavement marker, type B (0706-1-3)EACH206$5.00$4.00$8.26$7.00$8.23
0245Painted pavement markings, standard, white, solid, 6" (0710-11101)GM0.65$25,000$5,800.00$5,782.00$1,725.00$5,714.03
0250Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF1,790$1.50$2.25$5.90$2.30$5.85
0255Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF1,000$3.00$4.50$13.00$3.50$12.88
0260Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM0.06$1,150.00$1,320.00$944.00$863.00$935.30
0265Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM0.26$2,500.00$5,800.00$5,800.00$1,725.00$5,714.03
0270Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000$50,000$50,000
0275Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH11$750.00$400.00$773.00$805.00$675.63
0280Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH2$1,560.00$1,250.00$2,714.00$2,875.00$2,702.50
0285Single column ground sign assembly, remove (0700-1600)EACH7$200.00$50.00$248.00$57.00$101.05
0290Single column ground sign assembly, F&I cantilever mount, 20.1-30.0 SF (0700-1913)EACH3$6,500.00$3,750.00$4,773.00$4,140.00$4,700.00
0295Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115)EACH1$15,000$7,285.00$7,115.00$12,650$12,925
0300Object marker, type 1 (0705-10-1)EACH2$450.00$350.00$674.00$230.00$276.13
0305Raised pavement marker, type B (0706-1-3)EACH206$5.00$4.00$8.26$7.00$8.23
0310Painted pavement markings, standard, yellow, island nose (0710-11290)SF13$5.00$2.95$5.90$6.00$5.88
0315Painted pavement markings, surface (0710-90)LS1$18,000$6,500.00$13,216$11,500$16,450
0320Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102)GM0.06$6,500.00$6,500.00$10,207$10,350$10,164
0325Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF1,158$3.00$2.95$13.00$7.00$12.76
0330Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF221$5.00$4.50$15.35$14.00$15.23
0335Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.10$5,000.00$1,320.00$6,844.00$6,900.00$6,815.00
0340Thermoplastic, standard, message or symbol (0711-11160)EACH2$250.00$250.00$348.00$288.00$346.63
0345Thermoplastic, standard, arrow (0711-11170)EACH18$300.00$75.00$230.00$115.00$229.13
0350Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.04$5,000.00$1,320.00$6,844.00$6,900.00$6,815.00
0355Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF763$20.00$24.00$21.25$23.00$20.68
0360Thermoplastic, preformed, white, message (0711-14160)EACH1$650.00$350.00$460.00$345.00$458.25
0365Thermoplastic, preformed, white, arrow (0711-14170)EACH1$650.00$250.00$332.00$230.00$331.35
0370Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.56$6,500.00$5,800.00$8,142.00$2,875.00$8,087.53
0375Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM0.06$6,500.00$1,320.00$3,304.00$2,875.00$3,290.00
0380Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.26$6,500.00$5,800.00$8,142.00$8,625.00$8,087.53
0385Drilled shaft casing, 54" diameter (0455-107-8)LF36$2,100.00$3,500.00$244.00$4,801.00$1,265.00
0390Itsfm subsurface documentation- project length (0611-1-1)MI0.08$45,000$19,500$5,636.00$4,262.00$4,400.00
0395Itsfm location documentation- intersection (0611-2-1)EACH2$3,500.00$12,500$3,540.00$3,231.00$3,025.00
0400Conduit, furnish & install, open trench (0630-2-11)LF334$26.00$50.00$17.70$41.00$35.20
0405Conduit, furnish & install, directional bore (0630-2-12)LF4,892$44.00$35.00$67.56$35.00$31.35
0410Conduit, furnish & install, aboveground (0630-2-14)LF47$60.00$95.00$28.14$41.00$44.00
0415Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$18,000$19,500$17,936$16,453$19,250
0420Signal cable, remove- intersection (0632-7-6)PI1$2,650.00$9,500.00$6,985.00$3,183.00$2,090.00
0425Fiber optic cable, F&I, overhead, 2-12 fibers (0633-1111)LF240$10.00$6.00$8.70$8.00$4.95
0430Fiber optic cable, F&I, overhead,13-48 fibers (0633-1112)LF420$10.00$8.00$8.70$6.00$5.50
0435Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF290$8.00$6.00$5.80$5.00$7.15
0440Fiber optic cable, F&I, underground,13-48 fibers (0633-1122)LF794$10.00$8.00$6.05$6.00$7.43
0445Fiber optic cable, F&I, underground,49-96 fibers (0633-1123)LF5,190$10.00$5.00$6.55$7.00$7.70
0450Fiber optic cable, relocate, underground (0633-1420)LF249$10.00$4.00$4.76$4.00$5.50
0455Fiber optic cable, remove, overhead (0633-1610)LF479$10.00$2.00$2.00$2.00$1.65
0460Fiber optic connection, install, splice (0633-2-31)EACH84$95.00$95.00$66.50$62.00$60.50
0465Fiber optic connection, install, termination (0633-2-32)EACH84$105.00$95.00$125.00$117.00$115.50
0470Fiber optic connection hardware, F&I, splice (0633-3-11)EACH2$2,500.00$1,950.00$2,160.00$1,959.00$1,925.00
0475Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14)EACH7$200.00$125.00$148.00$117.00$115.50
0480Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16)EACH5$2,100.00$2,950.00$1,536.00$1,410.00$1,375.00
0485Fiber optic connection hardware, F&I, connector panel (0633-3-17)EACH5$180.00$295.00$170.00$138.00$137.50
0490Fiber optic cable locator (0633-6)DA190$265.00$295.00$338.00$310.00$302.50
0495Span wire assembly, F&I, two point, diagonal (0634-4152)PI2$8,500.00$9,500.00$2,428.00$5,827.00$7,975.00
0500Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH28$2,650.00$2,150.00$2,200.00$1,555.00$1,925.00
0505Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH13$2,650.00$3,450.00$3,045.00$3,079.00$4,015.00
0510Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13)EACH1$8,000.00$6,950.00$4,800.00$4,672.00$7,150.00
0515Pull & splice box, install (0635-2-30)EACH1$2,500.00$2,450.00$1,830.00$1,483.00$1,320.00
0520Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$7,000.00$7,500.00$5,000.00$6,630.00$5,445.00
0525Electrical service wire, & install (0639-2-1)LF235$13.00$25.00$14.75$33.00$9.90
0530Electrical service wire, (0639-2-6)LF20$2.00$10.00$3.42$8.00$3.30
0535Electrical power service- contribution in aid of construction (ciac), duke (DO not bid) (0639-8100)LS1$4,000.00$4,000.00$4,000.00$4,000.00$4,000.00
0540Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$2,550.00$4,500.00$1,850.00$3,654.00$3,190.00
0545Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80)EACH2$23,000$9,500.00$3,930.00$10,637$11,550
0550Aluminum signals pole, (0646-1-11)EACH8$3,200.00$2,950.00$2,845.00$3,658.00$3,905.00
0555Aluminum signals pole, remove (0646-1-60)EACH6$800.00$1,250.00$717.00$1,591.00$522.50
0560Steel strain pole, F&I, type PS- (0649-1-14)EACH4$49,000$65,000$65,490$22,904$66,550
0565Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS12$2,005.00$2,250.00$2,160.00$2,156.00$2,805.00
0570Vehicular traffic signal, furnish & install aluminum, 5 section cluster, 1 way (0650-1-19)AS2$3,300.00$3,250.00$3,010.00$2,973.00$4,125.00
0575Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS8$1,250.00$1,000.00$888.00$1,006.00$1,155.00
0580Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH1$30,000$24,950$21,650$20,478$26,400
0585Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH4$9,850.00$10,000$10,000$40,424$11,550
0590Traffic data detection system- video, furnish and install, cabinet equipment (0660-9-11)EACH1$40,000$37,500$28,025$30,000$33,000
0595Traffic data detection system- video, furnish and install, ground equipment (0660-9-12)EACH2$13,500$19,500$8,060.00$9,900.00$9,900.00
0600Signal priority and preemption system, furnish and install, detector (0663-1122)EACH1$9,500.00$3,750.00$9,500.00$11,915$7,920.00
0605Signal priority and preemption system, furnish and install, cabinet electronics (0663-1123)EACH1$9,500.00$9,500.00$9,300.00$9,631.00$9,790.00
0610Pedestrian detector, furnish & install, standard (0665-1-11)EACH8$780.00$495.00$370.00$509.00$594.00
0615Traffic controller assembly, F&I, NEMA W/electronic lock, 2 preemption (0670-5172)AS1$53,000$75,000$47,800$45,295$56,100
0620Traffic controller assembly, remove controller with (0670-5600)AS1$1,500.00$1,450.00$2,785.00$6,365.00$1,925.00
0625ITS CCTV camera, pressurized, high definition (0682-1163)EACH1$7,600.00$19,500$6,608.00$9,316.00$9,185.00
0630Managed field ethernet switch, furnish & install (0684-1-1)EACH2$2,850.00$5,950.00$3,422.00$4,435.00$4,785.00
0635Managed field ethernet switch, relocate (0684-1-4)EACH1$800.00$500.00$513.00$447.00$440.00
0640Wireless communication system device, remove (0684-6-6)EACH1$400.00$1,950.00$540.00$344.00$253.00
0645Uninterruptible power supply, furnish and install, line interactive (0685-1-11)EACH1$9,800.00$5,450.00$10,030$10,244$15,400
0650Remote power management rpmu, furnish and install (0685-2-1)EACH1$1,500.00$1,250.00$2,250.00$1,209.00$1,760.00
0655Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH2$1,500.00$400.00$1,300.00$1,054.00$1,177.00
0660Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH4$9,850.00$7,500.00$10,000$6,375.00$9,295.00
0665Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360)EACH2$9,000.00$8,500.00$11,800$4,577.00$7,645.00
FDOT contract T5859: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of July 30, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy