| 0005 | Mobilization (0101-1) | LS | 1 | $482,931 | $1,360,000 | $1,544,500 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $517,000 | $2,524,000 | $1,283,400 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $75,966 | $51,000 | $158,855 |
| 0020 | Traffic control officer (0102-14) | HR | 1,040 | $95.00 | $97.00 | $95.00 |
| 0025 | Work zone sign (0102-60) | ED | 89,465 | $0.21 | $0.30 | $0.25 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 55,555 | $0.10 | $0.16 | $0.15 |
| 0035 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 32,441 | $0.05 | $0.10 | $0.10 |
| 0040 | Arrow board / advance warning arrow panel (0102-76) | ED | 1,013 | $5.00 | $7.60 | $10.00 |
| 0045 | Portable changeable message sign, temporary (0102-99) | ED | 2,557 | $10.00 | $14.00 | $20.00 |
| 0050 | Temporary signalization and maintenance, intersection (0102-104) | ED | 2,280 | $26.00 | $20.00 | $30.00 |
| 0055 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 2,280 | $26.00 | $20.00 | $30.00 |
| 0060 | Type III barricade (0102-115) | ED | 1,904 | $0.35 | $0.34 | $0.25 |
| 0065 | Inlet protection system (0104-18) | EACH | 195 | $100.00 | $200.00 | $165.00 |
| 0070 | Litter removal (0107-1) | ACRE | 310.04 | $25.00 | $54.00 | $100.00 |
| 0075 | Mowing (0107-2) | ACRE | 202.05 | $50.00 | $86.00 | $90.00 |
| 0080 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $19,227 | $300,000 | $917,335 |
| 0085 | Removal of existing concrete (0110-4-10) | SY | 12,519 | $90.00 | $49.00 | $80.00 |
| 0090 | Borrow excavation, truck measure (0120-2-2) | CY | 1.50 | $500.00 | $770.00 | $250.00 |
| 0095 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $5,000.00 | $10,000 | $37,650 |
| 0100 | Optional base, base group 09 (0285-709) | SY | 21 | $945.84 | $400.00 | $485.00 |
| 0105 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 50,184 | $4.55 | $2.50 | $9.50 |
| 0110 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 4,143 | $215.75 | $191.00 | $260.00 |
| 0115 | Miscellaneous asphalt (0339-1) | TN | 104.30 | $550.00 | $408.00 | $555.00 |
| 0120 | Plain cement concrete 9" (0350-3-7) | SY | 415 | $197.00 | $183.00 | $505.00 |
| 0125 | Cleaning & sealing joints- concrete pavement (0350-5) | LF | 211,988 | $4.00 | $4.00 | $2.50 |
| 0130 | Cleaning & sealing random cracks- concrete pavement (0350-6) | LF | 5,599 | $8.00 | $10.70 | $2.50 |
| 0135 | Grinding concrete pavement (0352-70) | SY | 134,972 | $3.53 | $3.60 | $4.75 |
| 0140 | Concrete pavement slab replacement (0353-70) | CY | 2,666.30 | $1,089.00 | $1,050.00 | $1,440.00 |
| 0145 | Manhole, adjust (0425-5) | EACH | 20 | $961.36 | $2,200.00 | $2,500.00 |
| 0150 | Concrete curb & gutter, type E (0520-1-7) | LF | 161 | $66.68 | $46.00 | $95.00 |
| 0155 | Concrete curb & gutter, type F (0520-1-10) | LF | 1,384 | $122.00 | $39.00 | $95.00 |
| 0160 | Concrete curb, type B (0520-2-2) | LF | 8 | $121.72 | $415.00 | $48.00 |
| 0165 | Concrete curb, type D (0520-2-4) | LF | 76 | $106.36 | $66.00 | $100.00 |
| 0170 | Valley gutter- concrete (0520-3) | LF | 83 | $123.56 | $66.00 | $90.00 |
| 0175 | Traffic separator concrete- type I, 6' wide (0520-5-12) | LF | 16 | $249.34 | $153.00 | $250.00 |
| 0180 | Traffic separator - concrete, type II, 4' wide (0520-5-21) | LF | 51 | $223.81 | $157.00 | $250.00 |
| 0185 | Concrete traffic separator, special- variable width (0520-70) | SY | 2 | $346.19 | $141.00 | $500.00 |
| 0190 | Concrete traffic railing- retrofit-post & beam railing (0521-5-11) | EACH | 2 | $7,337.35 | $178.00 | $9,975.00 |
| 0195 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 697 | $117.00 | $62.00 | $155.00 |
| 0200 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 577 | $152.00 | $94.00 | $172.00 |
| 0205 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 27 | $125.43 | $150.00 | $310.00 |
| 0210 | Detectable warnings (0527-2) | SF | 937 | $28.00 | $40.00 | $75.00 |
| 0215 | Guardrail -roadway, general (0536-1-1) | LF | 2,737 | $23.72 | $25.00 | $25.00 |
| 0220 | Special guardrail post- special steel post for concrete structure mount (0536-7-2) | EACH | 25 | $286.38 | $295.00 | $300.00 |
| 0225 | Guardrail transition to rigid barrier, F&I- index 536- 002, approach TL-3 (0536-8122) | EACH | 2 | $2,996.66 | $3,100.00 | $3,500.00 |
| 0230 | Guardrail transition to rigid barrier, F&I- index 536- 002, trailing (0536-8123) | EACH | 2 | $1,674.04 | $1,750.00 | $1,800.00 |
| 0235 | Guardrail removal (0536-73) | LF | 2,298 | $2.00 | $2.10 | $3.00 |
| 0240 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 2 | $1,296.96 | $1,350.00 | $1,500.00 |
| 0245 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 2 | $3,072.44 | $3,400.00 | $3,500.00 |
| 0250 | Performance turf, sod (0570-1-2) | SY | 6,405 | $3.51 | $8.10 | $10.00 |
| 0255 | Conduit, furnish & install, open trench (0630-2-11) | LF | 115 | $28.00 | $72.00 | $30.00 |
| 0260 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 164 | $55.00 | $57.00 | $60.00 |
| 0265 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 6 | $908.00 | $1,450.00 | $1,100.00 |
| 0270 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 13 | $1,903.00 | $2,150.00 | $2,500.00 |
| 0275 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 13 | $1,046.00 | $2,050.00 | $1,500.00 |
| 0280 | Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162) | EACH | 3 | $6,352.00 | $6,650.00 | $7,000.00 |
| 0285 | Traffic monitoring site cabinet, remove existing cabinet (0695-7600) | EACH | 3 | $549.00 | $1,075.00 | $1,000.00 |
| 0290 | Raised pavement marker, type B (0706-1-3) | EACH | 295 | $5.00 | $4.65 | $4.00 |
| 0295 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 4,008 | $2.00 | $1.97 | $1.70 |
| 0300 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 1,888 | $4.00 | $2.20 | $1.90 |
| 0305 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $141,000 | $141,000 | $141,000 |
| 0310 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 312 | $525.00 | $570.00 | $600.00 |
| 0315 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 85 | $2,500.00 | $1,700.00 | $1,600.00 |
| 0320 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 12 | $2,900.00 | $2,250.00 | $2,200.00 |
| 0325 | Single column ground sign assembly, remove (0700-1600) | EACH | 264 | $25.00 | $31.00 | $50.00 |
| 0330 | Single column ground sign assembly, F&I cantilever mount, 12.0-20.0 SF (0700-1912) | EACH | 1 | $4,000.00 | $4,000.00 | $4,000.00 |
| 0335 | Single column ground sign assembly, F&I cantilever mount, 20.1-30.0 SF (0700-1913) | EACH | 6 | $3,400.00 | $4,700.00 | $4,600.00 |
| 0340 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 5 | $7,800.00 | $7,650.00 | $7,500.00 |
| 0345 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 4 | $1,500.00 | $1,150.00 | $1,500.00 |
| 0350 | Sign panel, furnish & install overhead mount, 12-20 SF (0700-3202) | EACH | 1 | $2,500.00 | $1,750.00 | $2,000.00 |
| 0355 | Sign panel, furnish & install overhead mount, 31-50 SF (0700-3204) | EACH | 1 | $3,300.00 | $3,150.00 | $3,500.00 |
| 0360 | Sign panel, furnish & install overhead mount, 101-200 SF (0700-3206) | EACH | 1 | $5,700.00 | $8,400.00 | $9,000.00 |
| 0365 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 36 | $175.00 | $165.00 | $200.00 |
| 0370 | Sign panel, remove, 12-20 SF (0700-3602) | EACH | 1 | $125.00 | $52.00 | $100.00 |
| 0375 | Sign panel, remove, 31-50 SF (0700-3604) | EACH | 1 | $150.00 | $207.00 | $300.00 |
| 0380 | Sign panel, remove, 51-100 SF (0700-3605) | EACH | 1 | $175.00 | $1,250.00 | $1,500.00 |
| 0385 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 124 | $100.00 | $135.00 | $130.00 |
| 0390 | Tubular marker, 36" white post (0704-1-3) | EACH | 20 | $225.00 | $217.00 | $250.00 |
| 0395 | Tubular marker, 36" yellow (0704-1-4) | EACH | 52 | $225.00 | $217.00 | $250.00 |
| 0400 | Object marker, type 1 (0705-10-1) | EACH | 29 | $300.00 | $336.00 | $350.00 |
| 0405 | Object marker, type 4 (0705-10-4) | EACH | 3 | $300.00 | $243.00 | $250.00 |
| 0410 | Raised pavement marker, type B (0706-1-3) | EACH | 3,621 | $5.00 | $4.65 | $4.00 |
| 0415 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 1,882 | $10.00 | $4.65 | $4.00 |
| 0420 | Painted pavement markings, surface (0710-90) | LS | 1 | $50,000 | $29,700 | $35,750 |
| 0425 | Thermoplastic, standard, solid, 12" for interchange markings (0711-11103) | GM | 0.21 | $11,776 | $11,000 | $9,500.00 |
| 0430 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 2,323 | $5.00 | $3.75 | $4.00 |
| 0435 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 587 | $7.00 | $5.60 | $5.00 |
| 0440 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 1,148 | $9.00 | $7.45 | $6.50 |
| 0445 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.06 | $3,947.37 | $2,550.00 | $3,000.00 |
| 0450 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 2 | $300.00 | $83.00 | $75.00 |
| 0455 | Thermoplastic, standard, arrow (0711-11170) | EACH | 14 | $90.00 | $65.00 | $60.00 |
| 0460 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 246 | $7.00 | $5.20 | $4.50 |
| 0465 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.04 | $3,461.54 | $2,210.00 | $2,000.00 |
| 0470 | Thermoplastic, preformed, white, solid, 12" for crosswalk (0711-14123) | LF | 53 | $12.00 | $9.50 | $9.00 |
| 0475 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 2,173 | $16.00 | $19.00 | $17.00 |
| 0480 | Thermoplastic, preformed, white, 2-4 dotted guideline on concrete surfaces (0711-14141) | GM | 0.95 | $14,921 | $9,400.00 | $8,500.00 |
| 0485 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 36 | $500.00 | $322.00 | $300.00 |
| 0490 | Thermoplastic, preformed, yellow, 2-4 dotted guideline on concrete surfaces (0711-14241) | GM | 0.43 | $14,754 | $9,300.00 | $8,500.00 |
| 0495 | Thermoplastic, preformed, black, 2-4 dotted guideline on concrete surfaces (0711-14341) | GM | 0.94 | $14,968 | $9,450.00 | $8,500.00 |
| 0500 | Thermoplastic, preformed, 24" white with 4" black contrast crosswalk on concrete pavement, 32" (0711-14526) | LF | 3,524 | $24.00 | $25.50 | $23.00 |
| 0505 | Thermoplastic, preformed, 24" white with 4" black contrast stop line on concrete 32" (0711-14527) | LF | 866 | $24.00 | $25.50 | $23.00 |
| 0510 | Thermoplastic, preformed, 12" white with 4" black contrast crosswalk on concrete pavement, 20" (0711-14528) | LF | 4,605 | $15.00 | $15.90 | $14.00 |
| 0515 | Thermoplastic, preformed, white with black contrast on concrete pavement, message symbol (0711-14560) | EACH | 37 | $1,000.00 | $910.00 | $800.00 |
| 0520 | Thermoplastic, preformed, white with black contrast, arrow on concrete surface (0711-14570) | EACH | 193 | $800.00 | $605.00 | $530.00 |
| 0525 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 4.00 | $5,998.50 | $5,500.00 | $5,000.00 |
| 0530 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.16 | $6,290.32 | $7,100.00 | $6,500.00 |
| 0535 | Thermoplastic, standard other surfaces, white, 6", 6-10 dotted managed lane marking (0711-16171) | GM | 0.07 | $4,436.62 | $2,850.00 | $3,000.00 |
| 0540 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 8.98 | $5,998.00 | $5,200.00 | $5,000.00 |
| 0545 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.21 | $31,068 | $32,100 | $30,000 |
| 0550 | Permanent tape, white, solid W/contrast, 6" primary line width, for concrete surfaces (0713-103121) | GM | 7.47 | $39,957 | $53,400 | $46,500 |
| 0555 | Permanent tape, white, solid W/contrast, 8" primary line width, for concrete surfaces (0713-103122) | GM | 0.51 | $49,805 | $71,000 | $62,000 |
| 0560 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 6.61 | $9,995.46 | $8,300.00 | $7,500.00 |
| 0565 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.21 | $31,068 | $32,100 | $28,000 |
| 0570 | Permanent tape, yellow, 6-10 dotted extension, 6" wide, for concrete surfaces (0713-103241) | GM | 0.56 | $9,982.17 | $12,400 | $11,000 |
| 0575 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 6.55 | $10,000 | $8,300.00 | $7,200.00 |
| 0580 | Itsfm location documentation- intersection (0611-2-1) | EACH | 6 | $2,524.00 | $407.00 | $3,000.00 |
| 0585 | Conduit, furnish & install, open trench (0630-2-11) | LF | 366 | $28.00 | $70.00 | $30.00 |
| 0590 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 2,147 | $55.00 | $53.00 | $60.00 |
| 0595 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 6 | $6,084.00 | $8,450.00 | $7,000.00 |
| 0600 | Signal cable, remove- intersection (0632-7-6) | PI | 6 | $3,245.00 | $1,620.00 | $3,500.00 |
| 0605 | Fiber optic cable locator (0633-6) | DA | 380 | $330.00 | $400.00 | $275.00 |
| 0610 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 54 | $908.00 | $1,450.00 | $1,100.00 |
| 0615 | Aluminum signals pole, (0646-1-11) | EACH | 34 | $3,172.00 | $3,100.00 | $3,200.00 |
| 0620 | Aluminum signals pole, remove (0646-1-60) | EACH | 16 | $874.00 | $895.00 | $900.00 |
| 0625 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 1 | $1,760.63 | $2,320.00 | $2,975.00 |
| 0630 | Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16) | AS | 1 | $2,430.00 | $2,750.00 | $4,518.10 |
| 0635 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 1 | $524.00 | $358.00 | $975.00 |
| 0640 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 34 | $976.00 | $1,070.00 | $1,200.00 |
| 0645 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 14 | $137.00 | $475.00 | $200.00 |
| 0650 | Loop detector inductive, remove- cabinet to remain (0660-1600) | EACH | 8 | $69.00 | $22.50 | $100.00 |
| 0655 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 6 | $27,426 | $33,500 | $28,000 |
| 0660 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 8 | $5,553.00 | $8,800.00 | $6,000.00 |
| 0665 | Vehicle detection system- remove (0660-4-60) | EACH | 2 | $1,965.00 | $1,450.00 | $2,500.00 |
| 0670 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 34 | $437.00 | $540.00 | $500.00 |
| 0675 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 14 | $69.00 | $218.00 | $100.00 |
| 0680 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 10 | $250.00 | $189.00 | $410.00 |
| 0685 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 38 | $50.00 | $129.00 | $150.00 |