FDOT contract T7564 bid tabulation

SR 60 FROM E OF BUCKINGHAM PLACE TO E OF LITHIA PINECREST RD. Let by Florida DOT on June 11, 2025, Hillsborough, District 7. 5 bids received; low bid $3,729,122 by Hubbard Construction Company.

Owner
Florida DOT
Letting
11 JUN 2025
Pay items
119
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Hubbard Construction Company$3,729,122Low
2C.W. Roberts Contracting, Inc.$3,754,002+1.0%
3Preferred Materials Inc.$3,807,053+2.0%
4Ajax Paving Industries of Florida LLC$4,294,903+15%
5Pigott Asphalt and Sitework LLC$4,814,234+29%
FDOT contract T7564: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Hubbard Construction Company2. C.W. Roberts Contracting, Inc.3. Preferred Materials Inc.4. Ajax Paving Industries of Florida LLC5. Pigott Asphalt and Sitework LLC
0005Mobilization (0101-1)LS1$156,495$264,135$280,354$429,533$525,569
0010Mobilization (0101-1)LS1$67,000$57,944$117,883$42,953$250,000
0015Maintenance of traffic (0102-1)DA1$239,800$212,029$56,653$419,510$297,000
0020Maintenance of traffic (0102-1)DA1$100,000$46,543$257,512$41,951$96,000
0025Traffic control officer (0102-14)HR296$108.78$94.87$92.74$116.75$100.00
0030Work zone sign (0102-60)ED9,812$0.29$0.35$0.24$0.34$0.30
0035Business sign (0102-61)EACH3$75.56$72.39$49.10$26.69$250.00
0040Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED14,902$0.16$0.14$0.10$0.13$0.05
0045Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD1,488$0.12$0.13$0.09$0.12$1.00
0050Portable changeable message sign, temporary (0102-99)ED360$13.95$16.09$10.91$11.95$20.00
0055Temporary signalization and maintenance, intersection (0102-104)ED540$31.23$8.91$29.46$30.02$35.00
0060Temporary traffic detection and maintenance, intersection (0102-107-1)ED540$1.16$26.90$1.09$1.11$75.00
0065Sediment barrier (0104-10-3)LF5,900$0.95$2.50$2.44$3.34$3.00
0070Inlet protection system (0104-18)EACH61$91.61$138.40$152.56$133.43$200.00
0075Litter removal (0107-1)ACRE94.77$137.41$128.36$185.48$83.40$10.00
0080Mowing (0107-2)ACRE19.06$515.28$318.10$927.40$277.99$150.00
0085Clearing & grubbing (0110-1-1)ACRE1$54,301$27,299$183,936$51,601$139,000
0090Removal of existing concrete (0110-4-10)SY847$83.74$46.01$61.00$104.96$65.00
0095Regular excavation (0120-1)CY84.50$133.35$123.08$72.69$352.69$250.00
0100Embankment (0120-6)CY511.60$71.12$119.97$118.29$140.43$40.00
0105Type B stabilization (0160-4)SY245$33.70$30.65$66.98$55.21$25.00
0110Optional base, base group 03 (0285-703)SY222$34.46$34.81$86.24$58.72$50.00
0115Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2)SY12,551$4.90$4.03$5.99$6.78$7.25
0120Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY35,414$3.46$3.30$4.10$5.74$5.10
0125Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY3,771$13.55$13.75$8.45$11.09$12.25
0130Superpave asphaltic conc, traffic E (0334-1-15)TN4,463.90$146.33$146.36$138.08$155.09$200.00
0135Asphalt concrete friction course,traffic E, FC-12.5, PG (0337-7-88)TN4,156.40$175.41$164.48$178.82$206.24$210.00
0140Inlets, curb, type P-2, partial (0425-1325)EACH1$21,249$7,451.56$10,160$11,285$8,500.00
0145Inlets, curb, type P-5, partial (0425-1355)EACH1$12,395$9,439.53$9,028.73$12,178$9,500.00
0150Inlets, ditch bottom, type C, partial (0425-1525)EACH1$14,166$7,852.49$7,711.33$4,825.81$8,000.00
0155Inlets, closed flume (0425-1910)EACH2$23,610$3,352.77$7,819.28$6,575.29$10,000
0160Manhole, adjust (0425-5)EACH6$925.16$285.71$1,406.36$1,939.30$3,500.00
0165Manhole, adjust, utilities (0425-5-1)EACH8$925.04$285.71$1,757.93$1,998.78$3,000.00
0170Valve boxes, adjust (0425-6)EACH25$529.24$251.19$749.88$447.35$1,800.00
0175Concrete curb & gutter, type E (0520-1-7)LF1,082$112.21$141.52$45.04$75.62$50.00
0180Concrete curb & gutter, type F (0520-1-10)LF902$111.45$138.83$45.72$88.97$50.00
0185Traffic separator concrete- type I, 4' wide (0520-5-11)LF161$145.68$147.87$95.69$128.42$125.00
0190Concrete traffic separator, special- variable width (0520-70)SY174$272.00$277.09$138.78$179.14$125.00
0195Concrete sidewalk and driveways, 4" thick (0522-1)SY170$199.34$224.21$92.88$122.19$85.00
0200Concrete sidewalk and driveways, 6" thick (0522-2)SY51$260.79$284.03$141.99$199.64$150.00
0205Concrete ditch pavt, non reinforced, 3" (0524-1-1)SY24$259.59$319.47$101.35$190.96$125.00
0210Concrete ditch pavement, non reinforced, 4" (0524-1-2)SY27$268.22$320.48$127.65$177.37$165.00
0215Detectable warnings (0527-2)SF136$35.97$34.88$32.08$24.70$40.00
0220Performance turf, sod (0570-1-2)SY2,457$5.51$5.02$7.70$11.49$4.00
0225Conduit, furnish & install, directional bore (0630-2-12)LF397$39.33$61.44$37.10$37.81$50.00
0230Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH3$1,387.97$1,730.69$1,309.27$1,334.34$1,500.00
0235Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH6$3,325.35$2,288.03$3,136.78$3,196.85$3,000.00
0240Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH6$2,203.41$2,669.94$2,078.46$2,118.26$2,500.00
0245Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132)EACH1$8,576.52$7,895.87$8,090.17$8,245.10$7,500.00
0250Traffic monitoring site cabinet, remove existing cabinet (0695-7600)EACH1$1,220.25$588.19$1,151.06$1,173.11$1,500.00
0255Painted pavement markings, standard, white, solid, 6" (0710-11101)GM3.48$2,076.57$1,507.22$1,958.82$2,001.51$2,500.00
0260Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF2,749$1.97$1.28$1.85$1.89$4.00
0265Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF297$2.08$2.18$1.96$2.00$5.00
0270Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF2,948$2.20$2.23$2.07$2.11$5.50
0275Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM3.16$577.77$872.52$545.01$555.97$1,600.00
0280Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.26$748.93$889.50$706.44$722.77$2,000.00
0285Painted pavement markings, standard, white, message or symbol (0710-11160)EACH4$52.05$72.55$49.10$50.04$100.00
0290Painted pavement markings, standard, white, arrows (0710-11170)EACH116$46.27$39.06$43.64$44.48$50.00
0295Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM1.79$2,077.32$1,559.11$1,959.52$2,001.51$2,500.00
0300Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.18$718.03$948.09$677.30$722.77$2,500.00
0305Initial contingency amount, DO not bid (0999-25)LS1$40,000$40,000$40,000$40,000$40,000
0310Initial contingency amount, DO not bid (0999-25)LS1$10,000$10,000$10,000$10,000$10,000
0315Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH33$751.82$502.26$709.19$722.77$565.00
0320Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH19$231.33$1,730.02$2,182.11$222.39$2,000.00
0325Single column ground sign assembly, relocate (0700-1500)EACH1$289.17$390.64$272.77$277.99$1,000.00
0330Single column ground sign assembly, remove (0700-1600)EACH25$86.75$50.23$81.83$83.40$100.00
0335Single column ground sign assembly, F&I cantilever mount, 20.1-30.0 SF (0700-1913)EACH3$3,469.93$1,674.21$3,273.16$3,335.85$5,000.00
0340Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113)EACH1$12,145$7,143.29$11,456$11,675$10,000
0345Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH32$375.91$245.55$354.59$361.38$350.00
0350Sign panel, furnish & install ground mount, 12-20 SF (0700-3102)EACH8$636.15$558.07$600.08$611.57$600.00
0355Sign panel, remove, UP to 12 SF (0700-3601)EACH29$57.83$50.23$54.55$55.60$50.00
0360Sign panel, remove, 12-20 SF (0700-3602)EACH7$86.75$94.87$81.83$83.40$100.00
0365Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH45$138.80$104.92$130.93$133.43$150.00
0370Tubular marker, 36" white post (0704-1-3)EACH4$231.33$200.91$218.21$222.39$250.00
0375Tubular marker, 36" yellow (0704-1-4)EACH11$231.33$212.07$218.21$222.39$250.00
0380Raised pavement marker, type B (0706-1-3)EACH1,776$4.63$4.46$4.36$4.45$5.00
0385Painted pavement markings, standard, white, island nose (0710-11190)SF6$4.63$4.47$4.36$4.45$100.00
0390Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF64$5.78$4.46$5.46$5.56$10.00
0395Painted pavement markings, surface (0710-90)LS1$30,040$26,787$28,337$28,880$50,000
0400Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF2,749$3.47$3.35$3.27$3.34$6.00
0405Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF297$5.20$4.69$4.91$5.00$7.00
0410Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF620$6.94$7.09$6.55$6.67$8.00
0415Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.26$2,707.70$2,724.06$2,554.18$2,613.08$5,000.00
0420Thermoplastic, standard, message or symbol (0711-11160)EACH4$73.10$178.58$68.96$70.28$250.00
0425Thermoplastic, standard, arrow (0711-11170)EACH116$70.56$87.06$66.55$67.83$100.00
0430Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.18$2,595.96$3,103.88$2,448.71$2,613.08$5,000.00
0435Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF2,328$17.47$17.63$16.47$16.79$12.00
0440Thermoplastic, preformed, white, message (0711-14160)EACH1$318.08$267.88$300.04$27.80$500.00
0445Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM3.48$5,658.66$5,973.06$5,337.78$5,454.11$7,500.00
0450Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.17$7,291.02$7,261.63$6,877.59$7,272.15$10,000
0455Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM3.16$1,417.85$2,125.36$1,337.45$1,364.36$5,000.00
0460Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM1.79$5,201.37$5,958.03$4,906.42$5,011.56$7,500.00
0465Conduit, furnish & install, open trench (0630-2-11)LF65$15.04$47.74$14.18$14.46$50.00
0470Conduit, furnish & install, directional bore (0630-2-12)LF405$36.43$37.10$34.37$35.03$50.00
0475Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH7$2,492.57$2,378.64$2,351.22$2,396.25$1,500.00
0480Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF1,914$3.18$2.68$3.00$3.06$2.00
0485Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 12' arm length (0715-61442)EACH2$13,486$13,779$12,722$12,965$10,000
0490Light pole complete, F&I, utility conflict pole standard foundation, 40' mounting height, 16' arm length (0715-65366)EACH2$12,839$14,607$12,111$12,343$10,000
0495Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH4$1,052.55$835.65$992.86$1,011.87$1,000.00
0500Itsfm subsurface documentation- project length (0611-1-1)MI0.92$1,901.81$2,385.81$1,793.96$1,830.31$5,000.00
0505Conduit, furnish & install, open trench (0630-2-11)LF279$16.19$61.13$15.27$15.57$30.00
0510Conduit, furnish & install, directional bore (0630-2-12)LF1,172$34.70$51.00$32.73$33.36$40.00
0515Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI3$9,970.27$3,973.04$9,404.89$9,585.00$6,000.00
0520Fiber optic cable locator (0633-6)DA180$237.11$518.05$223.67$227.95$50.00
0525Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH26$2,116.66$2,071.79$1,996.63$2,034.87$2,000.00
0530Aluminum signals pole, (0646-1-11)EACH3$2,851.13$2,989.88$2,689.45$2,740.96$3,500.00
0535Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH4$2,428.96$1,943.88$2,291.22$2,335.09$1,600.00
0540Aluminum signals pole, remove (0646-1-60)EACH2$341.21$588.19$321.86$328.03$1,000.00
0545Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH6$717.12$895.19$676.45$689.41$700.00
0550Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS3$1,023.63$1,036.02$965.58$984.08$1,200.00
0555Loop assembly, F&I, type B (0660-2102)AS12$1,526.77$1,570.75$1,440.19$1,467.77$1,600.00
0560Loop assembly, F&I, type F (0660-2106)AS12$1,411.11$2,205.03$1,331.09$1,356.58$1,750.00
0565Pedestrian detector, furnish & install, standard (0665-1-11)EACH2$329.65$673.55$310.95$316.91$750.00
0570Pedestrian detector, furnish & install, accessible (0665-1-12)EACH6$3,098.65$3,103.92$2,922.94$2,978.91$2,500.00
0575Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH5$172.34$98.03$162.57$165.68$100.00
0580Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH2$907.97$861.16$856.48$872.88$1,800.00
0585Sign panel, remove, UP to 12 SF (0700-3601)EACH2$115.67$98.03$109.11$111.19$150.00
0590Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH10$4,765.37$7,413.52$4,495.14$4,581.23$7,000.00
0595Internally illuminated sign, remove (0700-5-60)EACH10$346.99$588.19$327.32$333.58$500.00
FDOT contract T7564: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of June 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy