FDOT contract T7565 bid tabulation

SR 686 FROM W OF BELCHER RD TO E OF US 19. Let by Florida DOT on February 26, 2025, Pinellas, District 7. 4 bids received; low bid $7,978,009 by Hubbard Construction Company.

Owner
Florida DOT
Letting
26 FEB 2025
Pay items
128
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Hubbard Construction Company$7,978,009Low
2Watson Civil Construction, Inc.$8,367,239+5.0%
3Preferred Materials Inc.$8,429,266+6.0%
4Ajax Paving Industries of Florida LLC$8,474,320+6.0%
FDOT contract T7565: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Hubbard Construction Company2. Watson Civil Construction, Inc.3. Preferred Materials Inc.4. Ajax Paving Industries of Florida LLC
0005Mobilization (0101-1)LS1$284,363$830,000$802,510$421,000
0010Maintenance of traffic (0102-1)DA1$664,734$1,450,500$588,777$835,000
0015Pedestrian or bicycle special detour (0102-4-1)SY1$53,801$56,000$35,361$135,827
0020Traffic control officer (0102-14)HR1,240$100.45$95.00$98.46$100.44
0025Work zone sign (0102-60)ED150,900$0.21$0.33$0.23$0.19
0030Temporary barrier, F&I, low profile, concrete (0102-71-13)LF1,680$36.35$33.00$18.00$37.81
0035Temporary barrier, relocate, low profile concrete (0102-71-23)LF5,208$18.18$17.00$9.00$18.91
0040Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED50,700$0.10$0.16$0.12$0.09
0045Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD19,180$0.04$0.15$0.12$0.05
0050Arrow board / advance warning arrow panel (0102-76)ED1,042$5.58$7.80$5.79$5.00
0055Portable changeable message sign, temporary (0102-99)ED2,052$10.04$16.00$11.58$9.00
0060Temporary signalization and maintenance, intersection (0102-104)ED1,272$5.96$45.00$6.00$42.60
0065Temporary traffic detection and maintenance, intersection (0102-107-1)ED1,272$24.32$45.00$24.49$36.51
0070Type III barricade (0102-115)ED6,330$0.26$0.45$0.32$0.23
0075Removable tape, white, solid 6" (0102-913-21)GM4.10$12,401$10,500$11,913$12,152
0080Removable tape, white, 10'-30', 6'-10', or 2'-4' skip, 6" wide (0102-913-22)GM0.04$3,468.97$2,050.00$3,054.62$3,037.93
0085Removable tape, white, 24" stop bar (0102-913-23)LF22$16.91$15.40$17.38$17.72
0090Removable tape, white, 12" crosswalk (0102-913-24)LF84$11.27$7.70$8.69$8.86
0095Removable tape, white, symbol or arrow (0102-913-29)EACH4$208.56$367.00$415.87$424.20
0100Removable tape, yellow, solid, (0102-913-31)GM3.22$12,401$10,700$11,913$12,152
0105Inlet protection system (0104-18)EACH68$139.10$223.00$191.30$138.48
0110Litter removal (0107-1)ACRE7.59$1,820.38$57.00$1,861.04$275.40
0115Mowing (0107-2)ACRE6.27$2,287.21$76.00$2,338.29$333.38
0120Clearing & grubbing (0110-1-1)ACRE1$50,347$510,000$383,489$121,537
0125Removal of existing concrete (0110-4-10)SY2,680$61.27$41.00$86.39$65.44
0130Tree root and branch pruning (0110-22)EACH2$1,339.32$3,000.00$3,263.05$2,363.23
0135Borrow excavation, truck measure (0120-2-2)CY24.50$84.84$340.00$365.48$339.61
0140Regular excavation (3-R projects only) (0120-71)LS1$6,235.51$40,000$40,295$71,099
0145Optional base, base group 15 (0285-715)SY871$94.60$121.00$288.16$373.37
0150Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2)SY9,179$7.11$3.90$5.54$7.17
0155Milling existing asphalt pavement, 4 1/2" avg depth (0327-70-3)SY62,043$10.31$4.10$5.11$8.63
0160Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN11,492.60$183.45$156.00$188.09$189.90
0165Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN5,921$193.98$179.00$205.22$193.38
0170Manhole, adjust (0425-5)EACH24$149.98$1,900.00$2,219.70$861.21
0175Pipe handrail - guiderail, aluminum (0515-1-2)LF19$117.48$180.00$227.50$147.70
0180Concrete curb & gutter, type E (0520-1-7)LF369$104.60$74.00$71.25$79.91
0185Concrete curb & gutter, type F (0520-1-10)LF995$104.60$65.00$72.79$73.01
0190Concrete curb, type B (0520-2-2)LF151$104.60$91.00$82.05$71.04
0195Traffic separator concrete- type I, 4' wide (0520-5-11)LF2,230$187.83$78.00$98.68$86.76
0200Concrete traffic separator, special- variable width (0520-70)SY85$369.76$130.00$168.99$229.98
0205Concrete sidewalk and driveways, 4" thick (0522-1)SY249$178.40$64.00$127.33$122.42
0210Concrete sidewalk and driveways, 6" thick (0522-2)SY585$237.77$79.00$167.47$184.03
0215Detectable warnings (0527-2)SF399$35.06$41.00$34.06$24.81
0220Performance turf, sod (0570-1-2)SY152$32.08$34.00$11.69$32.38
0225Conduit, furnish & install, directional bore (0630-2-12)LF393$64.63$44.00$65.07$35.29
0230Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH5$1,587.86$1,400.00$1,598.60$1,849.94
0235Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH12$2,133.68$2,270.00$2,148.11$3,365.18
0240Traffic monitoring site speed/classification unit, furnish & install, volume speed and classification (0695-3-11)AS2$14,558$8,900.00$14,657$15,213
0245Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH12$2,120.97$2,420.00$2,135.31$3,651.19
0250Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132)EACH2$7,644.38$10,300$7,696.09$8,426.71
0255Painted pavement markings, standard, white, solid, 6" (0710-11101)GM3.96$1,097.52$1,790.00$2,024.13$2,067.83
0260Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.08$1,229.87$2,170.00$2,810.26$2,759.07
0265Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF3,343$1.13$1.65$1.85$1.89
0270Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF3,442$2.25$1.85$2.09$2.13
0275Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM3.76$563.09$505.00$572.80$584.90
0280Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM1.16$675.85$714.00$810.18$827.13
0285Painted pavement markings, standard, white, message or symbol (0710-11160)EACH30$56.37$36.00$40.54$41.36
0290Painted pavement markings, standard, white, arrows (0710-11170)EACH136$28.18$36.00$40.54$41.36
0295Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM2.13$1,097.13$1,790.00$2,023.40$2,067.83
0300Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF8$2.25$1.75$1.97$2.01
0305Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.40$674.74$713.00$808.85$827.13
0310Initial contingency amount, DO not bid (0999-25)LS1$81,932$81,932$81,932$81,932
0315Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80)EACH4$23,588$10,300$23,747$10,680
0320Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH37$591.87$405.00$608.16$620.35
0325Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH6$1,352.85$1,830.00$1,390.08$1,417.94
0330Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH2$2,367.48$1,900.00$2,432.64$2,481.39
0335Single column ground sign assembly, relocate (0700-1500)EACH2$225.47$360.00$231.68$236.32
0340Single column ground sign assembly, remove (0700-1600)EACH32$39.46$52.00$40.54$41.36
0345Single column ground sign assembly, F&I cantilever mount, 12.0-20.0 SF (0700-1912)EACH4$3,043.91$3,200.00$3,127.68$3,190.36
0350Sign panel, furnish & install overhead mount, 101-200 SF (0700-3206)EACH2$10,146$10,795$10,426$10,635
0355Sign panel, relocate, UP to 12 SF (0700-3501)EACH4$112.74$129.00$115.84$118.16
0360Sign panel, remove, 12-20 SF (0700-3602)EACH2$28.20$103.00$28.96$29.54
0365Sign panel, remove, 101-200 SF (0700-3606)EACH2$563.69$514.00$579.20$590.81
0370Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH10$112.74$78.00$115.84$118.16
0375Tubular marker, 36" white post (0704-1-3)EACH5$197.29$232.00$202.72$206.78
0380Tubular marker, 36" yellow (0704-1-4)EACH6$197.29$211.00$202.72$206.78
0385Object marker, type 4 (0705-10-4)EACH2$169.11$1,300.00$173.76$177.24
0390Raised pavement marker, type B (0706-1-3)EACH1,496$5.64$4.00$4.52$4.61
0395Painted pavement markings, standard, white, island nose (0710-11190)SF8$3.38$4.10$4.63$4.73
0400Painted pavement markings, standard, yellow, island nose (0710-11290)SF66$3.38$4.10$4.63$4.73
0405Painted pavement markings, surface (0710-90)LS1$67,642$29,000$33,148$33,812
0410Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF3,343$4.51$3.30$3.71$3.78
0415Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF697$6.76$6.55$7.41$7.56
0420Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM1.16$3,379.20$2,300.00$2,604.15$2,658.63
0425Thermoplastic, standard, arrow (0711-11170)EACH106$84.55$58.50$66.03$67.35
0430Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF178$5.64$4.95$5.56$5.67
0435Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.40$3,373.67$2,300.00$2,599.90$2,658.63
0440Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF2,748$16.07$17.00$19.11$19.50
0445Thermoplastic, preformed, white, message (0711-14160)EACH30$253.66$213.00$240.95$245.78
0450Thermoplastic, preformed, white, arrow (0711-14170)EACH30$169.11$90.00$101.94$103.98
0455Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM3.97$6,750.60$4,780.00$5,396.51$5,515.78
0460Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.08$7,082.18$5,705.00$7,394.74$7,354.37
0465Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM3.76$2,139.73$1,200.00$1,350.42$1,378.95
0470Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM2.29$6,746.48$4,500.00$5,054.70$5,169.57
0475Conduit, furnish & install, directional bore (0630-2-12)LF486$83.11$34.00$83.67$35.29
0480Conduit, furnish & install, mount (0630-2-15)LF100$52.86$51.00$53.22$80.33
0485Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH8$1,020.25$1,400.00$1,027.15$1,849.94
0490Pull & splice box, install (0635-2-30)EACH1$839.13$1,200.00$844.80$2,434.13
0495Junction box, furnish & install, mounted (0635-3-12)EACH4$394.95$640.00$397.62$1,064.93
0500Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$3,571.06$5,005.00$3,595.23$5,476.79
0505Electrical service wire, & install (0639-2-1)LF208$16.42$12.50$16.53$12.17
0510Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$3,628.76$2,900.00$3,653.30$3,158.28
0515Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF3,027$2.21$3.50$2.22$3.04
0520Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF6,018$0.47$0.22$0.47$0.91
0525Load center, F&I, secondary voltage (0715-7-11)EACH1$26,233$19,750$26,411$18,743
0530Load center, remove, voltage (0715-7-41)EACH1$3,405.70$900.00$3,428.74$1,217.06
0535Luminaire, F&I, under deck, wall mount (0715-11125)EACH4$1,160.24$1,125.00$1,168.09$1,442.22
0540Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH5$1,941.98$1,700.00$1,955.11$1,929.05
0545Luminaire, remove (0715-11500)EACH8$189.21$225.00$190.49$304.27
0550Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH9$806.43$790.00$811.89$1,034.50
0555Pole cable distribution system, wall mount (0715-500-3)EACH4$724.13$715.00$729.03$1,004.08
0560Light pole complete- special design, F&I, single arm shoulder mount, aluminum, 20' (0715-511120)EACH4$15,609$11,800$15,715$12,313
0565Conduit, furnish & install, open trench (0630-2-11)LF381$53.04$29.00$53.40$14.60
0570Conduit, furnish & install, directional bore (0630-2-12)LF1,045$52.42$35.00$52.78$42.60
0575Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI3$9,056.76$8,700.00$9,118.01$14,605
0580Signal cable, remove- intersection (0632-7-6)PI3$1,135.23$900.00$1,142.91$1,825.60
0585Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH50$1,711.31$1,250.00$1,722.89$1,874.28
0590Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH20$1,896.48$2,320.00$1,909.31$3,553.83
0595Aluminum signals pole, remove (0646-1-60)EACH11$756.82$675.00$761.94$973.65
0600Loop assembly, F&I, type F (0660-2106)AS52$2,142.89$1,800.00$2,157.38$2,335.55
0605Vehicle detection system- adjust/modify above ground equipment (0660-4-52)EACH12$1,925.13$935.00$1,938.15$2,677.54
0610Vehicle detection system- avi, bluetooth, furnish & install, cabinet equipment (0660-6121)EACH3$3,674.91$3,000.00$3,699.77$4,266.90
0615Vehicle detection system- avi, bluetooth, furnish & install, above ground equipment (0660-6122)EACH3$11,021$9,155.00$11,095$11,916
0620Pedestrian detector, furnish & install, accessible (0665-1-12)EACH24$571.85$1,820.00$575.71$2,409.36
0625Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH13$94.60$113.00$95.24$182.56
0630Traffic controller, modify (0671-2-40)EACH4$2,172.02$7,800.00$2,186.71$5,476.79
0635Sign panel, remove, UP to 12 SF (0700-3601)EACH12$756.82$225.00$761.94$547.68
0640Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH12$8,731.00$3,620.00$8,790.06$7,163.64
FDOT contract T7565: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of February 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy