FDOT contract T6592 bid tabulation
SR 886 (PORT BLVD) FROM BISCAYNE BLVD TO PORT OF MIAMI. Let by Florida DOT on September 24, 2025, Miami-Dade, District 6. 7 bids received; low bid $3,628,931 by Roadway Construction, LLC.
- Owner
- Florida DOT
- Letting
- 24 SEP 2025
- Pay items
- 119
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Roadway Construction, LLC | $3,628,931 | Low |
| 2 | Gosalia Concrete Constructors, Inc. | $3,867,097 | +7.0% |
| 3 | Ohla USA Inc | $3,898,390 | +7.0% |
| 4 | Florida Engineering & Development Corp | $4,021,283 | +11% |
| 5 | Jva Engineering Contractor, Inc | $4,038,868 | +11% |
| 6 | Bacallao Construction & Engineering Development, LLC D/B/A BC&E | $4,305,855 | +19% |
| 7 | General Asphalt Company, LLC | $4,614,885 | +27% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Roadway Construction, LLC | 2. Gosalia Concrete Constructors, Inc. | 3. Ohla USA Inc | 4. Florida Engineering & Development Corp | 5. Jva Engineering Contractor, Inc | 6. Bacallao Construction & Engineering Development, LLC D/B/A BC&E |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $362,000 | $380,000 | $384,391 | $341,552 | $448,500 | $400,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $459,038 | $403,497 | $360,000 | $256,509 | $362,500 | $75,000 |
| 0015 | Traffic control officer (0102-14) | HR | 1,036 | $75.00 | $85.00 | $85.00 | $96.66 | $86.25 | $90.00 |
| 0020 | Work zone sign (0102-60) | ED | 20,565 | $0.19 | $0.19 | $0.22 | $0.21 | $0.25 | $0.22 |
| 0025 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 365 | $55.00 | $30.00 | $1.00 | $47.43 | $50.60 | $0.01 |
| 0030 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 193 | $30.00 | $5.00 | $1.00 | $20.33 | $50.60 | $0.01 |
| 0035 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 104,670 | $0.09 | $0.09 | $0.10 | $0.11 | $0.12 | $0.15 |
| 0040 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 31,267 | $0.05 | $0.05 | $0.05 | $0.07 | $0.06 | $0.08 |
| 0045 | Arrow board / advance warning arrow panel (0102-76) | ED | 1,125 | $4.00 | $4.00 | $5.50 | $5.87 | $6.15 | $5.25 |
| 0050 | Portable changeable message sign, temporary (0102-99) | ED | 658 | $9.00 | $9.00 | $10.00 | $10.50 | $11.00 | $10.00 |
| 0055 | Temporary signalization and maintenance, intersection (0102-104) | ED | 810 | $15.00 | $20.56 | $15.00 | $16.94 | $11.50 | $15.00 |
| 0060 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 810 | $15.00 | $20.56 | $15.00 | $16.94 | $11.50 | $15.00 |
| 0065 | Type III barricade (0102-115) | ED | 4,095 | $0.23 | $0.30 | $0.30 | $0.29 | $0.37 | $0.25 |
| 0070 | Inlet protection system (0104-18) | EACH | 11 | $457.12 | $100.00 | $500.00 | $108.72 | $210.00 | $75.00 |
| 0075 | Litter removal (0107-1) | ACRE | 40.66 | $0.01 | $50.00 | $175.00 | $19.85 | $240.00 | $0.01 |
| 0080 | Mowing (0107-2) | ACRE | 40.66 | $0.01 | $35.00 | $275.00 | $23.74 | $250.00 | $0.01 |
| 0085 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $2,500.00 | $2,500.00 | $150,000 | $2,823.00 | $5,175.00 | $5,000.00 |
| 0090 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $2,141.93 | $50,000 | $150,000 | $12,591 | $5,750.00 | $5,000.00 |
| 0095 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $2,100.00 | $9,887.94 | $150,000 | $12,591 | $5,750.00 | $5,000.00 |
| 0100 | Selective clearing and areas with trees to remain (0110-2-2) | ACRE | 0.02 | $400,000 | $100,000 | $380,000 | $610,784 | $5,750.00 | $100,000 |
| 0105 | Removal of existing concrete (0110-4-10) | SY | 3,300 | $110.04 | $340.00 | $10.05 | $44.75 | $103.00 | $47.00 |
| 0110 | Tree protection barrier (0110-21) | LF | 149 | $8.52 | $3.90 | $30.00 | $12.11 | $4.85 | $0.01 |
| 0115 | Tree root and branch pruning (0110-22) | EACH | 2 | $750.00 | $5,000.00 | $5,200.00 | $5,646.00 | $3,000.00 | $1,000.00 |
| 0120 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $6,345.63 | $600.00 | $25,000 | $5,498.75 | $2,140.00 | $1,000.00 |
| 0125 | Type B stabilization (0160-4) | SY | 59 | $104.74 | $85.50 | $20.00 | $61.02 | $55.00 | $0.01 |
| 0130 | Optional base, base group 12 (0285-712) | SY | 59 | $299.58 | $85.50 | $400.00 | $83.69 | $240.00 | $100.00 |
| 0135 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 2,522 | $3.57 | $12.80 | $10.00 | $8.81 | $6.00 | $4.00 |
| 0140 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 6.50 | $1,814.72 | $360.00 | $1,230.00 | $1,054.23 | $941.00 | $250.00 |
| 0145 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 212.90 | $238.00 | $360.00 | $275.00 | $392.23 | $252.00 | $300.00 |
| 0150 | Miscellaneous asphalt (0339-1) | TN | 2.20 | $745.30 | $365.00 | $2,000.00 | $1,028.19 | $1,400.00 | $500.00 |
| 0155 | Cleaning & sealing joints- concrete pavement (0350-5) | LF | 23,252 | $12.62 | $3.62 | $3.20 | $5.25 | $6.90 | $3.50 |
| 0160 | Cleaning & sealing random cracks- concrete pavement (0350-6) | LF | 48 | $152.90 | $150.00 | $100.00 | $112.92 | $100.00 | $100.00 |
| 0165 | Grinding concrete pavement (0352-70) | SY | 14,430 | $7.00 | $3.00 | $7.00 | $9.54 | $10.35 | $10.00 |
| 0170 | Concrete pavement slab replacement (0353-70) | CY | 886.20 | $1,106.07 | $630.00 | $1,405.00 | $1,892.54 | $1,245.00 | $2,450.00 |
| 0175 | Manhole, adjust (0425-5) | EACH | 4 | $550.00 | $535.00 | $1,000.00 | $1,076.36 | $810.00 | $800.00 |
| 0180 | Concrete curb & gutter, type F (0520-1-10) | LF | 255 | $62.43 | $64.00 | $80.00 | $74.22 | $116.00 | $55.00 |
| 0185 | Concrete curb, type D (0520-2-4) | LF | 11 | $128.85 | $70.00 | $80.00 | $66.42 | $100.00 | $45.00 |
| 0190 | Shoulder gutter- concrete (0520-6) | LF | 56 | $89.00 | $232.00 | $100.00 | $67.92 | $255.00 | $55.00 |
| 0195 | Shoulder concrete barrier, 32" F-shape (0521-72108) | LF | 41 | $716.01 | $410.00 | $750.00 | $544.27 | $1,576.00 | $500.00 |
| 0200 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 95 | $166.64 | $70.00 | $100.00 | $91.77 | $190.00 | $95.00 |
| 0205 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 142 | $252.51 | $103.00 | $155.00 | $116.54 | $225.00 | $100.00 |
| 0210 | Pavers, architectural, (0526-1-2) | SY | 145 | $24.14 | $230.00 | $155.00 | $118.75 | $146.00 | $150.00 |
| 0215 | Detectable warnings (0527-2) | SF | 145 | $63.88 | $45.00 | $45.00 | $50.42 | $37.00 | $40.00 |
| 0220 | Guardrail -roadway, general (0536-1-1) | LF | 81 | $22.48 | $22.48 | $23.00 | $36.13 | $37.00 | $30.00 |
| 0225 | Pipe rail for guardrail (0536-6) | LF | 81 | $19.60 | $19.60 | $20.50 | $33.88 | $35.00 | $25.00 |
| 0230 | Special guardrail post- post for shallow mount (0536-7-3) | EACH | 4 | $365.70 | $365.70 | $375.00 | $282.30 | $290.00 | $480.00 |
| 0235 | Guardrail transition to rigid barrier, F&I- index 536- 001, approach TL-3 (0536-8112) | EACH | 1 | $3,287.88 | $3,287.88 | $3,360.00 | $3,952.20 | $4,025.00 | $4,250.00 |
| 0240 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 1 | $3,369.45 | $3,369.45 | $3,450.00 | $3,839.28 | $3,910.00 | $4,250.00 |
| 0245 | Crash cushion, TL-2, narrow (0544-2-1) | EACH | 1 | $28,473 | $28,514 | $30,000 | $27,101 | $27,600 | $19,000 |
| 0250 | Performance turf (0570-1-1) | SY | 44 | $74.94 | $10.00 | $115.00 | $10.64 | $12.00 | $9.00 |
| 0255 | Irrigation system- modify existing system (0590-70-5) | LS | 1 | $7,535.00 | $7,535.00 | $25,000 | $8,508.53 | $8,600.00 | $1,000.00 |
| 0260 | Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130) | LS | 1 | $9,262.79 | $9,262.79 | $9,262.79 | $9,262.79 | $9,262.79 | $9,262.79 |
| 0265 | Raised pavement marker, type B (0706-1-3) | EACH | 5,722 | $4.00 | $4.00 | $4.50 | $4.36 | $4.50 | $5.00 |
| 0270 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 8.16 | $1,197.27 | $1,197.27 | $1,225.00 | $1,192.44 | $1,214.40 | $1,500.00 |
| 0275 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.26 | $784.31 | $784.31 | $850.00 | $564.59 | $575.00 | $1,000.00 |
| 0280 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.06 | $750.00 | $750.00 | $800.00 | $564.53 | $575.00 | $1,000.00 |
| 0285 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 1.25 | $1,197.04 | $1,197.04 | $1,225.00 | $1,192.44 | $1,214.40 | $1,500.00 |
| 0290 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $48,000 | $48,000 | $48,000 | $48,000 | $48,000 | $48,000 |
| 0295 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 0300 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 12 | $500.00 | $595.00 | $511.00 | $671.87 | $684.00 | $600.00 |
| 0305 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 9 | $1,800.00 | $2,550.00 | $1,840.00 | $2,879.46 | $2,930.00 | $1,700.00 |
| 0310 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 1 | $1,900.00 | $2,950.00 | $1,940.00 | $3,331.14 | $3,390.00 | $2,250.00 |
| 0315 | Single column ground sign assembly, F&I barrier less than 12 SF (0700-1211) | EACH | 3 | $1,400.00 | $1,595.00 | $1,430.00 | $1,801.08 | $1,830.00 | $2,250.00 |
| 0320 | Single column ground sign assembly, F&I barrier 12.0-20.0 SF (0700-1212) | EACH | 1 | $1,400.00 | $2,550.00 | $1,430.00 | $2,879.46 | $2,930.00 | $3,250.00 |
| 0325 | Single column ground sign assembly, remove (0700-1600) | EACH | 15 | $150.00 | $10.00 | $155.00 | $11.29 | $11.50 | $1.00 |
| 0330 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 1 | $750.00 | $500.00 | $766.00 | $564.60 | $575.00 | $1,200.00 |
| 0335 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 2 | $550.00 | $3,500.00 | $562.00 | $1,242.12 | $1,210.00 | $1,500.00 |
| 0340 | Sign panel, install, 301-400 SF (0700-3408) | EACH | 2 | $3,500.00 | $3,500.00 | $3,575.00 | $3,952.20 | $4,025.00 | $2,000.00 |
| 0345 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 1 | $100.00 | $70.00 | $102.50 | $79.04 | $80.50 | $200.00 |
| 0350 | Sign panel, remove, 12-20 SF (0700-3602) | EACH | 1 | $150.00 | $100.00 | $155.00 | $112.92 | $115.00 | $200.00 |
| 0355 | Sign panel, remove, 51-100 SF (0700-3605) | EACH | 2 | $1,000.00 | $420.00 | $1,021.00 | $474.27 | $485.00 | $1,250.00 |
| 0360 | Sign panel, remove, 101-200 SF (0700-3606) | EACH | 4 | $1,250.00 | $540.00 | $1,280.00 | $609.77 | $620.00 | $1,400.00 |
| 0365 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 5 | $110.00 | $200.00 | $113.00 | $225.84 | $230.00 | $150.00 |
| 0370 | Raised pavement marker, type B (0706-1-3) | EACH | 962 | $4.00 | $4.00 | $4.10 | $5.65 | $5.75 | $5.00 |
| 0375 | Painted pavement markings, surface (0710-90) | LS | 1 | $3,678.83 | $3,678.83 | $15,000 | $6,007.34 | $3,450.00 | $4,000.00 |
| 0380 | Painted pavement markings, surface (0710-90) | LS | 1 | $1,653.00 | $1,653.00 | $15,000 | $6,007.34 | $2,660.00 | $2,000.00 |
| 0385 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.22 | $1,361.11 | $1,361.11 | $1,390.00 | $7,452.69 | $7,730.00 | $1,900.00 |
| 0390 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 180 | $2.25 | $2.25 | $2.35 | $2.71 | $2.76 | $3.00 |
| 0395 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 633 | $3.33 | $3.33 | $3.45 | $4.07 | $4.14 | $4.00 |
| 0400 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 47 | $4.00 | $4.00 | $4.10 | $5.42 | $5.52 | $5.00 |
| 0405 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.03 | $1,318.18 | $1,318.18 | $1,346.00 | $2,597.27 | $2,645.00 | $1,700.00 |
| 0410 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 1 | $200.00 | $200.00 | $205.00 | $135.50 | $138.00 | $225.00 |
| 0415 | Thermoplastic, standard, arrow (0711-11170) | EACH | 7 | $100.00 | $100.00 | $105.00 | $90.34 | $92.00 | $125.00 |
| 0420 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 228 | $3.33 | $3.33 | $3.40 | $4.07 | $4.14 | $4.25 |
| 0425 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 293 | $18.00 | $18.00 | $18.50 | $20.33 | $20.70 | $20.00 |
| 0430 | Thermoplastic, preformed, white, 2-4 dotted guideline on concrete surfaces (0711-14141) | GM | 0.09 | $10,787 | $10,787 | $1,101.00 | $954.04 | $12,280 | $14,000 |
| 0435 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 10 | $450.00 | $450.00 | $460.00 | $293.59 | $300.00 | $550.00 |
| 0440 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 15 | $450.00 | $450.00 | $460.00 | $169.38 | $172.50 | $550.00 |
| 0445 | Thermoplastic, preformed, 6" white, railroad dynamic envelope (0711-14191) | LF | 92 | $8.50 | $8.50 | $8.75 | $6.78 | $6.90 | $10.00 |
| 0450 | Thermoplastic, preformed, 12" white with 4" outside black contrast on concrete railroad dynamic envelope (0711-14194) | LF | 949 | $15.50 | $15.50 | $16.00 | $13.55 | $13.80 | $20.00 |
| 0455 | Thermoplastic, preformed, 24" white with 4" black contrast stop line on concrete 32" (0711-14527) | LF | 322 | $22.50 | $22.50 | $23.00 | $18.07 | $18.40 | $30.00 |
| 0460 | Thermoplastic, preformed, 12" white with 4" black contrast crosswalk on concrete pavement, 20" (0711-14528) | LF | 174 | $18.50 | $18.50 | $19.00 | $10.16 | $10.35 | $24.00 |
| 0465 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.13 | $4,664.12 | $4,664.12 | $4,760.00 | $7,154.66 | $7,286.40 | $6,000.00 |
| 0470 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.10 | $4,360.82 | $4,360.82 | $4,450.00 | $7,154.64 | $7,511.75 | $5,750.00 |
| 0475 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 1.97 | $30,719 | $30,719 | $31,350 | $59,621 | $60,600 | $40,000 |
| 0480 | Permanent tape, white, solid, 8" exit lane at interchange on concrete pavement (0713-103102) | GM | 0.19 | $44,000 | $44,000 | $45,000 | $47,697 | $48,700 | $55,000 |
| 0485 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 2.54 | $749.41 | $7,494.10 | $7,650.00 | $10,174 | $10,350 | $10,000 |
| 0490 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 1.44 | $31,500 | $31,500 | $32,150 | $44,603 | $45,425 | $40,000 |
| 0495 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 2.54 | $7,987.42 | $7,987.42 | $8,150.00 | $10,174 | $10,350 | $10,000 |
| 0500 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 12 | $2,000.00 | $1,761.61 | $2,050.00 | $2,258.40 | $2,070.00 | $2,000.00 |
| 0505 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,473 | $35.00 | $59.28 | $36.50 | $39.52 | $51.75 | $50.00 |
| 0510 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 3 | $10,000 | $10,054 | $10,205 | $11,292 | $12,075 | $18,000 |
| 0515 | Fiber optic cable locator (0633-6) | DA | 270 | $0.01 | $197.60 | $165.00 | $169.38 | $300.00 | $375.00 |
| 0520 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 31 | $2,000.00 | $1,761.61 | $2,050.00 | $2,258.40 | $1,955.00 | $2,000.00 |
| 0525 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $7,500.00 | $6,806.03 | $7,655.00 | $8,469.00 | $5,980.00 | $8,250.00 |
| 0530 | Electrical power service, remove underground (0639-1620) | AS | 1 | $1,500.00 | $1,526.68 | $1,550.00 | $1,693.80 | $977.50 | $1,600.00 |
| 0535 | Electrical service wire, & install (0639-2-1) | LF | 1,160 | $10.00 | $8.15 | $10.50 | $11.29 | $11.50 | $15.00 |
| 0540 | Electrical service wire, (0639-2-6) | LF | 600 | $1.00 | $2.87 | $1.05 | $1.13 | $1.15 | $1.50 |
| 0545 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $3,000.00 | $4,736.83 | $3,065.00 | $3,387.60 | $3,335.00 | $4,750.00 |
| 0550 | Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60) | EACH | 1 | $750.00 | $1,526.68 | $770.00 | $846.90 | $977.50 | $1,600.00 |
| 0555 | Aluminum signals pole, (0646-1-11) | EACH | 1 | $2,500.00 | $5,158.46 | $2,560.00 | $2,823.00 | $2,415.00 | $4,500.00 |
| 0560 | Aluminum signals pole, remove (0646-1-60) | EACH | 1 | $500.00 | $822.02 | $510.50 | $564.60 | $230.00 | $400.00 |
| 0565 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 1 | $1,800.00 | $1,010.07 | $1,850.00 | $2,032.56 | $1,150.00 | $1,500.00 |
| 0570 | Loop assembly, F&I, type F (0660-2106) | AS | 6 | $2,000.00 | $4,610.67 | $2,050.00 | $2,258.40 | $2,415.00 | $3,700.00 |
| 0575 | Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11) | EACH | 3 | $6,750.00 | $10,827 | $6,890.00 | $7,622.10 | $17,480 | $7,000.00 |
| 0580 | Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12) | EACH | 3 | $12,500 | $11,860 | $12,800 | $14,115 | $23,000 | $18,000 |
| 0585 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 1 | $450.00 | $424.83 | $460.00 | $508.14 | $402.50 | $850.00 |
| 0590 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 3 | $2,000.00 | $1,761.61 | $2,041.00 | $2,258.40 | $2,070.00 | $2,000.00 |
| 0595 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 1 | $3,000.00 | $2,669.91 | $3,062.00 | $3,387.60 | $3,565.00 | $4,800.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of September 24, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.