FDOT contract T6599 bid tabulation

SR 934 (NW 79 ST) FROM NW 27 AVE TO NW 1 PL. Let by Florida DOT on July 30, 2025, Miami-Dade, District 6. 6 bids received; low bid $5,847,847 by Aum Construction Inc..

Owner
Florida DOT
Letting
30 JUL 2025
Pay items
150
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Aum Construction Inc.$5,847,847Low
2Florida Engineering & Development Corp$5,894,803+1.0%
3Weekley Asphalt Paving, Inc.$6,059,424+4.0%
4Roadway Construction, LLC$6,446,078+10%
5Jva Engineering Contractor, Inc$6,557,500+12%
6Sice Inc$7,053,277+21%
FDOT contract T6599: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Aum Construction Inc.2. Florida Engineering & Development Corp3. Weekley Asphalt Paving, Inc.4. Roadway Construction, LLC5. Jva Engineering Contractor, Inc6. Sice Inc
0005Mobilization (0101-1)LS1$550,000$584,648$344,711$644,608$716,100$680,392
0010Maintenance of traffic (0102-1)DA1$200,000$553,371$620,000$250,000$298,800$444,958
0015Traffic control officer (0102-14)HR52$80.00$88.17$95.00$85.00$89.00$151.97
0020Work zone sign (0102-60)ED19,790$0.25$0.20$0.19$0.20$0.24$0.23
0025Temporary barrier, F&I, low profile, concrete (0102-71-13)LF1,600$55.00$47.48$33.00$0.01$50.00$58.29
0030Temporary barrier, relocate, low profile concrete (0102-71-23)LF2,400$20.00$17.98$28.00$0.01$25.00$20.73
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED27,639$0.20$0.12$0.09$0.08$0.11$0.15
0040Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD3,035$0.20$0.10$0.05$0.05$0.06$0.12
0045Arrow board / advance warning arrow panel (0102-76)ED810$8.00$5.36$5.00$5.00$6.34$6.32
0050Temporary crash cushion, redirective option (0102-89-1)LO27$1,150.00$921.85$3,800.00$0.01$1,330.00$1,088.08
0055Portable changeable message sign, temporary (0102-99)ED924$15.00$11.64$9.00$10.00$11.40$13.74
0060Temporary signalization and maintenance, intersection (0102-104)ED801$20.00$18.64$12.00$8.50$23.70$10.94
0065Temporary traffic detection and maintenance, intersection (0102-107-1)ED801$20.00$18.64$12.00$8.50$23.70$10.94
0070Type III barricade (0102-115)ED1,332$1.00$0.39$0.23$0.28$0.29$0.46
0075Inlet protection system (0104-18)EACH51$250.00$102.20$165.00$143.29$271.80$212.75
0080Litter removal (0107-1)ACRE79.92$75.00$110.55$20.00$0.01$304.00$48.63
0085Mowing (0107-2)ACRE28.80$100.00$366.85$50.00$0.01$278.30$72.94
0090Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$32,000$4,429.00$7,000.00$0.01$5,928.00$32,095
0095Monitor existing structures- vibration monitoring (0108-2)LS1$15,000$2,472.00$5,000.00$0.01$5,928.00$13,373
0100Clearing & grubbing (0110-1-1)ACRE1$30,000$165,938$197,995$1,459,195$47,400$91,400
0105Removal of existing concrete (0110-4-10)SY1,796$40.00$95.83$67.00$21.21$108.88$75.25
0110Tree protection barrier (0110-21)LF81$20.00$13.59$19.00$6.70$5.10$12.16
0115Borrow excavation, truck measure (0120-2-2)CY358$90.00$65.99$60.00$1.68$31.00$126.71
0120Regular excavation (3-R projects only) (0120-71)LS1$10,000$45,141$83,450$13,150$52,870$43,065
0125Type B stabilization (0160-4)SY532$20.00$25.90$39.00$17.96$51.00$62.17
0130Optional base, base group 09 (0285-709)SY814$45.00$102.47$67.00$55.65$127.00$150.58
0135Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12)SY24,392$8.00$4.64$3.00$4.00$6.60$9.42
0140Superpave asphaltic conc, traffic C (0334-1-13)TN120.90$450.00$243.05$320.00$172.20$343.00$450.50
0145Asphalt concrete friction course,traffic C, FC-9.5, PG 76-22 (0337-7-82)TN1,726.30$265.00$216.30$200.00$240.00$242.00$376.89
0150Inlets, curb, type 9, <10' (0425-1201)EACH1$16,000$8,824.39$14,000$6,412.71$8,980.00$17,404
0155Inlets, curb, type 10, <10' (0425-1211)EACH1$15,000$8,934.60$11,000$7,166.97$9,620.00$19,108
0160Inlets, curb, type P-6, <10' (0425-1361)EACH1$17,000$9,099.92$12,000$7,731.67$10,460$20,384
0165Inlets, DT bot, type F, <10' (0425-1561)EACH2$15,000$9,266.08$12,000$8,015.29$9,230.00$22,047
0170Manholes, P-7, <10' (0425-2-41)EACH1$15,000$10,498$14,000$6,710.13$15,275$18,086
0175Manholes, P-8, <10' (0425-2-61)EACH4$15,000$10,553$26,000$7,736.67$15,725$21,659
0180Manhole, adjust (0425-5)EACH7$2,000.00$984.55$1,200.00$550.00$1,067.00$863.71
0185Pipe culvert,optional material,round, 15"S/CD (0430-175115)LF5$1,500.00$767.22$554.00$596.21$730.00$1,494.06
0190Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF128$550.00$315.28$566.00$147.27$290.00$396.32
0195Pipe culvert, opt material, round, 30"S/CD (0430-175130)LF16$1,000.00$985.75$743.00$608.06$908.00$1,551.07
0200Pipe handrail - guiderail, aluminum (0515-1-2)LF30$250.00$87.55$130.00$219.00$296.00$343.91
0205Concrete curb & gutter, type E (0520-1-7)LF396$50.00$73.70$63.85$49.88$74.40$120.21
0210Concrete curb & gutter, type F (0520-1-10)LF3,427$50.00$74.31$49.45$47.15$47.00$113.93
0215Traffic separator concrete- type I, 4' wide (0520-5-11)LF363$160.00$122.41$92.00$63.18$77.40$149.91
0220Traffic separator concrete- type IV, 4' wide (0520-5-41)LF31$150.00$443.67$106.00$140.07$172.00$324.21
0225Concrete sidewalk and driveways, 4" thick (0522-1)SY818$100.00$101.39$67.00$68.34$130.00$160.52
0230Concrete sidewalk and driveways, 6" thick (0522-2)SY822$130.00$108.78$78.00$81.00$143.20$189.12
0235Detectable warnings (0527-2)SF434$45.00$41.03$36.00$30.97$41.40$71.07
0240Fencing, type B, 6.1-7.0, W/ barb wire attmt (0550-10231)LF30$100.00$61.80$79.00$83.50$60.00$343.92
0245Performance turf, sod (0570-1-2)SY695$20.00$8.05$9.80$28.56$12.60$73.81
0250Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130)LS1$16,000$16,000$16,000$16,000$16,000$16,000
0255Raised pavement marker, type B (0706-1-3)EACH858$7.50$5.15$5.00$3.50$5.90$5.50
0260Painted pavement markings, standard, white, solid, 6" (0710-11101)GM1.61$3,000.00$1,631.52$1,584.00$1,504.67$1,880.00$2,362.91
0265Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.15$6,000.00$1,903.49$1,848.00$1,973.68$2,190.00$3,099.43
0270Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF3,816$1.75$0.62$0.60$1.40$0.71$2.20
0275Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF241$3.00$0.93$0.90$1.50$1.07$2.36
0280Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF3,903$2.50$1.24$1.20$1.60$1.40$2.51
0285Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM1.05$2,200.00$407.87$396.00$488.14$470.00$766.57
0290Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.07$12,000$407.84$396.00$614.86$470.00$965.57
0295Painted pavement markings, standard, white, message or symbol (0710-11160)EACH27$150.00$61.80$60.00$35.00$71.10$54.96
0300Painted pavement markings, standard, white, arrows (0710-11170)EACH35$100.00$41.20$40.00$35.00$47.40$54.96
0305Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM1.11$3,500.00$1,631.52$1,584.00$1,706.15$1,880.00$2,679.31
0310Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF104$5.00$0.93$0.90$1.50$1.07$2.36
0315Painted pavement markings, standard, yellow, skip, 6" (0710-11231)GM0.02$15,000$407.89$396.00$515.79$470.00$809.99
0320Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.29$3,000.00$407.90$396.00$659.09$470.00$1,035.02
0325Painted pavement markings, standard, yellow, island nose (0710-11290)SF92$20.00$2.06$2.00$5.00$2.30$7.85
0330Initial contingency amount, DO not bid (0999-25)LS1$57,616$57,616$57,616$57,616$57,616$57,616
0335Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH5$1,750.00$991.48$2,000.00$1,399.00$2,371.00$1,033.37
0340Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH107$700.00$540.75$525.00$450.00$622.00$595.71
0345Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH1$2,500.00$2,672.85$2,595.00$1,300.00$3,080.00$2,005.96
0350Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH7$2,800.00$2,878.85$2,795.00$1,800.00$3,315.00$2,604.37
0355Single column ground sign assembly, remove (0700-1600)EACH35$50.00$10.30$10.00$20.00$12.00$121.57
0360Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113)EACH1$9,000.00$6,586.85$6,395.00$3,900.00$7,585.00$7,172.82
0365Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH7$150.00$257.50$250.00$120.00$296.00$170.20
0370Enhanced highway sign solar powered, F&I ground mount, highlighted sign <12 SF (0700-142140)EACH5$15,000$11,304$14,000$13,769$26,000$10,833
0375Tubular marker, 36" yellow (0704-1-4)EACH41$200.00$97.85$95.00$93.00$112.60$267.46
0380Raised pavement marker, type B (0706-1-3)EACH858$7.50$5.15$5.00$3.50$5.90$5.50
0385Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF92$15.00$2.06$2.00$5.00$2.40$7.85
0390Painted pavement markings, surface (0710-90)LS1$25,000$17,068$16,571$12,186$19,600$19,137
0395Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102)GM0.02$16,000$6,797.83$6,600.00$6,085.22$7,825.00$9,556.12
0400Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF3,815$2.75$2.47$2.40$3.10$2.85$4.87
0405Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF241$4.00$4.12$4.00$4.65$4.70$7.30
0410Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF564$5.00$5.15$5.00$6.20$5.90$9.74
0415Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.07$7,500.00$1,631.62$1,584.00$2,128.38$1,880.00$3,342.37
0420Thermoplastic, standard, message or symbol (0711-11160)EACH10$250.00$123.60$120.00$85.00$142.00$133.48
0425Thermoplastic, standard, arrow (0711-11170)EACH35$150.00$82.40$80.00$61.00$95.00$95.79
0430Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF104$8.00$3.71$3.60$4.26$4.20$6.69
0435Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.29$5,000.00$6,526.08$6,336.00$2,281.47$7,515.00$3,582.78
0440Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF3,318$24.00$19.57$19.00$16.00$22.50$25.13
0445Thermoplastic, preformed, white, message (0711-14160)EACH17$600.00$267.80$260.00$310.00$308.00$486.82
0450Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM1.61$7,500.00$6,526.08$6,336.00$5,263.35$7,515.00$8,265.47
0455Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.13$12,000$6,798.29$6,600.00$7,052.25$7,825.00$11,075
0460Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM1.06$3,500.00$2,266.00$2,200.00$1,315.72$2,610.00$2,066.18
0465Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM1.11$7,500.00$6,526.08$6,336.00$4,841.45$7,510.00$7,602.93
0470Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM0.02$15,000$2,265.79$2,200.00$1,269.47$2,610.00$1,993.55
0475Conduit, furnish & install, directional bore (0630-2-12)LF2,901$30.00$45.00$42.00$30.00$33.20$48.63
0480Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH42$1,750.00$1,100.00$1,800.00$1,399.00$1,423.00$1,033.37
0485Pull & splice box, install (0635-2-30)EACH3$1,500.00$1,250.00$1,800.00$1,017.50$1,185.00$607.87
0490Electrical power service, F&I, underground, meter by contractor (0639-1122)AS3$7,000.00$6,000.00$8,500.00$5,781.50$6,165.00$5,207.59
0495Electrical power service, remove underground (0639-1620)AS3$750.00$850.00$750.00$1,485.00$1,010.00$1,400.52
0500Prestressed concrete pole, type P-II service pole (0641-2-12)EACH3$2,000.00$2,900.00$3,500.00$3,036.00$2,964.00$2,400.74
0505Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH3$750.00$650.00$500.00$995.50$1,010.00$1,050.39
0510Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF9,075$3.50$5.00$5.00$2.90$3.50$3.14
0515Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13)LF1,646$6.00$5.00$7.00$4.50$5.30$6.22
0520Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF7,236$0.25$0.25$0.25$0.20$0.59$1.06
0525Load center, F&I, secondary voltage (0715-7-11)EACH3$16,500$16,000$18,000$17,636$26,600$12,948
0530Load center, remove, voltage (0715-7-41)EACH3$500.00$900.00$500.00$594.00$17,785$1,400.52
0535Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH7$1,300.00$1,500.00$1,800.00$1,542.00$2,194.00$1,195.49
0540Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 15' arm length (0715-61352)EACH6$8,600.00$7,500.00$12,000$8,000.00$11,265$8,896.32
0545Light pole complete, F&I, utility conflict pole standard foundation, 35' mounting height, 16' arm length (0715-65266)EACH1$9,000.00$8,000.00$12,500$8,010.00$17,784$13,529
0550Light pole complete, remove pole and foundation (0715-69000)EACH1$2,209.15$650.00$1,500.00$632.50$1,185.00$1,565.86
0555Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH26$750.00$750.00$1,200.00$1,232.00$1,720.00$974.17
0560Conduit, furnish & install, directional bore (0630-2-12)LF4,272$40.00$60.00$48.00$38.00$39.10$49.96
0565Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI11$12,000$12,000$14,000$10,098$12,450$14,615
0570Signal cable, remove- intersection (0632-7-6)PI7$500.00$750.00$800.00$1,728.00$950.00$1,575.59
0575Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH223$1,750.00$1,000.00$1,700.00$1,399.00$1,422.70$1,033.37
0580Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH11$2,500.00$2,000.00$3,000.00$3,455.50$3,035.00$1,823.60
0585Pull & splice box, install (0635-2-30)EACH11$1,500.00$850.00$1,700.00$1,017.50$1,185.00$729.44
0595Electrical power service, F&I, underground, meter by contractor (0639-1122)AS11$7,000.00$6,000.00$4,800.00$5,592.50$6,165.00$5,207.59
0600Electrical power service, remove overhead (0639-1610)AS8$750.00$560.00$500.00$1,498.50$1,010.00$1,400.52
0605Electrical service wire, & install (0639-2-1)LF2,404$8.00$11.00$10.00$10.00$11.80$8.46
0610Electrical service wire, (0639-2-6)LF650$1.00$0.10$1.00$1.20$1.19$1.82
0615Prestressed concrete pole, type P-II service pole (0641-2-12)EACH11$2,000.00$2,550.00$3,800.00$3,292.50$2,905.00$2,400.74
0620Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH3$750.00$750.00$500.00$1,089.00$1,010.00$1,050.39
0625Aluminum signals pole, (0646-1-11)EACH31$2,000.00$2,210.00$2,000.00$2,985.00$2,350.00$1,394.91
0630Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH8$1,900.00$2,100.00$2,200.00$2,568.00$2,134.00$1,169.11
0635Aluminum signals pole, remove (0646-1-60)EACH15$250.00$600.00$100.00$267.00$237.10$466.84
0640Steel mast arm assembly, and install, single arm 40' (0649-21-3)EACH1$62,000$55,000$50,000$54,737$78,000$68,264
0645Steel mast arm assembly, and install, double arm 40'-30' (0649-21-4)EACH1$79,000$70,000$95,000$69,245$110,800$83,049
0650Steel mast arm assembly, and install, single arm 50' (0649-21-6)EACH1$62,000$65,000$65,000$86,422$88,400$71,960
0655Steel mast arm assembly, and install, double arm 50'-30' (0649-21-7)EACH1$83,000$70,000$100,000$82,309$116,900$88,297
0660Steel mast arm assembly, and install, single arm 60' (0649-21-10)EACH3$75,000$70,000$88,000$66,527$94,250$80,234
0665Steel mast arm assembly, and install, single arm 78' (0649-21-21)EACH1$95,000$82,500$10,000$86,455$111,400$90,783
0670Steel mast arm assembly, remove, shallow foundation- bolt on attachment (0649-26-3)EACH3$5,000.00$3,500.00$4,000.00$4,983.00$4,150.00$10,942
0675Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS33$2,000.00$1,500.00$2,000.00$1,796.00$1,612.00$1,596.03
0680Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH38$350.00$500.00$800.00$558.00$1,010.00$497.59
0685Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS26$1,800.00$750.00$1,300.00$947.50$978.00$962.98
0690Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS9$2,200.00$1,550.00$1,800.00$1,649.50$1,482.00$1,791.17
0695Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS2$250.00$95.00$500.00$179.00$77.00$350.13
0700Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH21$5,500.00$5,050.00$4,500.00$5,065.00$6,285.00$5,422.79
0705Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH21$3,500.00$2,750.00$3,500.00$4,115.50$3,794.00$4,164.44
0710Pedestrian detector, furnish & install, standard (0665-1-11)EACH54$350.00$325.00$800.00$533.50$415.00$572.21
0715Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH7$50.00$95.00$300.00$66.00$60.00$233.42
0720Traffic controller assembly, F&I, caltrans W/standard lock (0670-5180)AS5$50,000$45,000$46,000$48,271$61,650$45,653
0725Traffic controller assembly, remove controller with (0670-5600)AS2$1,500.00$750.00$1,500.00$1,518.00$1,010.00$10,611
0730Cellular modem, furnish and install (0684-8-1)EACH5$2,500.00$1,900.00$5,000.00$4,947.00$5,930.00$1,970.97
0735Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH7$1,200.00$1,050.00$1,000.00$963.50$1,423.00$829.40
0740Sign panel, remove, UP to 12 SF (0700-3601)EACH7$100.00$260.00$400.00$139.50$83.00$175.07
0745Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH6$3,500.00$2,750.00$4,200.00$3,313.50$3,675.00$3,364.58
0750Enhanced highway sign AC powered, F&I overhead blank out sign 12-16 SF (0700-141390)EACH4$9,000.00$6,000.00$15,000$13,837$10,670$12,132
0755Relocate trees and palms, palms, <10.0" DBH, 14.0' or of clear trunk (0581-1272)EACH1$12,000$10,300$4,450.00$6,500.00$5,335.00$6,686.53
FDOT contract T6599: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of July 30, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy